This is a Requests for Information (RFI) Log that documents responses to vendor inquiries for the Expand Emergency Room project (Solicitation 36C26027R0002-0007) issued by the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 20. The RFI Log No. 2 compilation contains official VA responses to questions submitted by prospective contractors regarding the solicitation requirements, technical specifications, and project scope for the emergency room expansion initiative.
The document serves as an amendment reference providing clarification and official guidance to all potential bidders. The RFI responses address technical document revisions and incorporate official information necessary for contractors to develop compliant proposals. This log is part of Amendment 0007, which also extended the proposal due date and time while providing these consolidated RFI responses to ensure all interested parties have access to the same clarifications and technical updates relevant to submitting proposals for this VA construction/renovation project.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1 RFIs/QUESTIONS LOG NO. 2 Questions Due: COB 11/13/26 SOLICITATION/RFP NO. 36C26027R0002 - Expand Emergency Room, VAMC, Boise ID
| # of RFI | RFI/QUESTION | VA RESPONSE |
| 1 | We would like to be considered for equal alternates on the lighting and controls package for the project to provide a bid to the electrical contractors bidding the project. |
Attached are the cut sheets for our equals on the lighting and controls. If these could be reviewed and considered, we would greatly appreciate it. Refer to Amendment 0006.
The Government will not review or approve alternate products, technical substitutions, or product recommendations during the active solicitation phase. The successful awardee may submit product recommendations and substitution requests post-contract award for government evaluation through the formal submittal process for review and technical acceptability, and contract compliance in accordance with the contract's submittal procedures.
All prospective offerors must submit their proposal based strictly on the solicitation requirements, as amended.
2 There are a number of Headwalls shown at bed locations and in exam rooms.
There are no # A1110 Headwall shown at A6 Exam, A5 Mental Health, A2 General Exam, Triage, B6 General Exam and B4 General Exam.
| Do these rooms not get Headwalls? | Confirmed A6, A5, A2, Triage, B6, and B4 to have headwalls. | |
| 3 | A1200 Patient Lift shows up in two places on Sheet QH104 in Triage and on QH105 in B4 General Exam. |
A1200 shows up on the Elevation Sheets AE905 – Gen Exam 851005 and Triage, AE906 – Gen Exam 851033, Resuscitation, B3 Exam 851032, AE907 – C3 Airborne and on AE908 – C2 Gyn and B8 Gen Exam.
There are 8 shown on the Elevation Sheets but only 2 shown on the Equipment Plans.
| Which is correct? | Equipment plans are not ceiling plans. Refer to elevations as representative room types for different rooms. All patient exam rooms to have patient lifts. Please see AC101. Mental Health, exclusion, and A4 Fast Track Exam Room 851008 do not have patient lifts. | |
| 4 | We have some questions about the existing transformer and the requirements of the new transformer as well as some clearance concerns for the replacement of the ATS-6 and ATS-8. |
Please review the questions and comments below.
The transformer in question is T3. The one-line diagram identifies it as a 45 kVA transformer; however, the existing transformer I verified in the field is only 30 kVA.
o If the design requires a 45 kVA transformer, the existing unit will need to be replaced with a larger transformer, resulting in additional material and installation labor costs that would need to be accounted for.
