Attachment RFI Questions and Answers.pdf
PDF 2 MB Posted
- Solicitation number
- 36C26123R0038
About this file
This document includes responses to questions regarding a solicitation for replacing xeriscaping at the Veterans Affairs Medical Center campus in San Francisco, California. The solicitation seeks a contractor to remove existing synthetic turf and playground surfaces in seven designated areas that have reached the end of their useful life, and replace them with new xeriscaping materials. The contractor must dispose of the existing surfaces and install new synthetic turf that is rated for heavy traffic and has a minimum eight-year warranty in areas 1 through 6. A different surface rated to meet playground safety standards with a five-year warranty is required for area 7. The contractor will be responsible for trimming shrubs and temporarily removing picnic tables and playground equipment during installation. The Department of Veterans Affairs intends to issue this request for proposal as a total small business set-aside for Service-Disabled Veteran Owned Small Businesses. The estimated value of the construction is between $250,000 and $500,000.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C26123R0038 0002.docx | DOCX document | |
| 36C26123R0038 0001.docx | DOCX document | |
| Attachment SOW rev 02-08-23.pdf | ||
| Attachment Ariel Map.pdf | ||
| Attachment Pre-solicitation Site Vistit Briefing.pptx | PPTX presentation | |
| Attachment Sterling Playground Tile.pdf | ||
| Attachment Specifications Synthetic Turf.pdf | ||
| Attachment Worksite Picture.pdf | ||
| Attachment Price Breakdown.pdf | ||
| Attachment Construction Waste Management.pdf | ||
| Attachment General Requirements.pdf | ||
| Attachment REQUEST FOR INFORMATION (RFI) FORM.pdf | ||
| 36C26123R0038 Solicitation.docx | DOCX document | |
| Attachment Earthwork.pdf |
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Response to RFI for Solicitation No. 36C26123R0038
Project No. 662-23-120
Replace Xeriscape VAMC San Francisco
Published date: 5/8/2023
RFI #1
Q1: Can you please send an updated Identified Areas (Outlined in RED) sheet? With correct areas for identification?
Q1 VA Response: Answers below clarify area of work.
Q2: Does the sandbox in the play area stay or will it be taken out and gone over with turf?
Q2 VA Response: Yes, the sandbox in the play area stays.
Q3: Does the stump just south of T-32 need to be removed?
Q3 VA Response: Tree stump to be grinded to allow aggregate materials and xeriscaping.
Q4: Who is responsible for the temporary water/sprinkler removal - just south of T-33 outlined in red?
Q4 VA Response: The SFVA will remove water/sprinkler removal - just south of T-33 outlined in red.
Q5: Will the bushes in the same area from RFI #4 remain, or just the trees?
Q5 VA Response: Bushes to be removed.
Q6: Confirming side area between T-32 and the property line is NOT included.
Q6 VA Response: Concrete area behind T-32 not included.
Q7: Confirming tree/bushes will remain between the sidewalk & Bldg 7? Does the area below these trees need to be turfed?
Q7 VA Response: Trees/bushes between the sidewalk and BLDG 7 to remain. No turf needed in the area below trees.
Q8: Who is responsible for trimming back the overgrowth of the shrubs of the west end of area #1 north of the parking stalls?
Q8 VA Response: The contractor is responsible for trimming back the overgrowth of the shrubs of the west end of area #1 north of the parking stalls.
Q9: Who is responsible for moving the picnic tables with the umbrellas (free standing) in area #1?
Q9 VA Response: Contractor to remove the picnic tables with the umbrellas and reinstall after xeriscaping work is done.
Q10: Will the mulch area at the north end and west side of Bldg 9 remain? Will the mulch area on the south end and the west side of Bldg 10 remain?
Q10 VA Response: Both mulch areas to be replaced by xeriscaping material.
Q11: As currently installed the rectangle of turf sits on top of rubberized surface and is considered a tripping hazard. Is it the intention of the VA to have these 2 surfaces flushed out?
Q11 VA Response: Eliminate the tripping hazard/ flush out both surfaces.
Q12: Will equipment and standing shelters in the play area be removed?
Q12 VA Response: Equipment NOT anchored to be temporary removed for Xeriscaping installation and put back in place.
Q13: Can you please send an updated identified Areas (Outlined in Red) sheet? With correct areas for identification? (See photo)
Q13 VA Response: Answers to the RFIs give a clear representation of the area of work. Area between the side walk/ Building 7, concrete area behind Building 232 are not included.
Q14: Does the sandbox in the play area stay or will it be taken out and gone over the turf? (see photo)
Q14 VA Response: Yes, the sandbox in the play area stays.
Q15: Does the stump just south of T-32 need to be removed? (see photos)
Q15 VA Response: Tree stump to be grinded to allow aggregate materials and xeriscaping.
Q16: Who is responsible for the temporary water/sprinkler removal just south of T-33 outlined in red?
Will the bushes in the same area from RFI #4 remain, or just the trees? (see photos)
Q16 VA Response: SFVA to remove the temporary water sprinkler/bushes to be removed.
Q17: Confirming side area between T-32 and the property line is NOT included (see photo)
Q17 VA Response: The concrete area behind the building does not required xeriscaping.
Q18: Confirming trees/bushes will remain between the sidewalk and Bldg 7? Does the area below these trees need to be turfed? (see photo)
Q18 VA Response: Trees/bushes near BLDG 7 to remain. No turf needed in the area below trees.
Q19: Who is responsible for trimming back the overgrowth of the shrubs of the west end of area #1 north of the parking stalls? Who is responsible for moving the picnic tables with the umbrellas (free standing) in area #1? (see photos)
Q19 VA Response: The contractor is responsible for trimming back the overgrowth of the shrubs of the west end of area #1 north of the parking stalls.
Q20: Will the mulch area at the north end and west side of Bldg 9 remain? Will the mulch area on the south end and the west side of Bldg 10 remain?
Q20 VA Response: Both mulch areas to be replaced by xeriscaping material.
Q21: As installed currently the rectangle of turf sits on top of rubberized surface and is considered a tripping hazard. Is it the intention of the VA to have these two surfaces flushed out?
(see photo)
Q21 VA Response: Eliminate the tripping hazard/both surfaces flush.
Q22: Will equipment and standing shelters in the play area be removed? (see photo)
Q22 VA Response: Equipment NOT anchored to be temporary removed for Xeriscaping installation and put back in place.