36C25922R0089_1.docx

DOCX document 2 MB Posted

Attached to
Z2DA--T2 DB 442-22-004 Add Lightning Protection to campus (VA-22-00068380)
Solicitation number
36C25922R0089
Issued by

About this file

This federal solicitation seeks design, installation, testing, verification, and commissioning services for a lightning protection system at the Cheyenne VA Medical Center campus in Wyoming. The scope involves upgrading several buildings constructed in 1934 and registered as historical structures. Offerors must visit the site, submit qualifications and past performance, provide pricing on the attached form, and obtain verification from the VA's Center for Verification and Evaluation. Proposals are due by December 21, 2022. Award will be made based on past performance and price tradeoff procedures. The period of performance is 365 calendar days from notice to proceed. The solicitation identifies compliance requirements and standards including quality assurance, safety, security, and infection control measures.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

2014 AMBULATORY CARE, DENTAL, STAIRWAY, IT CLOSETS PROJECT

PROJECT NO. 442-14-06S

1. SOLICITATION NUMBER

2. TYPE OF SOLICITATION

3. DATE ISSUED

PAGE OF PAGES

4. CONTRACT NUMBER

5. REQUISITION/PURCHASE REQUEST NUMBER

6. PROJECT NUMBER

7. ISSUED BY

CODE

8. ADDRESS OFFER TO

a. NAME

b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date) 12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

12b. CALENDAR DAYS

13. ADDITIONAL SOLICITATION REQUIREMENTS:

STANDARD FORM 1442 (REV. 8/2014)

STANDARD FORM 1442

Prescribed by GSA-FAR (48 CFR) 52.236-1(d)

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

SOLICITATION

SOLICITATION

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

9. FOR INFORMATION

CALL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

SEALED BID (IFB)

NEGOTIATED (RFP)

11. The Contractor shall begin performance within ____________ calendar days and complete it within calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See _____________________________).

YES

NO

a.

Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________ (hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.

b.

An offer guarantee is, is not required.

c.

All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d.

Offers providing less than _______________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

36C25922R0089

X

442-22-004 36C259 Department of Veterans Affairs Network Contracting Office

NCO 19

6162 South Willow Drive, Suite 300 Greenwood Village CO 80111 joseph.wingfield@va.gov

Joseph Wingfield 303-712-5769 The contractor shall furnish all labor, equipment, materials, and supervision to procure services for design, install system continuity testing, verification and commissioning of a lighting protection system (LPS) at Cheyenne VAMC.

Project magnitude: between $500,000 and $1,000,000. The NAICS code is 236220 - Small Business size standard is $39.5 M

Important Notice: Apparent successful offerors must apply for and receive verification from the Department of Veterans Affairs Center for Verification and Evaluation (CVE) in accordance with 38 CFR Part 74 and VAAR 819.70 by submission of documentation of Veteran status, ownership and control enough to establish appropriate status. Offerors must be both VISIBLE and VERIFIED by the Department of Veteran Affairs CVE at the time of offer submission. Failure to be both VERIFIED by CVE and VISIBLE on VetBiz at the time of offer submission and contract award will result in the offeror’s proposal being deemed non-compliant. All offerors are urged to contact the CVE and submit the required documents to obtain CVE verification of their SDVOSB status if they have not already done so.

All questions in relation to this solicitation must be submitted in writing via e-mail to jsoeph.wingfield@va.gov and received no later than 2:00 PM MT, December 5, 2022.

A site visit shall be held on 29 November, 2022 at 10:00 AM MT. Prospective bidders will meet at building 11 2nd floor conference room.

Instructions, Conditions, and Notices to Offerors. All submitted proposals must be received in email by the closing date and time. This solicitation closes December 21, 2022 at 2:00 PM MT.

Proposals shall be submitted via e-mail in accordance with Part I/Section B, to be considered for this project.

Proposals received in any other format will result in the offeror's proposal not receiving further consideration.

A hard copy bid bond must be received at the address listed in the instructions to offerors prior to the closing date and time.

X X

52.211-10 X

14:00

MST

12-21-2022 X

14. NAME AND ADDRESS OF OFFEROR

15. TELEPHONE NUMBER

16. REMITTANCE ADDRESS

CODE

FACILITY CODE

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

AMENDMENT

NUMBER

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE

21. ITEMS ACCEPTED:

22. AMOUNT

23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

ITEM

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c)( 41 U.S.C. 3304(a) (

26. ADMINISTERED BY

27. PAYMENT WILL BE MADE BY

PHONE:

FAX:

28. NEGOTIATED AGREEMENT

29. AWARD

Your Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.

shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME OF CONTRACTING OFFICER

TO SIGN

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE

BY

OFFER

AWARD

STANDARD FORM 1442 (REV. 8/2014) BACK

(Include ZIP Code) (Include area code) (Include only if different than Item 14.)

(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each) (Type or print) (4 copies unless otherwise specified) (Type or print) (Type or print) (Contractor is required to sign this document and return _______ copies to issuing office.)

(Contractor is not required to sign this document.)

