Site Visit Meeting Doc.docx
DOCX document 18 KB Posted
- Solicitation number
- 36C25921Q0473
View the file
Other files
| File | Type | Posted |
|---|---|---|
| BLDG 38_AsbestosSurvey_022614.pdf | ||
| S06- Questions 2.docx | DOCX document | |
| 36C25921Q0473 0003.docx | DOCX document | |
| BLDG 38_roof AsbestosSurvey_041415.pdf | ||
| S05- Questions and Answers.docx | DOCX document | |
| 36C25921Q0473 0002.docx | DOCX document | |
| SOW - Board up and Secure Clermont campus_updated.docx | DOCX document | |
| 36C25921Q0473 0001.docx | DOCX document | |
| Bid Schedule_updated.docx | DOCX document | |
| Site Visit Attendance.pdf | ||
| 36C25921Q0473_1.docx | DOCX document | |
| Denver Decommissioning Window Boarding External Lighting.pdf | ||
| Reference - Pictues of Clermont Bldg Windows and MEP for B38 Wall 554-21-133.docx | DOCX document |
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Pre-Offer Site Visit Meeting 36C25921Q0473 Secure and Board up Clermont Campus at Denver VAMC
The contractor is to provide all labor, tools, materials, equipment, and supervision required to complete the construction of the Secure and Board up Clermont Campus at the Denver VA Medical Center. Work to include boarding up all accessible windows and doors.
Location: Denver VAMC
AGENDA:
· Introduction of Christina Beeler-Blackburn CS, Christopher Kolditz, COR
· The pre-offer meeting/site walk is not mandatory
· QUESTIONS During site visit MUST BE WRITTEN DOWN
· Address where to send RFQ:
· Electronic submissions to Christina.Beeler-Blackburn@va.gov
· Pertinent Dates:
· Questions due June 11, 2021 no later than 1:00 PM MT prior to closing of RFQ, any questions submitted after this time will not be reviewed or answered! Submit to Christina.Beeler-Blackburn@va.gov
· We’ll get the answers back to you timely
· Proposals due on 6/29/2021 at 10:30 AM MT via email
· Prospective offerors are prohibited from attempting to gain information by inquiring with VA employees about project other than through written questions submitted to Contracting Officer.
· Prospective offerors are prohibited from visiting site other than through formal invitation by Contracting Officer.
· Attendees of walk-through are to stay as a group while walking to various locations and are to leave the future project site once the walk-through is concluded.
· All VA campuses are Tobacco Free, including but not limited to, smokeless tobacco and vaping.
· Masks are to be worn at all times while on VA property.
· Confirmation of construction range is between $25,000 and $100,000.
· Bid Guarantee & Payment/Performance Bonds: Are required at 20% of bid price or $3,000,000.00 whichever is less, if the offer is over $150,000.
· Contractor shall begin performance within 10 days after Notice To Proceed (NTP) and complete within 90 days.
· Post Award Compliance:
· Compliance with Davis Bacon Wages and Application wage determination shall be expected of the contractor. The contractor can submit their weekly certified payrolls with their monthly invoice.