Their appears to be a concern for the replacement of ATS-6. The existing transfer switch is rated at 225A, while the new switch is specified at 400A. Hopefully, the larger switch will fit within the existing location without creating clearance issues. If there is a clearance issue, we will address it together
| • | The existing ATS-6 already encroaches slightly into the required working clearance for NDP1. Until we receive the equipment submittals and verify the dimensions of the new ATS, we won't know whether the replacement will further encroach into NDP1's working space. |
| • | For reference, ATS-8, located to the right of ATS-6, is an existing 400A transfer switch and is noticeably deeper than ATS-6. If the new ATS-6 is similar in size, this could create additional clearance issues. |
| 1. | If the replacement ATS further encroaches into the required working clearance, the VA will need to determine whether an approved variance or other acceptable solution can be provided to allow installation as shown. Otherwise, the ATS may need to be relocated, resulting in additional work and a potential cost impact. |
| T3 does not need to be replaced as part of this contract. It shall remain as shown on the drawings. The Contractor shall provide equipment of size, dimension, configuration, and location as required to place the equipment in the room indicated. Contract drawings are diagrammatic in nature as stated in the specifications. If a contractor believes an alternative location in the room is required for a given manufacturer, then it shall be bid as such. Contract modifications for this item will not be entertained. |
| 5 | The recent amendment has issued the bid submission date as Wednesday, November 25. We request that the government consider pushing the due date to the following week as the Thanksgiving holiday will limit the availability of subcontractors still providing their bids to our team. In the interest of providing the most cost effective price to the government, we request this change. | Please review this amendment SF30. |
| 6 | Pt. 1 - Please confirm that any furniture within each phase will be removed and stored by VA before construction begins. |
Pt. 2 - In addition to question above, if contractor is responsible for removing existing furniture. Please revise plans to show existing furniture to be removed in each space and confirm any items the VA is wanting to keep the contractor will not be responsible for storing any of the salvaged furniture. Pt. 1 - Confirmed. Furniture is to be removed and stored by VA prior to each phase.
Pt. 2 - N/A (See Pt. 1 response to this RFI, above)
| 7 | Reference Amendment 0006 RFI #36 and VA Response: Please confirm if corridor C11 can be performed under one of the three existing phases. If this is an additional phase (Phase 4). Please confirm logistical requirements such being ICRA plan for area. | See GC103 in the drawings. This is not an additional phase but should be planned as part of phase 3. The order of work is to be coordinated with the COR. Fire doors at either end of C11 will function as ICR barriers. |
| 8 | Reference Amendment 0006 RFI #55 and VA Response: Please provide headwall specifications as vendors are unable to provide pricing for headwalls without this information. | See JSN #A1110 for MILSTD 1691. Electrical connections are shown on the drawings. Exact heights of electrical connections to be coordinated with headwall provider and architectural drawings. Coordinate final counts with shop drawings. |
| 9 | Please provide dimensions of indicated headwall units, Gas outlet counts by type, and duplexes by type. | See JSN #A1110 for MILSTD 1691. Low voltage connections are shown on the drawings. Exact heights of electrical connections to be coordinated with headwall provider and architectural drawings. Coordinate final counts with shop drawings. |
| 10 | Please confirm any data or low voltage provisions required for the medical headwalls. | See JSN #A1110 for MILSTD 1691. |
| 11 | Reference Amendment 0006 RFIs #174 & #197 and VA Responses: |
Pt. 1 - Please confirm if contractor will be able to remove plumbing runs to the left of grid line J from the basement as described in RFI #174 from the ceiling of the basement. If so, please confirm any ceiling patch work or if ACT system is in place and can feasibly be accessed for pipe run removal.
Pt. 2 - In addition to question above, if possible to access from basement ceiling please confirm this will also apply for new plumbing work shown on PP100 for the installation of piping. Pt. 1 - Confirmed that the basement to the left of grid line J is either exposed to the structural deck or ACT system.
Pt. 2 - Ceiling access will remain the same for demolition and new work.