(Must be fully completed by offeror) (To be completed by Government)

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

36C259 Department of Veterans Affairs Network Contracting Office

NCO 19

6162 South Willow Drive, Suite 300 Greenwood Village CO 80111

Department of Veterans Affairs Financial Service Center PO Box 149971 Austin TX 78714-9971

Table of Contents

PART I - THE SCHEDULE1
SECTION A - SOLICITATION/CONTRACT FORM1
A.1 SF 1442 SOLICITATION, OFFER, AND AWARD (Construction, Alteration, or Repair)1
A.2 SF 1442 SOLICITATION, OFFER, AND AWARD (CONSTRUCTION, ALTERATION, OR REPAIR)– BACK2
A.3 PRICE/COST SCHEDULE5
ITEM INFORMATION5
A.4 Scope of Work5
INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS11
2.1 52.216-1 TYPE OF CONTRACT (APR 1984)18
2.2 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014)18
2.3 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014)18
2.4 52.233-2 SERVICE OF PROTEST (SEP 2006)19
2.5 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995)20
2.6 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)20
2.7 VAAR 852.233-70 PROTEST CONTENT/ALTERNATIVE DISPUTE RESOLUTION (OCT 2018)21
2.8 VAAR 852.233-71 ALTERNATE PROTEST PROCEDURE (OCT 2018)22
REPRESENTATIONS AND CERTIFICATIONS22
3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (MAY 2022) (JUL 2020) (DEVIATION)22
3.2 52.204-24 REPRESENTATION REGARDING CERTAIN TELECOMMUNICATIONS AND VIDEO SURVEILLANCE SERVICES OR EQUIPMENT (NOV 2021)26
3.3 52.209-7 INFORMATION REGARDING RESPONSIBILITY MATTERS (OCT 2018)29
3.4 52.209-13 VIOLATION OF ARMS CONTROL TREATIES OR AGREEMENTS—CERTIFICATION (NOV 2021)30
3.5 52.229-11 TAX ON CERTAIN FOREIGN PROCUREMENTS—NOTICE AND REPRESENTATION (JUN 2020)32
GENERAL CONDITIONS33
4.1 52.204-19 INCORPORATION BY REFERENCE OF REPRESENTATIONS AND CERTIFICATIONS (DEC 2014)33
4.2 52.209-9 UPDATES OF PUBLICLY AVAILABLE INFORMATION REGARDING RESPONSIBILITY MATTERS (OCT 2018)34
4.3 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984) ALTERNATE I (APR 1984)35
4.4 52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION (SEP 2021)35
4.5 52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (NOV 2021)38
4.6 SUPPLEMENTAL INSURANCE REQUIREMENTS42
4.7 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)43
4.8 VAAR 852.203-70 COMMERCIAL ADVERTISING (MAY 2018)46
4.9 VAAR 852.204-70 PERSONAL IDENTITY VERIFICATION OF CONTRACTOR PERSONNEL (MAY 2020)46
4.10 VAAR 852.219-10 VA NOTICE OF TOTAL SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESS SET-ASIDE (JUL 2019) (DEVIATION)46
4.11 VAAR 852.219-74 LIMITATIONS ON SUBCONTRACTING—MONITORING AND COMPLIANCE (JUL 2018)48
4.12 VAAR 852.219-77 VA NOTICE OF LIMITATIONS ON SUBCONTRACTING—CERTIFICATE OF COMPLIANCE FOR SERVICES AND CONSTRUCTION (SEP 2021) (DEVIATION)49
4.13 VAAR 852.228-70 BOND PREMIUM ADJUSTMENT (JAN 2008)51
4.14 VAAR 852.228-72 ASSISTING SERVICE-DISABLED VETERAN-OWNED AND VETERAN-OWNED SMALL BUSINESSES IN OBTAINING BONDS (DEC 2009)51
4.15 VAAR 852.232-71 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS (INCLUDING NAS– CPM) (NOV 2018)51
4.16 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV 2018)54
4.17 VAAR 852.236-71 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (APR 2019)55
4.18 VAAR 852.236-79 CONTRACTOR PRODUCTION REPORT (APR 2019)56
4.19 VAAR 852.236-80 SUBCONTRACTS AND WORK COORDINATION (APR 2019)57
4.20 VAAR 852.242-70 GOVERNMENT CONSTRUCTION CONTRACT ADMINISTRATION (OCT 2020)57
4.21 VAAR 852.243-70 CONSTRUCTION CONTRACT CHANGES—SUPPLEMENT (SEP 2019)58
4.22 VAAR 852.270-1 REPRESENTATIVES OF CONTRACTING OFFICERS (JAN 2008)60
4.23 Wage Determination61
4.24 Attachments, Drawings and Specifications66

A.3 PRICE/COST SCHEDULE

ITEM INFORMATION

ITEM NUMBER
DESCRIPTION OF SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
1.00
JB
__________________
__________________

Project 442-22-004, Add Lightning Protection to campus.

Contract Period: Base POP Begin: 01-06-2023 POP End: 01-06-2024 PRINCIPAL NAICS CODE: 236220 - Commercial and Institutional Building Construction PRODUCT/SERVICE CODE: Z1DA - Maintenance of Hospitals and Infirmaries

GRAND TOTAL

A.4 Scope of Work

STATEMENT OF WORK

LIGHTNING PROTECTION SYSTEM

VA PROJECT NO. 442-22-004

1. Background In 2019 a Facility Condition Assessment was performed for Cheyenne VA Medical Center. As part of the assessment, it was noted that lightning protection was not in place and a lightning protection risk analysis was recommended. The risk analysis was performed according to the NFPA 780 calculator, resulting from that is the recommendation to install a lightning protection system in the locations identified in this Statement of Work.

