Site Visit Meeting Doc.docx
DOCX document 18 KB Posted
- Attached to
- Z2DA--* T4 554-23-108 Install Ladders and Platforms in Mechanical Areas (VA-23-00006335)
- Solicitation number
- 36C25923Q0086
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C25923Q0086 0005.docx | DOCX document | |
| Pictures Question 11.docx | DOCX document | |
| Questions Set 2.docx | DOCX document | |
| Ladder.pdf | ||
| PSN.docx | DOCX document | |
| 36C25923Q0086 0004.docx | DOCX document | |
| 36C25923Q0086 0003.docx | DOCX document | |
| S04-Site Visit Attendance.pdf | ||
| Questions.docx | DOCX document | |
| 36C25923Q0086 0002.docx | DOCX document | |
| 36C25923Q0086 0001.docx | DOCX document | |
| 11-AS-107 PVS Roof Ladder.pdf | ||
| Fisher House Mech Room Ladder.pdf | ||
| XX.AS.411 Bldg D F Roof Access Detail.pdf | ||
| 03-PP-100-B DS-102 Vault Ladder.pdf | ||
| Bldg D Upper Roof Access 2.jpg | JPG image | |
| 13-PP-102-A Vault Lid Replacement.pdf | ||
| Combined Spec.pdf | ||
| PVS Elevator Machine Room on Roof.jpg | JPG image | |
| 36C25923Q0086.docx | DOCX document | |
| Bldg F Upper Roof Access.jpg | JPG image | |
| Bldg D Upper Roof Access.jpg | JPG image | |
| 03-AS-104-B Bldg D Upper Roof Access.pdf | ||
| 03-AS-104-A Bldg F Upper Roof Access.pdf |
Show all 24
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Pre-Bid Meeting
FOR
The contractor is to provide all labor, tools, materials, equipment and supervision for the Ladders and Platform Installation in Mechanical Areas at the Rocky Mountain Regional VAMC-ECHCS.
Location: RMR VAMC-ECHCS, 1700 N Wheeling St, Aurora CO 80045
AGENDA:
· Introduction of Christina Beeler-Blackburn CO, Mark Blehm COR, and Elia Ruiz Manzo CS
· The pre-bid meeting/site walk is not mandatory
· QUESTIONS During site visit MUST BE WRITTEN DOWN
· Address where to send Quote:
· Electronic submissions to Elia-Laritza.Ruiz-Manzo@va.gov
· Pertinent Dates:
· Questions due on 12/07/2022 at 10AM MT. Any questions submitted after this time will not be reviewed or answered! submit to Elia-Laritza.Ruiz-Manzo@va.gov
· Quotes due on 12/16/2022 at 10AM MT via email
· Prospective bidders are prohibited from attempting to gain information by inquiring with VA employees about project other than through written questions submitted to Contracting Officer.
· Prospective bidders are prohibited from visiting site other than through formal invitation by Contracting Officer.
· Attendees of walk-through are to stay as a group while walking to various locations and are to leave the future project site once the walk-through is concluded
· Masks are required at all times while on VA property. Entrance screenings will be conducted each day.
· Confirmation of construction range is between $25,000.00 and $100,000.00
· Contractor shall begin performance within 10 days after Notice To Proceed (NTP) and complete within 60 calendar days.
· Post Award Compliance:
· Compliance with Davis Bacon Wages and Application wage determination shall be expected of the contractor. The contractor can submit their weekly certified payrolls with their monthly invoice.