| 12 | Reference Amendment 0006 RFI #197 & Detail 16 on Sheet S900: Please confirm slab thickness and for patchwork to the right of grid line J for slab infill once saw cutting is complete. | Existing slab thickness is 4". Thickness of slab infill in detail 16/S900 to match thickness of existing slab on grade. |
| 13 | Reference Amendment 0006 RFI #250: Please confirm the 14 day duration to allow VA time to migrate equipment, staff, and medical operations will not penalize the contractors period of performance. | Confirmed. |
| 14 | Reference Amendment 0006 RFI #323: Please identify an area on the VA’s campus where contractor lay down area will be permitted. | The successful contractor shall submit a site layout and mobilization plan, which shall include all proposed container and material storage locations, to the COR for approval prior to physical construction phase. The COR's final approval of laydown area boundaries must be secured prior to mobilization. |
| 15 | Transformer T3 is shown on the one line diagram as a 45 kVA transformer; however, this transformer is only 30 kVA. Please confirm that T3 will be adequate to remain for the design intent. | T3 does not need replaced as part of this contract. It shall remain as shown on the drawings. |
| 16 | The existing transfer switch is rated at 225A, while the new switch is specified at 400A. The existing ATS-6 already encroaches slightly into the required working clearance for NDP1. Please confirm the 400A switch will fit within the existing location with creating clearance issues. |
For reference, ATS-8, located to the right of ATS-6, is an existing 400A transfer switch and is noticeably deeper than ATS-6. If the new ATS-6 is similar in size, this could create additional clearance issues.
If the replacement ATS further encroaches into the required working clearance, the VA will need to determine whether an approved variance or other acceptable solution can be provided to allow installation as shown. Otherwise, the ATS may need to be relocated, resulting in additional work and a potential cost impact. Contractor shall provide equipment of size, dimension, configuration, and location as required to place the equipment in the room indicated. Contract drawings are diagrammatic in nature as stated in the specifications. If a contractor believes an alternative location in the room is required for a given manufacturer, then it shall be bid as such. Contract modifications for this item will not be entertained.
| 17 | Sheet AE801: Please confirm ICRA barrier walls are to be constructed per partition type T. | Confirmed. |
| 18 | Reference Amendment 0006 RFI #39 & RFI #178: There seems to be a conflict of information between these responses. #39 states that the AHU will be brought through an exterior door and may require the unit to be “knockdown”. RFI #178 states the penthouse is located on the roof. |
Pt. 1 - Please confirm if the penthouse is enclosed or is open.
Pt. 2 - To follow up the previous question whether the penthouse is an enclosed space. Please confirm if any walls will need to be removed and built back to install the AHU-18. Pt. 1 - Penthouse is enclosed.
Pt. 2 - Unit to be brought in through existing openings in the penthouse.
| 19 | Reference Amendment 0006 RFI #54: Please confirm provide installation requirements for the patient lifts to allow contractors to properly include. | See JSN# A1200 for MILSTD 1691. |
| 20 | Reference Amendment 0006 RFI #57 Pt2: Please revise plans showing where new carriers will be located. | Plans will not be revised. Carriers to be located adjacent to the pneumatic tube system. |
| 21 | Please confirm that no new tube network or any other equipment/material is required for the pneumatic tube scope outside of the singular station and the 4 carriers we are to provide as described in RFI #57. | Confirmed. |
| 22 | Addendum 006 revised the lighting drawings. Drawing EL102 identifies one new lighting-control panel designated CP-LTG, and Drawing EP103 identifies the power-supply circuit for CP-LTG. CP-LTG is not identified in the E700 luminaire schedule, and a separate CP-LTG equipment schedule, lighting-control riser, or panel schedule does not appear to be provided. The drawings do not identify which lighting branch circuits, luminaires, or control zones are controlled through CP-LTG. |
E700 provides the Lighting Control Wall Device Schedule and Lighting Control Sequence of Operations referenced by the control tags on EL102. These schedules appear to establish local occupancy/vacancy sensing, ON/OFF switching, and dimming functions within the individual rooms. The Sequence of Operations also identifies the control types as networked, while scheduled control appears to apply to the CORR control type and not to the individual room control types. The relationship between these local room controls, the network designation, and CP-LTG is not shown.