2. Purpose

a) The purpose of this Statement of Work (SOW) is to procure services for design, install, system continuity testing, verification and commissioning of a lightning protection system (LPS) for the following buildings as represented on Figure 1 CVAMC Lightning Risk Assessment Drawing dated July 2020; RRTP, 1-CLC, 1-A, 1-B, 1-C, 45, 1-CA, 1-CX, 1-AR, 1-MRI, 11, 12, 13, 31 in addition to the photovoltaic parking canopies at the northeast property location as well as lightning protection for above ground fueling station and oxygen storage tank.

b) These buildings have been identified through a Lightning Protection Risk Assessment as required in the US Department of Veteran Affairs Electrical Design Manual (dated December 2019). Per these calculations, the buildings requiring lightning protection are listed in the attachment labeled “CVAMC Lightning Risk Assessment Data JMEdit”. The buildings needing lightining protection are identified in the accompanying aerial site plan (figure 1) located at the end of this SOW.

c) According to the Lighting Risk Assessment Outbuildings 4, 5, 6 7, 8 do not require lightning protection, however, will require a surge protection system as part of this work.

d) Many of the outbuildings and buildings on the original main campus are vintage 1934 and are registered as historical structures and any modifications must follow the VA guidelines per SHPO requirements. As a result, care and special treatment must be given to attaching the lightning protection system to the clay tile roofs without damaging or compromising the integrity of the structures or historical features.

e) Implementation of the LPS will be according to a Contractor furnished Project Phasing plan such that the tallest buildings will be provided with the LPS before the others. Contractor must furnish their phasing plan along with their bids in addition to preliminary locations of all downlead conductors, ground loops, ground rods and ground wells. Successful bidders must also submit detailed construction drawings and equipment shop drawings for approval prior to commencing any construction.

All outages and shutdowns must be closely coordinated with the Contracting Officer Representative (COR) with minimum 20 days’ notice, per the specification requirements.

This SOW is provided in order to construct the project as outlined herein, in the construction drawings (including any addendums), and specifications. All work must be planned and scheduled to minimize the construction activity impact on the operation of the medical center. All work must be conducted with strict adherence to Cheyenne Medical Center and Veteran’s Health Administration regulations and infection control requirements.

3. Scope of Work

This scope of work must include ALL work associated with the Lightning Protection installation and implementation, surge protection of identified outbuildings and associated work including but not limited to; verification of existing condition, utility locates prior to digging/excavation, trenching, compaction, compaction tests, asphalt cutting and patching, replacement of sod where applicable, roof penetrations (according to roof manufacturer’s recommendations in order to maintain warranties), gypsum board cutting and patching, texture, prime and paint where required for downlead conductors, concrete cutting and patching where applicable, as-built drawings of LPS, manufacturer closeout information, preventative maintenance.

Below is a rough outline of the sscope of the associated work:

a) Phase Visit the site and each building individually, survey and ascertain the conditions of the roof and any roof-mounted equipment which may need to be protected and connected to the LPS. Submit a report with photos of any pertinent areas or conditions. In the report, compile the data from all the buildings that have been identified for receiving an LPS.

b) Phase Submit construction documents indicating the layout of the designed LPS including details for each building. The basis of design for the structures will be a UL Master Label D Franklin type System. The LPS will consist of roof-mounted air terminals, main and downlead conductors, ground rods and ground test-wells. Roof mounted mechanical equipment will also be bonded to the LPS. The LPS will be bonded to the electrical service ground. In addition, the grounding must be verified, and new test ground wells installed in several locations or to a ground loop. The downlead conductors must be bonded at each location to the building service ground. Downlead conductors will be concealed in the exterior building walls.

c) Confirm that the LPS complies with NFPA 780 – Standard for the Installation of Lightning Protection Systems, and NFPA 70 – National Electrical Code.

4. Contractor Responsibilities

Contractor must supply all labor, and materials and equipment necessary to provide a complete and working system as outlined in the construction documents.

It is the responsibility of the Contractor to properly assess the contract documents and existing site conditions for the installation of the work.

a) Contractor must assess the contract drawings for the installation of the work as called out in the drawings and specifications. Contractor and/or Sub-contractors must be responsible for timely and accurate determination of work to be performed.

b) If there is a discrepancy between the specifications and the drawings, the specifications or the more stringent condition must apply.

c) Contractor and/or Sub-contractors must be responsible for reviewing all drawings and specifications and must submit Requests for Information (RFI’s) directed to the VAMC’s Contracting Officer for any discrepancies or clarifications needed to provide a complete and working system prior to the bidding of the work.

d) Contractors must adhere to the VAMC’s facility security requirements, including preparation of a fire safety plan, protection of all existing facility improvements and coordination with the COR.

e) All requests for any clarification must be forwarded by the VAMC’s Contracting Officer (CO) and copy the Contracting Officer Representative (COR).

