36C26125N0436 459-24-001 Modernize Generator System VAMC Honolulu - 030-EP-012 Addendum 1. pdf.pdf

PDF 1 MB Posted

Attached to
Z2DZ--Modernize Generator Project
Solicitation number
36C26126R00310005
Issued by

About this file

This document is a construction drawing set for the modernization of emergency generators at the Honolulu Veterans Affairs Medical Center, located at 1 Jarrett White Road, Honolulu, Hawaii 96819. The project, identified as 459-24-001 and drawing number 030-EP-012, involves enlarging electrical plans for Building 30 and covers both Phase 1 and Phase 2 installation sequences for generator and fuel tank systems.

The work requires installation of a new 1200A, 480V, 3-phase switchboard interior with matching main circuit breaker and new branch breakers to feed existing circuits. The contractor must provide a new generator control panel, new quick connect enclosure for 1200A load bank testing, and a new 316 stainless steel electrical enclosure to house fuel monitoring wiring and a 208V panel. All existing generator equipment must be relocated or temporarily removed to accommodate a 2-hour fire-rated wall reinforcement. The generator manufacturer basis of design is Caterpillar, with all work on existing generators to be performed by local authorized dealer Hawthorn Cat to maintain UL listing. Temporary power systems must be operational prior to construction, with all generator-related work, testing, commissioning, and transfer switch operations performed after normal business hours. The contractor must submit a temporary generator location request within seven days of Notice to Proceed for VA consideration with USAG, and submit full design details for the switchboard enclosure retrofit and main fuel tank enclosure for approval prior to construction.

View the file

Other files

File Type Posted
000-EJ-002 - Addendum No 01 - Stamped.pdf PDF
36C26126R0031 0005.pdf PDF
030-EP-011 - Addendum No 01 - Stamped.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

C B

J J

J J

PROJECT KEY PLAN

HONOLULU VETERANS AFFAIRS

1 JARRETT WHITE RD | HONOLULU, HI 96819

E

(N) ELECTRICAL ENCLOSURE(N) FUEL PUMP

000-EJ-001

24 25

SWBD 'GENERATOR'

000-EJ-001

(1) 2"C VEEDER ROOT FEEDER

(1) 2"C PUMP FEEDER

(1) 2"C SPARE

(R) ATS-FP

(1)1"C.

SEE CONTINUATION ON

SHEET 030-EP-011

SEE CONTINUATION ON

SHEET 030-EP-011

(3) 2"C.

(2) 2"C.

30-DT-1

30-TM-1

(R) EXIT SIGN 12

F A

MECH/FIRE

PROTECT. ROOM

1A29

EMERGENCY

GENERATOR

1A28

(X) FUEL MONITORING

CONTROL PANEL

(X) DAYTANK

(R) ATS-FP

2(E) SWBD 'GENERATOR'3

(R) EXIT SIGN10

F A

EMERGENCY

GENERATOR

1A28

MECH/FIRE

PROTECT. ROOM

1A29

PROJECT NO.

BUILDING NO.

DRAWING NO.

PROJECT TITLE

FLS

ISSUE DATE CHECKED BY DRAWN BY

DRAWING TITLE

APPROVED:

VA FORM 08 - 6231

A

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

PHASEARCHITECT/ENGINEER OF RECORD

321 4 5 6 7 8 9 10

STAMP

LOCATION

''1

CONSULTANT

CONSULTANT: A/E:

GDM-AE, INC.

1308 NE 134TH ST SUITE A

VANCOUVER, WA 98685

P: 541.436.4723

MICHAEL REBSTOCK, PE

WWW.GDM-AE.COM

FULLY

SPRINKLERED

CONSTRUCTION

FACILITIES

MANAGEMENT

(CFM) 459 PATTERSON RD.

HONOLULU, HI 96819-1522

35% SCHEMATIC DESIGN

65% DESIGN DEVELOPMENT

07-10-2025 08-28-2025

95% CONSTRUCTION DOCUMENTS 10-16-2025

100% CONSTRUCTION DOCUMENTS 11-26-2025

FINAL BID DOCUMENTS 12-22-2025

ADDENDUM 1 - SOLICITATION RFI 05-15-2026

A u to d e s k D o c s /2

-0

V

A H o n o lu lu G e n e ra to rs

/2 -0

H o n o lu lu

H

I M

G S

V A

M C

E le c tr ic a l_ r2

.r v t

030-EP-012

BUILDING 30 ENLARGED ELECTRICAL

PLANS

MER AJW

MODERNIZE GENERATORS

VA PACIFIC ISLAND HEALTH CARE SYSTEM

FINAL BID DOCUMENTS 459-24-001

12-22-2025

1/4" = 1'-0"2

ENLARGED PHASE 2 PLAN - BLDG 30 FUEL TANK

1/4" = 1'-0"4

ENLARGED PHASE 2 PLAN - BLDG 30 GENERATOR

NORTH NORTH

NORTH NORTH

1/4" = 1'-0"1

ENLARGED PHASE 1 PLAN - BLDG 30 FUEL TANK

1/4" = 1'-0"3

ENLARGED PHASE 1 PLAN - BLDG 30 GENERATOR

GENERAL NOTES

1. TEMPORARY GENERATOR LOCATIONS SHOWN IN DRAWINGS ARE

PROPOSED LOCATIONS ONLY. CONTRACTOR TO PERFORM

ASSESSMENT AND PROPOSE A PLACEMENT LOCATION. CONTRACTOR

SHALL SUBMIT A REQUEST FOR TEMPORARY GENERATOR LOCATION TO

COR WITHIN 7 DAYS OF NTP FOR VA CONSIDERATION WITH USAG.