Please clarify the following:
| a. Confirm whether CP-LTG controls only corridor and common-area lighting or also controls or supervises lighting within patient, exam, support, and administrative rooms. | CP-LTG is diagrammatically showing a lighting central control panel for the addressable lighting control system specified in 26 09 23. CP-LTG is not a luminaire so it is not included in the luminaire schedule. CP-LTG is not a piece of equipment. Lighting control risers are not representative of a modern lighting controls system of this type and would restrict bidding. The lighting controller is the central logic unit for the lighting control system. It is the connection point for all the distributed components of the lighting system as required to meet the operational descriptions in the project documents. All tags are on the networked low voltage control system and explicitly show a required connection to a head end which is now explicitly shown as CP-LTG. All controls shall be networked type. It is a networked lighting control system. | ||
| 23 | b. Identify every lighting-control type or zone connected to CP-LTG, including the CORR, PAT, FP20, LM5, RSTS, and other control designations shown on EL102 and E700. | All, as shown in the NETWORK column. | |
| 24 | c. Identify the lighting branch circuits, luminaires, and control zones controlled through CP-LTG. | All, as shown in the NETWORK column. | |
| 25 | d. Explain the “Network” designation shown in the E700 Lighting Control Sequence of Operations and confirm whether the individual room controls are local networked components of the CP-LTG system or independent standalone controls. | No standalone independent controls. It is a networked lighting control system. | |
| 26 | e. Confirm whether the scheduled-control designation shown for CORR means that only corridor/common-area lighting receives time-scheduled control through CP-LTG. If not, identify the scheduled-control requirements for each room control type. | The only one showing schedule control is CORR, so only CORR should receive schedule control. | |
| 27 | f. Provide a lighting-control riser or system architecture identifying CP-LTG, panel capacity, network hubs, distributed relay modules, room controllers, controlled branch circuits, and system interfaces. | This is the responsibility of the lighting controls contractor. Sufficient information has been provided for bidding this system. | |
| 28 | g. Provide a typical lighting-control circuiting and wiring diagram showing the branch circuit from the lighting panel; CP-LTG, network hub, or relay module; line-voltage wiring through the control relay; wiring from the relay to the controlled luminaires; occupancy-sensor, wall-switch, and dimming-control connections; communication wiring; emergency-lighting control connections if applicable. | This is the responsibility of the lighting controls contractor. Sufficient information has been provided for bidding this system. | |
| 29 | h. Provide the manufacturer or basis of design, model, enclosure requirements, relay capacity, for CP-LTG. | There is no manufacture restriction. | |
| 30 | Reference Amendment 0006 RFI #60 directs coordination with the ATC contractor for lighting-control integration with the existing Automated Logic WebCTRL building automation system. Clima-Tech will provide the required DDC/BACnet integration; however, the contract documents do not define the lighting scheduling functions required by the VA. | ||
| Please identify the lighting zones or control types that the VA requires to be scheduled through the DDC/WebCTRL system and provide the project-specific scheduling requirements, including occupied and unoccupied times, holiday schedules, after-hours overrides, and any lighting status or monitoring points required in WebCTRL. | The only portion needed to integrate is the occupancy sensors/modes. Coordinate with lighting controls provider. | ||
| 31 | Door hardware: Set 3 lists 18 electrified locks/readers. Doors 851007, 851008, 851029 and 851031 show no card reader on AE701, and 851025 has a reader but gets Set 8 (no electrified lock). What is the final controlled door list? | Doors 851025 and 851031 to be set 3. Doors 851008, 851007, and 851029 to be set 5. |
Refer to revised Drawings AE701 (11/18/26) and Specifications 087100
| 32 | Telecom room: E601 says reuse plus additions. What rack, patch panel and PoE switch quantities, or what allowance should we carry? | "Contractor is responsile for device count and quantity of patch panels required. Field verify existing conditions." |
| 33 | Please confirm any LV demolition associated with this project. Please provide updated demolition drawings depicting work. | This is a blanket demolition project except where selective demolition is explicitly shown. |
| 34 | Intrusion detection: spec 28 13 53 was removed, but the RFI 113 answer still mentions it. Please confirm IDS is excluded. | A full intrusion detection system (IDS) is not included nor are any components specified. Components of the access control system, namely door position switches, require being connected to the intrusion detection system. That is the extent of the scope related to the intrusion detection system. |
| 35 | The revised electrical drawings identify three hand-wave switches and one push plate for the four automatic door opening. However, the required activation device quantities and locations are unclear. Please confirm the required activation device, types, quantities, and locations at each opening. Including whether activation is required on both sides or through access control. | See security symbol legend. |
| 36 | In response to RFI #219, Amendment 0006 revised the drawings to identify four automatic door openings. However, hardware sets 2 and 10 still reference automatic operators at openings 851037B, C004B, ST14, and E851027B, which are not identified with operators on AE701. Please confirm that the revised architectural door schedule governs and that automatic operators are not required at these four additional openings. | C16B to change to set 1. 851037B, C004B, St14, and E841027B to have automatic DOOR CLOSERS and remain as specified sets. |
| 37 | As per RFI 214, the Blast GP Values are protected information, and are not included in the design documents. |
As there are several openings called out to have blast ratings on the door schedule, as well as windows in walls that have Blast sure-board for the Police room.