f) Contractor and/or Sub-contractors must be responsible for the accuracy and scope of the specifications, drawings, and cost estimates in relation to areas or items addressed in this SOW. Any deficiencies in the documents must be brought to the attention of the Contracting Officer prior to bid receipt.

g) Contractor and/or Sub-contractors must perform all necessary investigations and work to determine and verify work can be performed as specified.

h) Contractor and/or Sub-contractors must provide all materials and equipment as well as installation as required in the specifications and drawings.

i) Contractor and/or Sub-contractors must provide material submittals to the Engineer of Record and COR for review and approval prior to purchase or installation.

j) Contractor and/or Sub-contractors are responsible for providing all tools and equipment necessary to perform this work.

k) The medical center must remain operational throughout the construction period. Any required shutdowns must be the coordinated through the COR and a minimum of 20 days prior to the proposed date of the shutdown.

l) All work performed and specified must comply with applicable Local, State, and Federal code requirements, and VA Master Construction Specifications. It is the responsibility of the Contractor to understand and comply with all applicable municipal, county, state, and federal codes, laws, ordinances, standards, rules and regulations.

m) The Contractor will work under the identified phasing schedule and if there are any deviations the contractor will seek approval from the COR.

n) The contractor must meet all specifications and approved drawings.

o) The contractor will be held responsible for any damages to VA property and must replace any damage in full.

p) The contractor must meet the safety requirements of OSHA and VA.

q) The contractor must meet all deadlines for construction.

r) The contractor must identify to the COR any possible problems and or deficiencies if they foresee a future problem related to the construction of the project.

5. Safety & Training:

a) Comply with the requirements of the Div. 01 Safety Requirement’s specification.

b) A competent person must always be on site who has completed OHSA’s 30-hour construction safety course per VA directive 2011-036. All other employees of general contractor must at a minimum has completed the OSHA 10-hour construction worker course and /or other relevant competency training, as determined by VA CP with input from the ICRA team.

c) Submit training records of all such employees for approval before the start of work.

6. Security Requirements:

a) THE CONTRACTOR MUST COMPLY WITH AGENCY PERSONAL IDENTITY VERIFICATION PROCEDURES IDENTIFIED IN THE CONTRACT THAT IMPLEMENT HOMELAND SECURITY PRESIDENTIAL DIRECTIVE-12 (HSPD-12), OFFICE OF MANAGEMENT AND BUDGET (OMB) GUIDANCE M-05-24, AND FEDERAL INFORMATION PROCESSING STANDARDS PUBLICATION (FIPS PUB) NUMBER 201.

b) THE CONTRACTOR MUST INSERT THIS CLAUSE IN ALL SUBCONTRACTS WHEN THE SUBCONTRACTOR IS REQUIRED TO HAVE ROUTINE PHYSICAL ACCESS TO A FEDERALLY CONTROLLED FACILITY AND/OR ROUTINE ACCESS TO A FEDERALLY CONTROLLED INFORMATION SYSTEM.

c) Every worker must wear a valid VA ID badge at all times to work on this site. The VA Police will issue day badges to workers who produce valid IDs. Right-to-work documentation will be required for workers who are not US citizens.

7. Infection Control Requirements:

a) All personnel involved in the construction or renovation activity must be educated and trained in infection prevention measures. The contractor is responsible for ensuring compliance with this training requirement.

b) Waste materials must be removed in containers with tightly fitting lids or covers that are taped in place and are wet wiped down before removal.

c) Implement the requirements of VAMC’s Infection Control Risk Assessment (ICRA). Infection Prevention and/or Safety personnel may monitor dust in the vicinity of the construction work and require the Contractor to take corrective action immediately if the safe levels are exceeded.

d) Establish and maintain a dust control program as part of the contractor’s infection preventive measures in accordance with the VA requirements.

e) All equipment, tools, material, worker’s clothing, etc. transported through occupied areas must be made free from dust and moisture by vacuuming and wipe down prior to entering all existing hospital areas.

f) Vacuum and wet mop all transition areas from construction to the occupied medical center at the end of each workday. Vacuum must utilize HEPA (High Efficiency Particulate Accumulator) filtration. Using a HEPA vacuum, clean inside the barrier and vacuum ceiling tile prior to replacement. Any ceiling access panels opened for investigation beyond sealed areas must be sealed immediately when unattended.

g) Medical Center Infection Control personnel may monitor for micro-organisms associated with construction dust (e.g. aspergillosis) as appropriate during construction. A baseline of conditions may be established by the medical center prior to the start of work and periodically during the construction stage to determine impact of construction activities on indoor air quality.

h) Construction areas must maintain a sealed barrier between the construction areas and the working areas of the hospital. Above ceiling spaces must be sealed to the deck above in order to achieve an isolated workspace.

i) The construction areas are “Infection Control-Class III/IV” areas and require negative pressure to be maintained during construction activity. The Contractor must establish containment to accomplish an area pressure of negative 0.01 in. WC. The VA has two portable containment units that may be available for use for smaller work areas. See the attached Infection Control sheet.

j) New construction ductwork must follow specification requirements for sealing off during construction.

