This document includes a master specification for the renovation of Building 7 at the Mann-Grandstaff VA Medical Center in Spokane, Washington. The specification covers requirements for various construction disciplines including demolition, hazardous materials abatement, concrete, metals, thermal and moisture protection, openings, finishes, specialties, furniture, conveyance systems, fire protection, plumbing, HVAC, electrical, communications, electronic safety and security, earthwork, and exterior improvements. The related federal contract opportunity is a solicitation for construction services to complete project 668-21-101 for the Building 7 Renovation with a performance period of 365 calendar days. Offerors must be registered in SAM and certified through SBA as a Service-Disabled Veteran Owned Small Business. The requirement is set aside 100% for SDVOSBs. The contracting agency is the Department of Veterans Affairs Veterans Health Administration VISN 20.

View the file

Other files

Show all 20

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

VA Spokane, Renovate Building 7 – Mental Health 04-2023

00 01 10-1

DEPARTMENT OF VETERANS AFFAIRS

VHA MASTER SPECIFICATIONS

TABLE OF CONTENTS

Section 00 01 10

SECTION NO. DIVISION AND SECTION TITLES DATE

DIVISION 00 - SPECIAL SECTIONS

00 01 15 List of Drawing Sheets 05-20

DIVISION 01 - GENERAL REQUIREMENTS

01 00 00 General Requirements 05-21

01 32 16.15 Project Schedules (Small Projects – Design/Bid/Build 03-20

01 33 23 Shop Drawings, Product Data, and Samples 06-21

01 35 26 Safety Requirements 07-20

01 42 19 Reference Standards 11-20

01 45 00 Quality Control 02-21

01 45 35 Special Inspections 06-21

01 57 19 Temporary Environmental Controls 01-21

01 58 16 Temporary Interior Signage 07-15

01 74 19 Construction Waste Management 01-21

01 81 13 Sustainable Construction Requirements 10-17

01 91 00 General Commissioning Requirements 10-15

DIVISION 02 – EXISTING CONDITIONS

02 41 00 Demolition 08-17

02 82 11 Traditional Asbestos Abatement 01-21

02 82 13.19 Asbestos Floor Tile and Mastic Abatement 01-21

02 83 33.13 Lead-Based Paint Removal and Disposal 01-21

DIVISION 03 – CONCRETE

03 30 00 Cast-in-Place Concrete 01-21

DIVISION 05 – METALS

05 12 00 Structural Steel Framing 11-18

05 31 00 Steel Decking 01-21

05 50 00 Metal Fabrications 08-18

DIVISION 06 – WOOD, PLASTICS AND COMPOSITES

06 20 00 Finish Carpentry 01-21

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 01 50.19 Preparation for Re-Roofing 01-21