In order to provide an accurate number for the openings that are to have both blast and ballistic resistance levels, I need the full blast resistance as soon as possible. What is provided for the glazing is not enough to get an accurate price for the doors, frames, and hardware that are to be blast and ballistic rated.
| Can you reach out and get approval from the VA CFM to release the full blast criteria to us? | The Government/VA believes that offerors should be able to provide proposals without needing this sensitive information. Applicable walls, doors, and windows are shown on the drawings. | |
| 38 | We help contractors protect the good stuff once it starts going in — floors, stairs, glass, countertops, millwork, etc. |
Could you connect me with the right person on the project?
| Awardee information will be posted on SAM.gov, after award. | |
| 39 | The transformer is T3. The one-line diagram identifies it as a 45 kVA transformer; however, the existing transformer I found in the field is only 30 kVA. |
Another concern is the replacement of ATS-6. The existing transfer switch is rated at 225A, while the new switch is specified at 400A. Hopefully, the larger switch will fit within the existing location without creating clearance issues.
The existing ATS-6 already encroaches slightly into the required working clearance for NDP1. Until we receive the equipment submittals and verify the dimensions of the new ATS, we won't know whether the replacement will further encroach into NDP1's working space.
For reference, ATS-8, located to the right of ATS-6, is an existing 400A transfer switch and is noticeably deeper than ATS-6. If the new ATS-6 is similar in size, this could create additional clearance issues.
If the replacement ATS further encroaches into the required working clearance, the VA will need to determine whether an approved variance or other acceptable solution can be provided to allow installation as shown. Otherwise, the ATS may need to be relocated, resulting in additional work and a potential cost impact. T3 does not need to be replaced as a part of this contract. It shall remain as shown on the drawings. Contractor shall provide equipment of size, dimension, configuration, and location as requied to place the equipment in the room indicated. Contract drawings are diagrammatic in nature as stated in the specifications. If a contractor believes an alternative location in the room is required for a given manufacturer, then it shall be proposed as such. Contract modifications for this item will not be entertained.
| 40 | Angled nurse stations, E0406. QH101 lists "nurse station, angle, free standing" under code CC and QH105 tags two of them, but no casework detail shows them. Are the angled desks Millwork or manufactured furniture? | See JSN #E0406 for MILSTD 1691. |
| 41 | Solid-surface wall panels, SS-2. IN101 note 16 calls for SS-2 behind the lavatories in the exam and treatment rooms. The plumbing plan tags 19 exam lavatories, and the interior elevations tag 7 panels. For example, Detail 8 on sheet AE906 does call out for the SS-2. Please confirm that all exam and treatment rooms receive SS-2 behind lavatories? | Confirmed. Note 16 applies to all exam and treatment rooms. |
| 42 | Medication Room 851026. Elevation 2 on AE913 shows a two-door base cabinet with a top under a refrigerator R6200, there is no tag or equipment number for what this cabinet is, and the AE302 plan does not show it. Is it casework? | Drawing corrected to reference detail 9 on AE904 for casework. |
Refer to revised Drawing Sheet E501.