k) There must be no standing water during construction. This includes water in equipment drip pans and open containers within the construction areas. All accidental spills must be cleaned up and dried within 12 hours. Remove and dispose of porous materials that remain damp for more than 72 hours.

l) All work will be performed per the Contractor submitted and approved VA schedule, updated on a weekly basis, and the COR must be notified at least 20 days in advance the proposed areas that will undergo construction. All scheduling of areas will be coordinated with the relevant hospital personnel by the COR to minimize impact to normal hospital functions. Coordination to include, but not limited to: Office of Information and Technology, Biomed Electronics Technician, and O&M Electrician.

m) Fire sprinkler lines will be down less than four hours unless otherwise approved by the COR. All sprinkler line shutdowns must be coordinated with the COR at least 2 weeks in advance.

n) Final Cleanup:

1. Upon completion of project, or as work progresses, remove all construction debris from above ceiling, vertical shafts and utility chases that have been part of the construction.

2. Perform HEPA vacuum cleaning of all surfaces in the construction area. This includes walls, ceilings, cabinets, furniture (built-in or free standing), partitions, flooring, etc.

3. All work performed cleaned by the Contractor per Cheyenne VA hospital standards prior to turning the area over for use by the VA.

8. Place of Performance

VA Medical Center, Cheyenne 2360 E. Pershing Blvd, Cheyenne, WY 82001

9. Hours of Work

a) WSee the Phasing Plan for any required night and weekend work. This work must be coordinated with the COR. All other work is expected to conform to customer agency normal operation hours of Monday through FFriday from 7:00am – 4:30pm (MST).

b) Work requiring shutdown, interruption, infection control, or potential interruption of power to critical areas of the Medical Center will require extensive coordination and planning with the COR and will require at least 20 days’ notice. Major shutdowns will have to occur on weekends.

10. Schedule and General Requirements

Construction must be completed 365 calendar days from Notice to Proceed. This period of performance includes considerations for long lead equipment times and phasing of the project.

Federal Legal Holidays: The following Federal legal holidays are observed by this facility:

New Year’s DayJanuary 1
Martin Luther King’s BirthdayThird Monday in January
President’s DayThird Monday in February
Memorial DayLast Monday in May
JuneteenthJune 19
Independence DayJuly 4
Labor DayFirst Monday in September
Columbus DaySecond Monday in October
Veteran’s DayNovember 11
Thanksgiving DayFourth Thursday in November
Christmas DayDecember 25

11. Historic Preservation

Where the Contractor or any of the Contractor's employees, prior to, or during the construction work, are advised of or discover any possible archeological, historical and/or cultural resources, the Contractor must immediately notify the COR verbally, and then with a written follow up.

Figure 1: CVAMC Lightning Risk Assessment aerial site plan.

- END OF SOW-

INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS

PART I - INSTRUCTIONS, CONDITIONS AND NOTICES TO OFFERORS

PART I/SECTION A – REQUEST FOR PROPOSAL

I.1A JOINT VENTURES

If submitting an offer as a joint venture as defined by P.L. 109-461 AND Department of Veterans Affairs I.L. 049-06-4, http://www.vetbiz.gov/library/jtventure.pdf , an offeror must provide a copy of the joint venture agreement specific to the project that is consistent with the percentage of required work and net proceed. Additionally, the offeror must provide a breakdown or labor of which is to be performed by the SDVOSB firm and that which is performed by the small business joint venture firm and that which is sub-contracted. All Joint Ventures will be required to be registered and verified as an entity in VETBIZ prior to award.

I.2A SELECTION PROCEDURES

This acquisition will be a competitive acquisition utilizing FAR Part 15 source selection employing tradeoff source selection procedures. By submission of its offer, the offeror accedes to all solicitation requirements, including terms and conditions, representations, and certifications. All such offers shall be treated equally except for their prices and performance records. Failure to meet a requirement may result in an offer being determined non-compliant. It is the intent of the Government to award without discussions; however, the Government will reserve the right to have discussions if such are needed.

I.3A PRE-PROPOSAL SITE VISIT

See SF 1442, Block 10 and FAR Provision 52.236-27, Site Visit (Construction) of this solicitation. Please leave extra time to complete COVID-19 screening process when entering the building. Masks are required to be worn by all employees and contractors while on VA property.

I.4A SELECTION CRITERIA

This acquisition will utilize the tradeoff process in accordance with FAR 15.101-1. This process permits tradeoffs between non-cost factors and cost/price and allows the Government to accept other than the lowest priced proposal or other than the highest rated proposal to achieve a best value contract award based on established evaluation criteria. Inherent in this process is the necessity to make tradeoffs considering the non-cost strengths and weaknesses, risks, and the cost (or price) offered in each proposal.

The source selection process will be conducted utilizing FAR part 15.101-1 Trade-off Process Source Selection Procedures with Special Standards of Responsibility. Offers will be evaluated using the following evaluation factors:

Factor 1 – Past Performance Factor 2 – Price

In addition to the general standards of responsibility found at FAR 9.104-1, in accordance with FAR 9.104-2, the special standards of responsibility described below apply to this procurement. Offerors who fail to meet any special standard of responsibility will not be eligible to receive contract award.

Past performance will be evaluated on a basis of significantly more important than, cost or price.