07 08 00 Facility Exterior Closure Commissioning 01-21

07 11 13 Bituminous Dampproofing 01-21

07 18 13 Pedestrian Traffic Coatings 01-21

00 01 10-2

SECTION NO. DIVISION AND SECTION TITLES DATE

07 21 13 Thermal Insulation 01-21

07 22 00 Roof and Deck Insulation 01-21

07 24 00 Exterior Insulation and Finish Systems 01-21

07 54 23 Thermoplastic Polyolefin (TPO) Roofing 01-21

07 60 00 Flashing and Sheet Metal 01-21

07 71 00 Roof Specialties 01-21

07 72 00 Roof Accessories 01-21

07 92 00 Joint Sealants 10-17

07 95 13 Expansion Joint Cover Assemblies 01-21

DIVISION 08 - OPENINGS

08 11 13 Hollow Metal Doors and Frames 01-21

08 14 00 Interior Wood Doors 01-21

08 17 10 Integrated Door Assemblies 01-21

08 31 13 Access Doors and Frames 01-21

08 51 13 Aluminum Windows 01-21

08 56 53 Blast Resistant Windows 01-21

08 71 00 Door Hardware 01-21

08 71 13 Automatic Door Operators 01-21

08 80 00 Glazing 01-21

08 90 00 Louvers and Vents 01-21

DIVISION 09 – FINISHES

09 05 16 Subsurface Preparation for Floor Finishes 01-21

09 06 00 Schedule for Finishes 01-21

09 22 16 Non-Structural Metal Framing 06-18

09 29 00 Gypsum Board 04-20

09 30 13 Ceramic/Porcelain Tiling 01-21

09 51 00 Acoustical Ceilings 12-18

09 65 13 Resilient Base and Accessories 01-21

09 65 16 Resilient Sheet Flooring 05-18

09 65 19 Resilient Tile Flooring 05-18

09 68 00 Carpeting 01-21

09 91 00 Painting 01-21

DIVISION 10 – SPECIALTIES

10 11 13 Markerboards 01-21

10 14 00 Signage 01-21

10 26 00 Wall and Door Protection 01-21

10 28 00 Toilet, Bath, and Laundry Accessories 01-21

10 44 13 Fire Extinguisher Cabinets 08-18

DIVISION 12 – FURNISHINGS

12 32 00 Manufactured Wood Casework 09-15

12 36 00 Countertops 12-18

00 01 10-3

DIVISION 13 - SPECIAL CONSTRUCTION

13 05 41 Seismic Restraint Requirements for Non-Structural

Components

01-14

DIVISION 21- FIRE SUPPRESSION

21 08 00 Commissioning of Fire Suppression System 11-16

21 13 13 Wet-Pipe Sprinkler Systems 06-15

DIVISION 22 – PLUMBING

22 05 11 Common Work Results for Plumbing 09-20

22 05 12 General Motor Requirements for Plumbing 09-20

22 05 19 Meters and Gages for Plumbing Piping 09-20

22 05 23 General-Duty Valves for Plumbing Piping 09-20

22 05 33 Heat Tracing for Plumbing Piping 09-19

22 07 11 Plumbing Insulation 09-19

22 08 00 Commissioning of Plumbing Systems 11-16

22 11 00 Facility Water Distribution 05-21

22 13 00 Facility Sanitary and Vent Piping 09-20

22 14 00 Facility Storm Drainage 09-20

22 33 00 Electric Domestic Water Heaters 09-20

22 40 00 Plumbing Fixtures 09-15

DIVISION 23 – HEATING, VENTILATING, AND AIR

CONDITIONING (HVAC)

23 05 11 Common Work Results for HVAC 02-20

23 05 12 General Motor Requirements for HVAC and Steam

Generation Equipment

02-20

23 05 41 Noise and Vibration Control for HVAC Piping and

Equipment

02-20

23 05 93 Testing, Adjusting, and Balancing for HVAC 02-20

23 07 11 HVAC and Boiler Plant Insulation 02-20

23 08 00 Commissioning of HVAC Systems 02-20

23 09 23 Direct-Digital Control System for HVAC 09-11

23 21 13 Hydronic Piping 02-20

23 22 13 Steam and Condensate Heating Piping 02-20

23 31 00 HVAC Ducts and Casings 02-20

23 34 00 HVAC Fans 02-20

23 36 00 Air Terminal Units 02-20

23 37 00 Air Outlets and Inlets 02-20

23 40 00 HVAC Air Cleaning Devices 03-20

23 73 00 Indoor Air-Handling Units 03-20

23 82 16 Air Coils 03-20

DIVISION 26 – ELECTRICAL

26 05 11 Requirements for Electrical Installations 01-16

26 05 13 Medium-Voltage Cables 01-17

00 01 10-4

SECTION NO. DIVISION AND SECTION TITLES DATE

26 05 19 Low-Voltage Electrical Power Conductors and Cables 01-17

26 05 26 Grounding and Bonding for Electrical Systems 01-17

26 05 33 Raceway and Boxes for Electrical Systems 01-18

26 05 41 Underground Electrical Construction 01-18

26 05 73 Overcurrent Protective Device Coordination Study 01-18

26 08 00 Commissioning of Electrical Systems 11-16

26 09 23 Lighting Controls 01-18

26 12 19 Pad-Mounted, Liquid-Filled, Medium-Voltage Transformers 01-18

26 24 16 Panelboards 01-18

26 27 26 Wiring Devices 01-18

26 29 21 Enclosed Switches and Circuit Breakers 01-17

26 36 23 Automatic Transfer Switch 01-17

26 41 00 Facility Lightning Protection 01-17

26 43 13 Surge Protective Device 01-22

26 51 00 Interior Lighting 01-18

26 56 00 Exterior Lighting 01-18

DIVISION 27 – COMMUNICATIONS

27 05 11 Requirements for Communications Installations 09-19

27 05 26 Grounding and Bonding for Communications Systems 06-15

27 05 33 Raceways and Boxes for Communications Systems 10-18

27 08 00 Commissioning of Communications Systems 11-16

27 10 00 Control, Communication and Signal Wiring 06-15

27 11 00 Communications Equipment Room Fittings 06-15

27 15 00 Communications Structured Cabling 01-16

27 51 16 Public Address and Mass Notification Systems 10-18

27 52 23 Nurse Call and Code Blue Systems 10-18

DIVISION 28 – ELECTRONIC SAFETY AND SECURITY

28 05 00 Common Work Results for Electronic Safety and Security 04-18

28 05 28.33 Conduits and Backboxes for Electronic Safety and

Security

09-11

28 08 00 Commissioning of Electronic Safety and Security Systems 03-23

28 13 00 Physical Access Control System 10-11

28 16 00 Intrusion Detection System 10-11

28 23 00 Video Surveillance 09-11

28 31 00 Fire Detection and Alarm 10-11

DIVISION 31 – EARTHWORK

31 20 11 Earthwork (Short Form) 10-12

31 23 19 Dewatering 10-12

DIVISION 32 – EXTERIOR IMPROVEMENTS

32 05 23 Cement and Concrete for Exterior Improvements 08-16

32 12 16 Asphalt Paving 09-15

32 17 23 Pavement Markings 08-16

00 01 10-5

DIVISION 33 – UTILITIES

33 08 00 Commissioning of Site Utility Systems 11-16

33 46 13 Foundation Drainage 10-11