S05- Questions and Answers.docx

DOCX document 15 KB Posted

Attached to
Z1DA--(C)554-21-133 Board up and secure Clermont VAMC Campus (VA-21-00047767)
Solicitation number
36C25921Q0473
Issued by

View the file

Other files

File Type Posted
BLDG 38_AsbestosSurvey_022614.pdf PDF
S06- Questions 2.docx DOCX document
36C25921Q0473 0003.docx DOCX document
BLDG 38_roof AsbestosSurvey_041415.pdf PDF
36C25921Q0473 0002.docx DOCX document
SOW - Board up and Secure Clermont campus_updated.docx DOCX document
36C25921Q0473 0001.docx DOCX document
Bid Schedule_updated.docx DOCX document
Site Visit Attendance.pdf PDF
Site Visit Meeting Doc.docx DOCX document
36C25921Q0473_1.docx DOCX document
Denver Decommissioning Window Boarding External Lighting.pdf PDF
Reference - Pictues of Clermont Bldg Windows and MEP for B38 Wall 554-21-133.docx DOCX document
Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions

1. Please confirm that there is no Performance, Payment, or Bid Bond. Bonds are required for any offer of $150,000.00 or above.

2. Is there a Wage Determination? Yes. The Wage Determination is embedded in the solicitation document, which can be viewed through ‘Attachments” section of the solicitation on SAM.gov.

3. Will you be able to provide the blueprints of the window schedules showing their dimensions? We do not have the window schedules for the Bldgs.

4. Will we be able to set up a staging/ work area in different areas to do our saw cutting/misc. We will coordinate with the awarded contractor to set up staging/work areas but remember that either no or very limited electrical power will be available. Security of the site and Bldgs. must be maintained at all time by the contractor.

5. No specification for the project other than the SOW has been provided – it lists materials on A.4 SOW - 2.0 as “fire rated ½’’ plywood”. Will plywood meeting regulatory standard – Class A/Class 1 fire retardant (ASTM E-84) satisfy this requirement? Yes

6. The SOW requires cutting of utilities to construct the CMU wall at Building 38/Building 1 hallway. Can you confirm that all of these utilities can be cut so a solid floor to lid CMU wall can be constructed? All of the utilities in the hallway can be cut.