About this file

36C26119B0019 02 41 00 Demolition.docx

View the file

Other files

File Type Posted
36C26119C0100-000.docx DOCX document
36C26119B0019-0007001.pdf PDF
36C26119B0019-0007000.docx DOCX document
36C26119B0019-0006000.docx DOCX document
36C26119B0019-0006001.pdf PDF
36C26119B0019-0006002.pdf PDF
36C26119B0019-0005000.docx DOCX document
36C26119B0019-0004001.pdf PDF
36C26119B0019-0004000.docx DOCX document
36C26119B0019-0003000.docx DOCX document
36C26119B0019-0003001.pdf PDF
36C26119B0019-0002003.pdf PDF
36C26119B0019-0002005.pdf PDF
36C26119B0019-0002004.pdf PDF
36C26119B0019-0002002.pdf PDF
36C26119B0019-0002000.docx DOCX document
36C26119B0019-0002001.pdf PDF
36C26119B0019-0001000.docx DOCX document
36C26119B0019-013.docx DOCX document
36C26119B0019-018.jpg JPG image
36C26119B0019-007.docx DOCX document
36C26119B0019-017.jpg JPG image
36C26119B0019-003.docx DOCX document
36C26119B0019-001.docx DOCX document
36C26119B0019-010.docx DOCX document
36C26119B0019-002.docx DOCX document
36C26119B0019-015.docx DOCX document
36C26119B0019-011.docx DOCX document
36C26119B0019-016.jpg JPG image
36C26119B0019-020.jpg JPG image
36C26119B0019-004.docx DOCX document
36C26119B0019-014.docx DOCX document
36C26119B0019-006.docx DOCX document
36C26119B0019-012.docx DOCX document
36C26119B0019-005.docx DOCX document
36C26119B0019-022.docx DOCX document
36C26119B0019-009.docx DOCX document
36C26119B0019-019.jpg JPG image
36C26119B0019-021.pdf PDF
36C26119B0019-000.docx DOCX document
Show all 40

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Section 02 41 00 DEMOLITION 12-12-2018 Part 1 - General

1.1. Description

A. This section specifies demolition and removal of buildings, portions of buildings, utilities, other structures and debris from trash dumps shown General Intention.

1.2. Related Work

A. Section 00 72 00,GENERAL CONDITIONS
B. Section 01 00 00,GENERAL REQUIREMENTS
C. Section 01 32 16.17,PROJECT SCHEDULES
D. Section 01 33 23,SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES
E. Section 01 35 26,SAFETY REQUIREMENTS
F. Section 01 42 19,REFERENCE STANDARDS
G. Section 01 57 19,ENVIRONMENTAL CONTROLS
H. Section 02 41 00,DEMOLITIONS
I. Section 13 05 41,SEISMIC RESTRAINT REQUIREMENTS FOR NON-STRUCTURAL COMPONENTS
J. Section 23 05 11,COMMON WORK RESULTS for HVAC
K. Section 23 05 41,NOISE AND VIBRATION CONTROL FOR HVAC PIPING and EQUIPMENT
L. Section 23 05 93,TESTING, ADJUSTING, and BALANCING FOR HVAC
M. Section 23 07 11,HVAC, and BOILER PLANT INSULATION
N. Section 23 08 00,COMMISSIONING OF HVAC SYSTEMS
O. Section 23 64 00,PACKAGED WATER CHILLERS

1.3. Protection

A. Perform demolition in such manner as to eliminate hazards to persons and property; to minimize interference with use of adjacent areas, utilities and structures or interruption of use of such utilities; and to provide free passage to and from such adjacent areas of structures. Comply with requirements of GENERAL CONDITIONS Article, ACCIDENT PREVENTION.

B. Provide safeguards, including warning signs, barricades, temporary fences, warning lights, and other similar items that are required for protection of all personnel during demolition and removal operations. Comply with requirements of Section 01 00 00, GENERAL REQUIREMENTS, Article PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES AND IMPROVEMENTS.

C. Maintain fences, barricades, lights, and other similar items around exposed excavations until such excavations have been completely filled.

D. Provide enclosed dust chutes with control gates from each floor to carry debris to truck beds and govern flow of material into truck. Provide overhead bridges of tight board or prefabricated metal construction at dust chutes to protect persons and property from falling debris.

E. Prevent spread of flying particles and dust. Sprinkle rubbish and debris with water to keep dust to a minimum. Do not use water if it results in hazardous or objectionable condition such as, but not limited to; ice, flooding, or pollution. Vacuum and dust the work area daily.

F. In addition to previously listed fire and safety rules to be observed in performance of work, include following:

1. No wall or part of wall shall be permitted to fall outwardly from structures.

2. Keep hydrants clear and accessible at all times. Prohibit debris from accumulating within a radius of 4500 mm (15 feet) of fire hydrants.

G. Before beginning any demolition work, the Contractor shall survey the site and examine the drawings and specifications to determine the extent of the work. The contractor shall take necessary precautions to avoid damages to existing items to remain in place, to be reused, or to remain the property of the Medical Center any damaged items shall be repaired or replaced as approved by the Resident Engineer. The Contractor shall coordinate the work of this section with all other work and shall construct and maintain shoring, bracing, and supports as required. The Contractor shall ensure that structural elements are not overloaded and shall be responsible for increasing structural supports or adding new supports as may be required as a result of any cutting, removal, or demolition work performed under this contract. Do not overload structural elements. Provide new supports and reinforcement for existing construction weakened by demolition or removal works. Repairs, reinforcement, or structural replacement must have Resident Engineer’s approval.

H. The work shall comply with the requirements of Section 01 57 19, TEMPORARY ENVIRONMENTAL CONTROLS.

I. The work shall comply with the requirements of Section 01 00 00, GENERAL REQUIREMENTS, Article 1.7 INFECTION PREVENTION MEASURES.

1.4. Utility Services

A. Remove abandoned outside utility lines that would interfere with installation of new utility lines and new construction.

Part 2 – Products (Not Used) Part 3 - Execution

3.1. Demolition

A. Completely remove structures, including all appurtenances related or connected thereto, as noted below:

1. As required for installation of new utility service lines.

B. Debris, including brick, concrete, stone, metals and similar materials shall become property of Contractor and shall be disposed of by him daily, off the Medical Center to avoid accumulation at the demolition site. Materials that cannot be removed daily shall be stored in areas specified by the COR. Contractor shall dispose debris in compliance with applicable federal, state or local permits, rules and/or regulations.

C. Remove existing utilities as indicated or uncovered by work and terminate in a manner conforming to the nationally recognized code covering the specific utility and approved by the COR. When Utility lines are encountered that are not indicated on the drawings, the COR shall be notified prior to further work in that area.

3.2. Clean Up

A. On completion of work of this section and after removal of all debris, leave site in clean condition satisfactory to COR. Cleanup shall include off the Medical Center disposal of all items and materials not required to remain property of the Government as well as all debris and rubbish resulting from demolition operations.

- E N D