Past Performance Evaluation For Factor 1, based on the evaluation of all recent and relevant past performance for an offeror, an overall performance confidence rating shall be assigned. The performance confidence ratings are defined below:

ASSESSMENT
DESCRIPTION
Substantial Confidence
Based on the offeror’s recent/relevant performance record, the Government has a high expectation that the offeror will successfully perform the required effort.
Satisfactory Confidence
Based on the offeror’s recent/relevant performance record, the Government has a reasonable expectation that the offeror will successfully perform the required effort.
Limited Confidence
Based on the offeror’s recent/relevant performance record, the Government has a low expectation that the offeror will successfully perform the required effort.
No Confidence
Based on the offeror’s recent/relevant performance record, the Government has no expectation that the offeror will be able to successfully perform the required effort.
Unknown Confidence (Neutral)
No recent/relevant performance record is available, or the offeror’s performance record is so sparse that no meaningful confidence assessment rating can be reasonably assigned.

Note: In the case of an offeror without a record of past performance or for whom information on past performance is not available or so sparse that no meaningful past performance rating can be reasonably assigned, the offeror may not be evaluated favorably or unfavorably on past performance. Therefore, the offeror shall receive an unknown confidence (neutral) performance confidence rating.

(a) Aspects of Past Performance Evaluation. The past performance evaluation is an assessment based on the offeror’s record of relevant and recent past performance information that pertain to the products and/or services outlined in the solicitation requirements. There are two aspects of the past performance evaluation.

(1) The first is to evaluate whether the offeror’s present/past performance is relevant or not relevant to the effort to be acquired. The criteria to establish what is relevant is unique to each source selection.
(2) The second aspect of the past performance evaluation is to determine how well the contractor performed on the contracts. The past performance evaluation performed in support of a current source selection does not establish, create, or change the existing record and history of the offeror’s past performance on past contracts; rather, the past performance evaluation process gathers information from customers on how well the offeror performed those past contracts. In addition, the Government reserves the right to obtain information for use in the evaluation of past performance from all sources including sources outside of the Government. Other sources may include, but are not limited to, past performance information retrieved through the Past Performance Information Retrieval System (PPIRS) using all CAGE/DUNS numbers of Contractors who are part of a partnership or joint venture identified in the Offeror’s proposal, inquiries of owner representative(s), Federal Awardee Performance and Integrity Information System (FAPIIS), Electronic Subcontract Reporting System (eSRS), and any other known sources not provided by the Offeror.
(b) Source Selection Evaluation Board (SSEB) members will review past performance information to determine the quality and usefulness as it applies to the performance confidence assessment.

Adverse past performance is defined as past performance information that supports a less than satisfactory rating on any evaluation element or any unfavorable comments received from sources without a formal rating system.

Factor 1-Past Performance

(a) Solicitation Submittal Requirements:

Offerors shall provide a maximum of five (5) recent and relevant projects (as defined below) to demonstrate their ability to perform the proposed work identified within the Specifications, drawings, and Statement of Work. If a completed Contractor Performance Assessment Reporting System (CPARS) evaluation is available, it shall be submitted. The Government will evaluate past performance based upon sources available to the contracting officer that may include Past Performance Information Retrieval System (PPIRS), Federal Awardee Performance and Integrity Information System (FAPIIS) and Electronic Subcontract Reporting System (eSRS). IF THERE IS NOT A PAST PERFORMANCE EVALUATION IN PPIRS or FAPPIIS, then the offeror shall submit Past Performance Questionnaires (PPQ) for each project. Offerors shall not incorporate by reference into their proposal PPQs previously submitted for other RFPs. However, this does not preclude the Government from utilizing previously submitted PPQ information in the past performance evaluation. If the offeror is unable to obtain a completed PPQ from a client for a project(s) before proposal closing date, the offeror shall complete and submit with the proposal the first page of the PPQ, which will provide contract and client information for the respective project(s). The Government may make reasonable attempts to contact the client noted for that project(s) to obtain the PPQ information. However, offerors should follow-up with clients/references to help ensure timely submittal of questionnaires. If the client requests, questionnaires may be submitted directly to the Government’s point of contact, Joseph Wingfield, joseph.wingfield@va.gov.

Recency – a recent project is defined as being completed within five years of the due date of this solicitation.

Relevant – includes performance of efforts in a project of renovation or remodeling that include general construction in an active medical facility that are similar or greater in scope, magnitude, and complexity than the effort described in this solicitation.

Offerors are cautioned to submit enough information in the format specified in the solicitation. Offerors may be asked to clarify certain aspects of their proposal (for example, the relevance of past performance information) or respond to adverse past performance information to which the offeror has not previously had an opportunity to respond. Adverse past performance is defined as past performance information that supports a less than satisfactory rating on any evaluation element or any unfavorable comments received from sources without a formal rating system. Communication conducted to resolve minor or clerical errors will not constitute discussions and the contracting officer reserves the right to award a contract without the opportunity for proposal revision.

