3rd questions and Answers_Final.docx

DOCX document 15 KB Posted

Attached to
J041-- (CONS)Topeka AHU replacement, building 9, 2nd floor (VA-21-00059538)
Solicitation number
36C25921R0074
Issued by

View the file

Other files

File Type Posted
36C25921R0074 0008.docx DOCX document
36C25921R0074 0007.docx DOCX document
S06- 2nd Questions_Final.docx DOCX document
Site Visit Meeting Doc_2nd.docx DOCX document
S04- Topeka AHU_2nd site visit signin_20JUL2021.pdf PDF
36C25921R0074 0006.docx DOCX document
36C25921R0074 0005.docx DOCX document
S05- Questions and Answers.docx DOCX document
Pictures of space.pdf PDF
Second Floor HVAC.pdf PDF
S05- Questions and Answers.docx DOCX document
Second Floor Piping.pdf PDF
S04- Site Visit Attendance.pdf PDF
062-MH103-R.pdf PDF
36C25921R0074 0004.docx DOCX document
065-MP103_.pdf PDF
36C25921R0074 0003.docx DOCX document
36C25921R0074 0002.docx DOCX document
36C25921R0074 0001.docx DOCX document
36C25921R0074 Full Solicitation.docx DOCX document
SELF-PERFORMED CALCULATIONS.docx DOCX document
S02 Past Performance Questionnaire.docx DOCX document
36C25921R0074_1.docx DOCX document
Show all 23

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions 3

1. The HVAC unit do we get a size or model number of what is there?

The model was shown at the 2 site visits. Reference attachment “Pictures B”.

2. Are we upsizing the unit to a different size go with equal what is there?

Equal to what is in place. It needs to meet functionality and current space.

3. Lots of phasing this project does that mean this is night work and is area is fulling functional with workers? Night work not required

4. Are there curtain work hours? Hours are 7:30a-4p. work can’t start until 7:30a and must be out of the building at 4p

5. Are there any specs on the new VAV boxes? Or do we use what the manufacture recommends with the new AHU? There are no new VAV boxes on this contract. current ones in place will be used.

6. Will this requirement be responsible for disconnecting and reconnecting BMS to AHU equipment? The contractor is responsible for disconnecting and reconnecting. Johnson Controls is the BMS system, we do not have a POC for them. There requirements will need to be followed for reconnection.

7. Will nights and weekends work be required for this requirement? Night work or weekends not required at this time.

8. Will the government provide a space to house new equipment and materials for the project? you can park a trailer on site.

9. Some clients prefer that the past performance questionnaire come directly from you/CO of the requirement. Will you be able to send questionnaire to references and have them send responses directly to you? You can provide the questionnaire with my contact information and they can send directly to me. A blank form is included with the solicitation attachments.

10. Who is the POC for BMS? Johnson Controls is the BMS system, we do not have a POC for them. There requirements will need to be followed for reconnection.