2. TEMPORARY POWER SYSTEM MUST BE ONLINE PRIOR TO

CONSTRUCTION. COORDINATION WITH VA ON ANY REQUIRED OUTAGES

OF EMERGENCY POWER WITH VA PRIOR TO INSTALLATION.

3. TEMPORARY POWER CONNECTIONS SHALL REMAIN OPERATIONAL

UNTIL NEW GENERATORS HAVE BEEN COMPLETELY INSTALLED AND

READY FOR CUTOVER FROM TEMPORARY EQUIPMENT.

4. ALL WORK RELATED TO CONNECTING TEMPORARY GENERATOR

SYSTEM SHALL BE PERFORMED AFTER NORMAL BUSINESS HOURS. ALL

WORK TESTING AND COMMISIONING GENERATOR AND OPERATION OF

TRANSFER SWITCHES SHALL BE PERFORMED AFTER NORMAL BUSINESS

HOURS.

5. ALL GENERATOR WORK ON EXISTING GENERATOR SHALL BE

PERFORMED BY THE LOCAL CATERPILLAR DEALER HAWTHORN CAT TO

MAINTAIN UL LISTING.

6. THE GENERATOR MANUFACTURE FOR THE BASIS OF DESIGN IS

CATERPILLAR. THE CONTRACTOR IS RESPONSIBLE FOR ALL COST

ASSOCIATED DUE TO ALTERNATE SELECTION AND REJECTED

SUBMITTALS.

KEY NOTES

1 DISCONNECT EXISTING DAYTANK CIRCUIT. DEMO BRANCH CIRCUIT TO

NEAREST JUNCTION BOX.

2 EXISTING CONDUCTORS TO EMERGENCY SIDE OF 'ATS-FP' TO BE

REMOVED BACK TO SOURCE. EXISTING CONDUIT TO REMAIN FOR

REUSE.

3 EXISTING GENERATOR SWITCHBOARD INTERIOR TO BE REMOVED.

EXISTING CONDUIT AND CONDUCTORS TO REMAIN TO BE

RECIRCUITED TO NEW INTERIOR IN SAME PLACE.

4 DEMO EXISTING PULLBOX AFTER MECHANICAL REMOVES EXISTING

WIRING. DEMO THE 2 EXISTING 2"GRC 24" BELOW SURFACE.

5 DISCONNECT EXISTING CIRCUIT TO VEEDER ROOT PANEL.

DEMOLITION OF PANEL AND WIRING TO BE PERFORMED BY

MECHANICAL.

6 DISCONNECT EXISTING FUEL TANK WIRING. DEMO TO BE DONE BY

MECHANICAL.

7 DEMO EXISTING JUNCTION BOX.

8 EXISTING FIRE PUMP ATS TO BE RELOCATED TEMPORARILY 2' AWAY

FROM WALL TO ALLOW FOR 2-HOUR FIRE RATED REINFORCEMENT.

EXTEND EXISTING NORMAL POWERED FEEDER AND CONNECT

TEMPORARY POWER TO EMERGENCY SIDE AS REQUIRED FOR

COMPLETE OPERATION. THIS WORK IS TO BE COMPLETED AFTER

NORMAL BUSINESS HOURS.

9 ALL EXISTING CONDUITS, JUNCTION BOXES, MISCELLANEOUS

ENCLOSURES AND FIRE PROTECTION EQUIPMENT MOUNTED ON WALL

TO BE TEMPORARILY REMOVED AND RELOCATED TO ALLOW FOR

2-HOUR FIRE RATED REINFORCEMENT.

10 EXISTING EXIT SIGN TO BE TEMPORARILY REMOVED TO FACILITATE

2-HOUR FIRE RATED WALL REINFORCEMENT. MAINTAIN EXISTING

CONDUIT AND CONDUCTORS FOR REUSE.

11 EXISTING RECEPTACLE TO BE TEMPORARILY REMOVED TO FACILITATE

2-HOUR FIRE RATED WALL REINFORCEMENT. MAINTAIN EXISTING

CONDUIT AND CONDUCTORS FOR REUSE.

12 REPLACE EXISTING EXIT SIGN IN SAME LOCATION AS REMOVED.

RECONNECT EXISTING CONDUIT AND CONDUCTORS.

13 REPLACE EXISTING RECEPTACLE IN SAME LOCATION AS REMOVED.

RECONNECT EXISTING CONDUIT AND CONDUCTORS.