(b) – Basis of Evaluation:

The contracting officer shall review recent and relevant performance information on each offeror based on past efforts provided by the offeror and may obtain data independently from other government and commercial sources. Past performance regarding predecessor companies, key personnel who have relevant experience, or sub-contractors that will perform major or critical aspects of the requirement will not be considered as highly as past performance information for the principal offeror. Offerors with no past performance history or the offeror’s performance record is so limited that no confidence assessment rating can be reasonably assigned shall receive the rating "Unknown Confidence," meaning the rating is treated neither favorably nor unfavorably.

Initially offers shall be ranked according to price, including any option prices if applicable. The lowest price offer’s past performance shall be evaluated to determine its performance confidence rating.

If the lowest priced evaluated offer is judged to have a Substantial Confidence performance assessment, that offer represents the best value for the government and the evaluation process stops at this point. Award shall be made to that offeror without further consideration of any other offers.

If the lowest price offer does not receive a Substantial Confidence performance confidence rating, the past performance evaluation continues until an offeror’s past performance is judged to have a Substantial Confidence performance rating. The Government reserves the right to award a contract to other than the lowest priced offeror if the lowest priced offeror is judged to have a performance confidence assessment of "Satisfactory Confidence" or lower. In that event, the Source Selection Authority shall make an integrated assessment best value award decision.

Factor 2 – Price:

(a) Solicitation Submittal Requirements:

· Standard Form 1442, Solicitation Offer and Award

· All pages of the SF1442 Continuation Sheet

· Submit pricing on the attached Calculation Worksheet

(b) Basis of Evaluation: The Government will evaluate price based on the total price. Analysis will be performed by one or more of the following techniques to ensure a fair and reasonable price:

· Comparison of proposed prices received in response to the RFP

· Comparison of proposed prices with the IGCE.

· Comparison of proposed prices with available historical information.

Special Standard of Responsibility Solicitation Submittal Requirements:

The Offeror shall submit the following information: (For a partnership or joint venture, the following submittal requirements are required for each Contractor who is part of the partnership or joint venture and for the entity itself. EMR shall not be submitted for subcontractors.)

1. OSHA or EPA Violation(s):

Offerors shall provide Summary of Work-Related Injuries and Illnesses, affirming that the Offeror has no more than three serious, or one repeat, or one willful OSHA or EPA violation(s) in the past 3 years.

2. Experience Modification Rate (EMR):

Offerors shall provide documentation to show that the offeror has an Experience Modification Rate (EMR) of equal to or less than 1.0.

Offerors who fail to meet any special standard of responsibility will not be eligible to receive contract award.

PART I/SECTION B - INSTRUCTIONS, CONDITIONS AND NOTICES TO OFFERORS

I.1B COST RANGE: Between $500,000.00 and $1,000,000.00

I.2B GENDER: Wherever the masculine gender is used in this solicitation and contract documents, it shall be considered to include both masculine and feminine.

I.3B METRIC PRODUCTS:

Products manufactured to metric dimensions will be considered on an equal basis with those manufactured using inch-pound units, providing they fall within the tolerance specified using conversion tables contained in the latest revision of Federal Standard No. 376, and all other requirements of this document are met.

If a product is manufactured to metric dimensions and those dimensions exceed the tolerance specified in the inch-pound units, a request should be made to the Contracting Officer to determine if the product is acceptable. The Contracting Officer, in concert with the Contracting Officer’s Representative (COR), will accept or reject the product.

I.4B REQUESTS FOR INFORMATION:

All requests for information must be submitted in writing to the Contracting Officer for action no later than the date shown in Block 10 of the Standard Form 1442, Solicitation, Offer and Award.

I.5B PROPOSAL REQUIREMENTS

General – Both past performance information and price proposal shall be submitted in response to this solicitation. Proposals shall be submitted via email joseph.wingfield@va.gov. Emails are limited to 15 MB. The proposal, in its entirety, shall be one email (one attachment for price proposal, one attachment for LOS certification, and one attachment for past performance information) not to exceed 15MB. Failure to submit in the format required and clearly address those factors may result in rejection of the offer. An original Bid Bond, in the amount of twenty (20%) percent (but not to exceed $3,000,000) of the bid price shall be mailed to the address listed in block 8 of the SF1442 and be received at the address no later than the closing date and time. Failure to furnish the required bid guarantee in the proper form and amount, by the time set for due date, will require rejection of the proposal in all cases except those listed in FAR 28.101-4, and may be cause for rejection even then. SEE FAR Provision 52.228-1, Bid Guarantee, of this Solicitation. Electronic copies of the proposals will be time/date stamped by Microsoft Outlook upon receipt of email. Further details on electronic submission are outlined below.

Proposals shall be received by 2:00 PM MT on December 21, 2022. There will be no public opening of the proposals. Submit proposals to: joseph.wingfield@va.gov.

Submit bid bonds to:

Department of Veterans Affairs

NCO 19

ATTN: Joseph Wingfield 6162 S Willow Dr., Ste 300 Greenwood Village, CO 80111

Past performance information and price sections of the offeror’s proposal will be evaluated independently. Offerors shall include all required Representations and Certifications and complete their registration in System for Award Management (SAM). See FAR 52.204-7 and 52.204-8, of this solicitation.

