Site Visit Roster and RFI.pdf
PDF 228 KB Posted
- Attached to
- Y1ND--531-24-108 | UPGRADE STORM SEWER SYSTEM
- Solicitation number
- 36C26025R0035
About this file
This file contains an RFI response and site visit roster for a VA storm sewer system upgrade project at the Boise VAMC. The RFI (#1) concerns the installation of StormTech 4500 Chambers and questions whether the VA would consider expanding the limits of disturbance to avoid costly shoring requirements that would exceed the $500,000 budget limit. The VA's response simply states that all work must be accomplished according to the drawings and specifications.
The associated site visit roster shows this is for Solicitation 36C26025R0035, Project Number 531-24-108, with key dates including: Site Visit on 01/30/2025 at 9:00 AM MT, RFI Due on 02/06/2025, and Proposals Due on 02/24/2025. The contracting team includes Stephen Slaby (CO), Alan Perez (CS), and Jon Wagner (COR), with multiple contractors in attendance including representatives from Cutting Edge Construction, Global Engineering, Winspear Construction, Hance Construction, HD Inc., and Shamrock Construction.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C26025R0035 0001.docx | DOCX document | |
| S02 EXHIBIT B Past Performance Reference Form.docx | DOCX document | |
| 36C26025R0035_2.docx | DOCX document | |
| S02 Exhibit A Project Information Sheet for Contractors.docx | DOCX document | |
| S02 Specifications 531-24-108 Upgrade Storm Sewer.pdf | ||
| S02 Wage Determination ID20250104_01-03-2025.docx | DOCX document | |
| S02 Drawings 531-24-108 Upgrade Storm Sewer.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFI #1
We have been evaluating the feasibility of installing the StormTech 4500 Chambers within the project's limits of disturbance. To maintain these limits, shoring will be necessary for safe installation, as benching the excavation will not be possible. If shoring is required, (our company) believes this will increase the project cost beyond the $500,000 budget limit. Would the VA consider expanding the limits of disturbance to allow for safe excavation practices and possibly remain within the given budget?
All work must be accomplished in accordance with the drawings and specifications.
Response:
| RFI |
| Boise Site Visit Storm Sewer |