14 RELOCATE EXISTING FIRE PUMP TRANSFER SWITCH BACK TO ITS NEW

LOCATION AFTER 2-HOUR FIRE RATED REINFORCEMENT OF WALL.

EXTEND CONDUIT AND CONDUCTORS AS REQUIRED FOR COMPLETE

OPERATION OF ATS. UTILIZE TEMPORARY POWER FOR THE

EMERGENCY SIDE UNTIL GENERATOR SWITCHBOARD INTERIOR

INSTALLATION IS COMPLETE. WORK SHALL BE COMPLETED AFTER

NORMAL BUSINESS HOURS.

15 ALL EXISTING CONDUITS, JUNCTION BOXES, MISCELLANEOUS

ENCLOSURES AND FIRE PROTECTION EQUIPMENT REMOVED FROM

WALL TO BE REPLACED IN SAME LOCATION AS REMOVED AFTER

2-HOUR FIRE RATED REINFORCEMENT OF WALL.

16 PROVIDE NEW 1200A, 480V, 3-PHASE SWITCHBOARD INTERIOR WITH

1200A MAIN CIRCUIT BREAKER. PROVIDE NEW BRANCH BREAKERS OF

SAME SIZE AS REMOVED TO FEED EXISTING BRANCH CIRCUITS TO

REMAIN. RECONNECT EXISTING SWITCHBOARD AND BRANCH FEEDERS

TO SAME CIRCUITS AS REMOVED BOARD. REFER TO ONE-LINE ON

000-EJ-002 FOR ADDITIONAL INFORMATION.

17 PROVIDE NEW GENERATOR CONTROL PANEL MOUNTED IN AVAILABLE

SPACE IN NEW GENERATOR SWITCHBOARD. PROVIDE CONDUIT AND

CONDUCTORS AS REQUIRED FOR COMPLETE OPERATION OF

GENERATOR CONTROLS. CONTROL PANELS AND TERMINATIONS OF

CONDUCTORS SHALL BE DONE BY GENERATOR VENDOR.

18 PROVIDE CONDUCTORS IN EXISTING CONDUIT FROM NEW 50A

BREAKER TO EMERGENCY-SIDE OF 'ATS-FP'.

19 PROVIDE NEW QUICK CONNECT ENCLOSURE ON END OF EXISTING

SWITCHBOARD ENCLOSURE. PROVIDE PROVISIONS FOR 1200A LOAD

BANK.

20 PROVIDE NEW 50A BREAKER IN EXISTING GENERATOR TO FEED

EMERGENCY-SIDE OF EXISTING TRANSFER SWITCH 'ATS-FP'. PROVIDE

CONDUIT AND CONDUCTORS TO NEW SWITCHBOARD INTERIOR AND

FROM NEW GENERATOR SWITCHBOARD INTERIOR THROUGH EXISTING

CONDUIT TO REMAIN.

21 RECONNECT EXISTING DAYTANK CIRCUIT TO NEW DAYTANK.

22 EXTEND CONNECTION FROM EXISTING VEEDER ROOT TO NEW

VEEDER ROOT PANEL IN SAME LOCATION.

23 ROUTE 2"C THROUGH DUCTBANK.

24 ROUTE PUMP FEEDER FROM NEW PANEL 'FT' TO FUEL PUMP IN 3/4"

SEAL TIGHT CONDUIT. COORDINATE WITH MECHANICAL ON EXACT

LOCATION. SEE SHEET 030-EP-011 FOR FEEDER INFORMATION AND

ROUTING FROM BUILDING 30 TO MAIN FUEL TANK.

25 PROVIDE NEW ELECTRICAL FREE STANDING 316 STAINLESS STEEL

ENCLOSURE WITH PULL SECTION FOR FUEL MONITORING WIRING AND

A POWER SECTION TO HOUSE A 208V PANEL. SEE DETAIL 4 ON SHEET

000-EJ-001 FOR ADDITIONAL INFORMATION. SEE DETAIL 4 ON 000-S-011

FOR ADDITIONAL STRUCTURAL INFORMATION AND REQUIREMENTS.

7. THE BASES OF DESIGN FOR THE GENERATOR SWITCHBOARD

ENCLOSURE RETRO FIT AND MAIN FUEL TANK ENCLOSURE WAS BY TR

ELECTRICAL SERVICES LOCATED IN BOX ELDER, SOUTH DAKOTA.

MANUFACTURE SHALL BE A UL891 AND 508 SHOP. ALL COSTS

ASSOCIATED WITH ALTERNATE MANUFACTURERS ARE THE

RESPONSIBILITY OF THE CONTRACTOR. VA IS NOT LIABLE FOR ANY

ALTERNATIVES. CONTRACTOR TO SUBMIT FULL DESIGN FOR

APPROVAL PRIOR TO CONSTRUCTION.

Revisions: Date:

Sheets
030-EP-012 - BUILDING 30 ENLARGED ELECTRICAL PLANS

File details come from the government source that posted it. Updated .