Important Notice: Apparent successful offerors must apply for and receive verification from the Department of Veterans Affairs Center for Verification and Evaluation (CVE) in accordance with 38 CFR Part 74 and VAAR 819.70 by submission of documentation of Veteran status, ownership and control enough to establish appropriate status. Offerors must be both VISIBLE and VERIFIED by the Department of Veteran Affairs CVE at the time of offer submission. Failure to be both VERIFIED by CVE and VISIBLE on VetBiz at the time of offer submission and contract award will result in the offeror’s proposal being deemed non-compliant. All offerors are urged to contact the CVE and submit the required documents to obtain CVE verification of their SDVOSB status if they have not already done so.

I.6B PROPOSAL REVISIONS

If it is determined to be necessary, proposal revisions will be requested from the offers received. The Contracting Officer may identify those offerors, whose proposals are within the competitive range based upon the selection criteria identified in this solicitation. Negotiations may be conducted with those firms falling within the competitive range, after which proposal revisions may be requested. Offerors submitting proposal revisions will not be required to re-submit any documents which are unchanged from their proposals. They should provide necessary changes to individual paragraphs, as briefly as possible, together with the Table of Contents that clarifies where within the initial proposal the additional information and/or changed document would be placed. A new bid bond shall be submitted only if the final cost proposal revisions are greater than its initial cost proposal.

1.7B REQUIREMENTS FOR ELECTRONIC SUBMISSION OF OFFER

Unless paper offers are specifically authorized in an individual solicitation, all responses to solicitations must be submitted electronically as described below. Responses submitted in a paper form are unacceptable. Failure to comply with this requirement may jeopardize the possibility of receiving an award for the contract due to noncompliance with the terms of the solicitation. You must submit your electronic offer, and any supplemental information (such as spreadsheets, backup data, technical information), using any of the electronic formats and media described below.

In addition, contractors are notified of the award via an electronic Notice of Award e-mail. The award document will be attached to the Notice of Award e-mail.

Acceptable Electronic Formats (Software) for Submission of Offers

1. Files readable using the current Microsoft© Office version Products: Word, Excel, PowerPoint, or Access. Please see security note below for caution regarding use of macros. When submitting construction drawings contractors are required to submit one set in AutoCAD and one set in Adobe PDF. (purpose: contracting can open the PDF version and engineering can open AutoCAD files).

2. Files in Adobe© PDF (Portable Document Format) Files: When scanning documents scanner resolution should be set to 200 dots per inch, or greater.

3. Another electronic format. If you wish to submit an offer using another format other than described in these instructions, e-mail the Contracting Officer who issued the solicitation. Please submit your request at least ten (10) calendar days before the scheduled closing date of the solicitation. Request a decision as to the format acceptability and make sure you receive approval of the alternate format before using it to send your offer.

4. Please note that we can no longer accept .zip files due to increasing security concerns.

E-mail Submission Procedures: For simplicity in this guidance, all submissions in response to a solicitation will be referred to as offers.

a. Subject Line: Include the solicitation number, name of company, and closing date of solicitation. Use only one of the terms Quotation, Offer, Proposal, or Bid depending on the solicitation type.

b. Size: Maximum size of the e-mail message shall not exceed five (5) megabytes. Only one email is permitted unless otherwise stated in this solicitation or in writing by the Contract Officer submitting the solicitation.

c. Unless approved by the contracting officer: DO NOT submit a link to your PDF documents. Please submit your request in an email for other electronic format at least ten (10) calendar days before the scheduled closing date of the solicitation. Request a decision as to the format acceptability and ensure you receive approval of the alternate format before using it to send your offer.

Each electronic offer must also include a signed and scanned SF-1442, Solicitation, Offer, and Award (Construction, Alteration, or Repair)

The Microsoft Outlook © Email time/date stamp will be used to date and time stamp offers for the official record of receipt for the submission. The date and time stamp in recipient’s “inbox” is the official record of receipt.

Security Issues, Late Bids, Unreadable Offers

1. Late submission of offers is outlined at FAR 52.215-1(c)(3). Particular attention is warranted to the portion of the provision that relates to the timing of submission.

2. Please see FAR 15.207(c) for a description of the steps the Government shall take with regard to unreadable offers.

3. To avoid rejection of an offer, vendors must make every effort to ensure their electronic submission is virus-free. Submissions or portions thereof submitted and which the automatic system detects the presence of a virus or which are otherwise unreadable will be treated as “unreadable” pursuant to FAR 15.207(c).

4. The virus scanning software used by our e-mail systems cannot always distinguish a macro from a virus. Therefore, sending a macro embedded in an e-mail message or an e-mail attachment may cause the e-mail offer to be quarantined. You may send both the spreadsheet and the spreadsheet saved in PDF format to ensure that your proposal is readable.

5. Password protecting your offer is not permitted. The Contracting Officer will file the offer electronically which will allow access only by designated individuals.

2.1 52.216-1 TYPE OF CONTRACT (APR 1984)

The Government contemplates award of a Firm-Fixed-Price contract resulting from this solicitation.

(End of Provision)

2.2 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014) (a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements, of this solicitation.

(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.

(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.

(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.

(End of Provision)

2.3 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014)

(a) Definitions. "Commercially available off-the-shelf (COTS) item," "construction material," "domestic construction material," and "foreign construction material," as used in this provision, are defined in the clause of this solicitation entitled "Buy American—Construction…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .