36C25919R0064-003.pdf
PDF 2 MB Posted
- Attached to
- Improve Patient Safety, 5P Grand Junction VAMC
- Solicitation number
- 36C25919R0064
About this file
36C25919R0064 S02 Specifications 02.pdf
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C25919R0064-0001001.pdf | ||
| 36C25919R0064-0001000.docx | DOCX document | |
| 36C25919R0064-001.docx | DOCX document | |
| 36C25919R0064-002.pdf | ||
| 36C25919R0064-005.docx | DOCX document | |
| 36C25919R0064-004.docx | DOCX document | |
| 36C25919R0064-000.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Grand Junction VA
Improve Patient Safety, 5P Project No.: 575-18-106
For the
Department of Veterans Affairs
Network Contracting Office 19
6162 South Willow Drive, Suite 300
Greenwood Village, CO 80111
BID DOCUMENTS
SPECIFICATIONS
08 / 24 / 2018
Grand Junction VAMC August 24, 2018
Improve Patient Safety Bid Documents
Grand Junction, CO 81501 Project No. 575-18-106
GUIDON DESIGN INC.
PROJECT CONTACTS:
OWNER: Grand Junction VA Medical Center
Attn: Rojelio Chavez, Bldg. 8, Engineering
2121 North Avenue, Grand Junction, CO 81501
Phone: 406-447-7836
Email: Rojelio.Chavez@va.gov
PROJECT LEAD: GUIDON DESIGN INC.
Attn: Stewart Whitcomb
905 N. Capitol Ave.
Indianapolis, IN 46204
Phone: 317-800-6388 x102
Email: swhitcomb@guidondesign.com
ISSUE DATE: August 24, 2018 mailto:swhitcomb@guidondesign.com
Improve Patient Safety, 5P Bid Documents
Grand Junction, CO 81501 Project No. 575-18-106
00 01 10-1
TABLE OF CONTENTS
Section 00 01 10
DIVISION 00 - SPECIAL SECTIONS DATE
00 01 15 List of Drawing Sheets 07-15
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 General Requirements 10-17
01 32 16 Network Analysis Schedules 02-15
01 33 23 Shop Drawings, Product Data, and Samples 05-17
01 42 19 Reference Standards 05-16
01 45 00 Quality Control 01-18
01 57 19 Temporary Environmental Controls 01-11
01 58 16 Temporary Interior Signage 07-15
01 74 19 Construction Waste Management 09-13
01 81 13 Sustainable Construction Requirements 10-17
DIVISION 02 – EXISTING CONDITIONS
02 41 00 Demolition 08-17
DIVISION 05 – METALS
05 40 00 Cold-Formed Metal Framing 05-16
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 92 00 Joint Sealants 10-17
DIVISION 08 - OPENINGS
08 14 00 Interior Wood Doors 02-16
08 31 13 Access Doors and Frames 02-16
08 51 13 Aluminum Windows 02-16
08 71 00 Door Hardware 01-16
08 80 00 Glazing 10-15
DIVISION 09 – FINISHES
09 06 00 Schedule for Finishes 04-15
09 29 00 Gypsum Board 11-14
09 91 00 Painting 01-16
Grand Junction, CO 81501 Project No. 575-18-106
00 01 15 - 1
SECTION 00 01 15
LIST OF DRAWING SHEETS
The drawings listed below accompanying this specification form a part of the contract.
Drawing No. Title
GI001 COVER SHEET AND INFORMATION
AS001 ARCHITECTURAL GENERAL INFORMATION AND PHASING
AS100 ARCHITECTURAL PLANS AND DETAILS
AS200 REFLECTED CEILING PLANS AND DOOR DETAILS
- - - END - - -
Grand Junction, CO 81501 Project No. 575-18-106 i
SECTION 01 00 00
GENERAL REQUIREMENTS
TABLE OF CONTENTS
1.1 SAFETY REQUIREMENTS
1.2 GENERAL INTENTION
1.3 STATEMENT OF BID ITEM(S)
1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
1.5 CONSTRUCTION SECURITY REQUIREMENTS
1.6 OPERATIONS AND STORAGE AREAS
1.7 ALTERATIONS
1.8 DISPOSAL AND RETENTION
1.9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT,
UTILITIES, AND IMPROVEMENTS
1.10 RESTORATION
1.11 PHYSICAL DATA
1.12 PROFESSIONAL SURVEYING SERVICES
1.13 LAYOUT OF WORK
1.14 AS-BUILT DRAWINGS
1.15 USE OF ROADWAYS
1.16 RESIDENT ENGINEER'S FIELD OFFICE
1.17 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT
1.18 TEMPORARY USE OF EXISTING ELEVATORS
1.19 TEMPORARY USE OF NEW ELEVATORS
1.20 TEMPORARY TOILETS
1.21 AVAILABILITY AND USE OF UTILITY SERVICES
1.22 NEW TELEPHONE EQUIPMENT
1.23 TESTS
1.24 INSTRUCTIONS
Grand Junction, CO 81501 Project No. 575-18-106 ii
1.25 GOVERNMENT-FURNISHED PROPERTY
1.26 RELOCATED ITEMS
1.27 STORAGE SPACE FOR DEPARTMENT OF VETERANS AFFAIRS EQUIPMENT
1.28 CONSTRUCTION SIGN
1.29 SAFETY SIGN
1.30 PHOTOGRAPHIC DOCUMENTATION
1.31 FINAL ELEVATION Digital Images
1.32 HISTORIC PRESERVATION
1.33 VA TRIRIGA CPMS
Grand Junction, CO 81501 Project No. 575-18-106
01 00 00 -1
SECTION 01 00 00
GENERAL REQUIREMENTS
1.1 SAFETY REQUIREMENTS
Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.
1.2 GENERAL INTENTION
A. Contractor shall completely prepare site for the work, construction operations, including demolition and removal of existing construction, and furnish labor and materials and perform work for Improve Patient
Safety in upgrading the windows, access hatches and door hardware as required by drawings and specifications.
B. Visits to the site by Bidders may be made only by appointment with the
Medical Center Engineering Officer.
C. Offices of Guidon Design Inc., as Architect-Engineers, will render certain technical services during construction. Such services shall be considered as advisory to the Government and shall not be construed as expressing or implying a contractual act of the Government without affirmations by Contracting Officer or his duly authorized representative.
D. Before placement and installation of work subject to tests by testing laboratory retained by Department of Veterans Affairs, the Contractor shall notify the COR in sufficient time to enable testing laboratory personnel to be present at the site in time for proper taking and testing of specimens and field inspection. Such prior notice shall be not less than three work days unless otherwise designated by the COR .
E. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.
Grand Junction, CO 81501 Project No. 575-18-106
01 00 00 -2
1.3 SCOPE OF BID ITEM(S)
A. ITEM I, BASE BID WORK: PROVIDE INTERIOR PSYCHIATRIC WINDOWS,
REPLACEMENT ACCESS HATCHES AND SELECTED DOOR HARDWARE FOR THE 5TH FLOOR
BEHAVIORAL HEALTH UNIT: Work includes general construction, alterations, administration, oversight, coordination, selective demolition, storage, infection control, and logistics necessary removal of existing structures and construction and certain other items.
ALL PATIENT ROOM CEILING HATCHES ARE BASE BID WORK
REPLACEMENT OF DOOR 5020 AND HARDWARE INSTALLATION IS BASE BID WORK
1. ___________________________________ Dollars ($___________).
1. ALTERNATE NO.A: OMIT INDICATED DOOR AND DOOR HARDWARE REPLACEMENT WORK.
DO NOT PROVIDE LABOR, MATERIALS, COORDINATION OR OVERSIGHT FOR DOOR
REMOVAL, SALVAGE, AND DOOR MODIFICATION TO UPGRADE HINGES TO CONTINUOUS
HINGE AT PATIENT ROOMS.
a. ADD____ DEDUCT____ NO CHANGE____ NOT APPLICABLE____.
b. __________________________________ Dollars ($___________).
c. ADD____ DEDUCT____ calendar days to adjust the Contract Time for this alternate.
2. ALTERNATE NO. B:_OMIT ACCESS PANEL/HATCH REPLACEMENT WORK. DO NOT
PROVIDE LABOR, MATERIALS, COORDINATION OR OVERSIGHT FOR STAINLESS STEEL
SECURITY HATCH REPLACEMENT, AND ASSOCIATED SELECTIVE DEMOLITION AND
INFECTION CONTOL IN CORRIDOR 5032, WALLS AND CEILING HATCHES.
a. ADD____ DEDUCT____ NO CHANGE____ NOT APPLICABLE____.
b. ___________________________________ Dollars ($___________).
c. ADD____ DEDUCT____ calendar days to adjust the Contract Time for this alternate.
3. ALTERNATE NO. C:_OMIT DOOR MODIFICATIONS AND WINDOW FROM SELECTED
SPACES. DO NOT PROVIDE LABOR, MATERIALS, COORDINATION OR OVERSIGHT FOR
SELECTIVE DEMOLITION, INTERIOR WINDOWS FOR ROOMS 5021, 5022, 5023,
CONTINUOUS HINGES FOR 5010A, 5011 AND 5012, AND ANY ASSOCIATED INFECTION
CONTROL.
Grand Junction, CO 81501 Project No. 575-18-106
01 00 00 -3
a. ADD____ DEDUCT____ NO CHANGE____ NOT APPLICABLE____.
b. ___________________________________ Dollars ($___________).
c. ADD____ DEDUCT____ calendar days to adjust the Contract Time for this alternate.
1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
A. Drawings and contract documents may be obtained in digital format from the website where the solicitation is posted. Additional copies will be at Contractor's expense.
1.5 CONSTRUCTION SECURITY REQUIREMENTS
A. Security Plan:
1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.
2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.
B. Security Procedures:
1. General Contractor’s employees shall not enter the project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.
2. Before starting work the General Contractor shall give one week’s notice to the Contracting Officer so that security arrangements can be provided for the employees. This notice is separate from any notices required for utility shutdown described later in this section.
3. No photography of VA premises is allowed without written permission of the Contracting Officer.
4. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the
Grand Junction, CO 81501 Project No. 575-18-106
01 00 00 -4 event of a national emergency. The General Contractor may return to the site only with the written approval of the Contracting Officer.
D. Key Control:
1. The General Contractor shall provide duplicate keys and lock combinations to the Contracting Officers Representative (COR for the purpose of security inspections of every area of project including tool boxes and parked machines and take any emergency action.
E. Document Control:
1. Before starting any work, the General Contractor/Sub Contractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of
“sensitive information”.
2. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.
3. Certain documents, sketches, videos or photographs and drawings may be marked “Law Enforcement Sensitive” or “Sensitive Unclassified”.
Secure such information in separate containers and limit the access to only those who will need it for the project. Return the information to the Contracting Officer upon request.
4. These security documents shall not be removed or transmitted from the project site without the written approval of Contracting
Officer.
5. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the VA.
6. Notify Contracting Officer and Site Security Officer immediately when there is a loss or compromise of “sensitive information”.
7. All electronic information shall be stored in specified location following VA standards and procedures using an Engineering Document
Management Software (EDMS).
Grand Junction, CO 81501 Project No. 575-18-106
01 00 00 -5
a. Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the
EDMS system.
b. “Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.
F. Motor Vehicle Restrictions
1. Vehicle authorization request shall be required for any vehicle entering the site and such request shall be submitted 24 hours before the date and time of access. Access shall be restricted to picking up and dropping off materials and supplies.
2. Contractors shall park off site.
1.6 OPERATIONS AND STORAGE AREAS
A. The Contractor shall confine all operations (including storage of materials, if permitted) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.
B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the
Contracting Officer and shall be built with labor and materials furnished by the Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the
Contractor and shall be removed by the Contractor at its expense upon completion of the work. With the written consent of the Contracting
Officer, the buildings and utilities may be abandoned and need not be removed.
C. The Contractor shall, under regulations prescribed by the Contracting
Officer, use only established roadways as authorized by the Contracting
Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The
Grand Junction, CO 81501 Project No. 575-18-106
01 00 00 -6
Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.
D. Working space and space available for storing materials shall be as shown on the drawings.
E. Workmen are subject to rules of Medical Center applicable to their conduct.
F. Execute work so as to interfere as little as possible with normal functioning of Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and Contractor's personnel, except as permitted by COR where required by limited working space.
1. Do not store materials and equipment in other than assigned areas.
2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by Department of
Veterans Affairs in quantities sufficient for not more than two work days. Provide unobstructed access to Medical Center areas required to remain in operation.
3. Where access by Medical Center personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment will be permitted subject to fire and safety requirements.
G. Phasing:
The Medical Center must maintain its operation 24 hours a day 7 days a week. Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses in operation occur.
It is the CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks. The work to be outlined shall include, but not be limited to:
Grand Junction, CO 81501 Project No. 575-18-106
01 00 00 -7
To insure such executions, Contractor shall furnish the COR with a schedule of approximate phasing dates on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the COR two weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof. Arrange such phasing dates to insure accomplishment of this work in successive phases mutually agreeable to
Medical Center Director, COR and Contractor, as indicated in the drawings on AS001.
H. All areas of Building(s) No. (s) 1 will be occupied by Medical Center personnel for the duration of the work:
1. Contractor shall take all measurements and provide all material necessary for protecting existing equipment and property in areas of construction against dust and debris, so that equipment and areas to be used in the Medical Centers operations shall not be hindered.
Contractor shall permit access to Department of Veterans Affairs personnel and patients through construction areas which serve as routes of access to such areas and equipment. These routes whether access or egress shall be isolated from the construction area by temporary partitions and have walking surfaces, lighting, etc. to facilitate patient and staff access. Coordinate work in areas occupied by Department of Veterans Affairs so that Medical Center operations will continue during the construction period.
2. Patient Rooms indicated for alterations will be temporarily vacated while alterations are performed, but the patient wing or unit will remain occupied by VA staff and Patients.
I. Utilities Services: Maintain existing utility services for Medical
Center at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services.
Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped at suitable places, where directed by COR.
1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be
Grand Junction, CO 81501 Project No. 575-18-106
01 00 00 -8 interrupted without prior approval of Resident COR and Chief of
Facilities Management. Electrical work shall be accomplished with all affected circuits or equipment de-energized. When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without a detailed work plan, the
Medical Center Director’s prior knowledge and written approval.
2. Contractor shall submit a request to interrupt any such services to
COR, in writing, 7 days in advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption.
3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of Medical Center. Interruption time approved by Medical Center may occur at other than Contractor's normal working hours.
4. Major interruptions of any system must be requested, in writing, at least 15 calendar days prior to the desired time and shall be performed as directed by the COR.
5. In case of a contract construction emergency, service will be interrupted on approval of COR. Such approval will be confirmed in writing as soon as practical.
6. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.
J. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, which are to be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged at the main, branch or panel they originate from. The lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or partitions; so that they are completely behind the finished surfaces.
Grand Junction, CO 81501 Project No. 575-18-106
01 00 00 -9
K. To minimize interference of construction activities with flow of
Medical Center traffic, comply with the following:
1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles.
2. Method and scheduling of required cutting, altering and removal of existing roads, walks and entrances must be approved by the COR.
L. Coordinate the work for this contract with other construction operations as directed by COR. This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF ROADWAYS.
1.7 ALTERATIONS
A. Survey: Before any work is started, the Contractor shall make a thorough survey with COR and a representative of VA Supply Service, of areas of buildings in which alterations occur and areas which are anticipated routes of access, and furnish a report, signed by both, to the Contracting Officer. This report shall list by rooms and spaces:
1. Existing condition and types of resilient flooring, doors, windows, walls and other surfaces not required to be altered throughout affected areas of building.
2. Existence and conditions of items such as plumbing fixtures and accessories, electrical fixtures, equipment, venetian blinds, shades, etc., required by drawings to be either reused or relocated, or both.
3. Shall note any discrepancies between drawings and existing conditions at site.
4. Shall designate areas for working space, materials storage and routes of access to areas within buildings where alterations occur and which have been agreed upon by Contractor and COR.
B. Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of COR and/or Supply Representative, to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by
Contractor with new items in accordance with specifications which will
Grand Junction, CO 81501 Project No. 575-18-106
01 00 00 -10 be furnished by Government. Provided the contract work is changed by reason of this subparagraph B, the contract will be modified accordingly, under provisions of clause entitled "DIFFERING SITE
CONDITIONS" (FAR 52.236-2) and "CHANGES" (FAR 52.243-4 and VAAR
852.236-88).
C. Re-Survey: Thirty days before expected partial or final inspection date, the Contractor and COR together shall make a thorough re-survey of the areas of buildings involved. They shall furnish a report on conditions then existing, of resilient flooring, doors, windows, walls and other surfaces as compared with conditions of same as noted in first condition survey report:
1. Re-survey report shall also list any damage caused by Contractor to such flooring and other surfaces, despite protection measures; and, will form basis for determining extent of repair work required of
Contractor to restore damage caused by Contractor's workmen in executing work of this contract.
D. Protection: Provide the following protective measures:
1. Wherever existing roof surfaces are disturbed they shall be protected against water infiltration. In case of leaks, they shall be repaired immediately upon discovery.
2. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled and equipment moved and/or relocated.
3. Protection of interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, floor surfaces that are to remain in place shall be adequately protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.
1.8 DISPOSAL AND RETENTION
A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:
Grand Junction, CO 81501 Project No. 575-18-106
01 00 00 -11
1. Reserved items which are to remain property of the Government are noted on drawings or in specifications as items to be stored or salvaged. Items that remain property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re-installation and reuse. Store such items where directed by COR.
2. Items not reserved shall become property of the Contractor and be removed by Contractor from Medical Center .
3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Government. When rooms and spaces are vacated by the Department of Veterans Affairs during the alteration period, such items which are NOT required by drawings and specifications to be either relocated or reused will be removed by the Government in advance of work to avoid interfering with Contractor's operation.
1.9 NOT USED
1.10 RESTORATION
A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the
COR. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the COR before it is disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.
B. Upon completion of contract, deliver work complete and undamaged.
Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.) disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.
C. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workmen to
Grand Junction, CO 81501 Project No. 575-18-106
01 00 00 -12 existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems (including telephone) which are not scheduled for discontinuance or abandonment.
D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract time and price in accordance with clause entitled "CHANGES"
(FAR 52.243-4 and VAAR 852.236-88) and "DIFFERING SITE CONDITIONS" (FAR
52.236-2).
1.11 PHYSICAL DATA
A. Data and information furnished or referred to below is for the
Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.
1. The indications of physical conditions on the drawings and in the specifications are the result of site investigations by design team responsible for the drawings and specifications.
(FAR 52.236-4)
B. Government nor the design team does not guarantee that other materials will not be encountered nor that proportions, conditions or character of several materials will not vary from those indicated by explorations.
Bidders are expected to examine site of work; and, after investigation, decide for themselves character of materials and make their bids accordingly. Upon proper application to Department of Veterans Affairs, bidders will be permitted to make explorations of their own at site.
1.12 PROFESSIONAL SURVEYING SERVICES – NOT USED, INTERIOR WORK
1.13 LAYOUT OF WORK
A. The Contractor shall lay out the work from Government established base lines and bench marks, indicated on the drawings, and shall be responsible for all measurements in connection with the layout. The
Contractor shall furnish, at Contractor's own expense, all stakes, templates, platforms, equipment, tools, materials, and labor required to lay out any part of the work. The Contractor shall be responsible for executing the work to the lines and grades that may be established or indicated by the Contracting Officer. The Contractor shall also be
Grand Junction, CO 81501 Project No. 575-18-106
01 00 00 -13 responsible for maintaining and preserving all stakes and other marks established by the Contracting Officer until authorized to remove them.
If such marks are destroyed by the Contractor or through Contractor's negligence before their removal is authorized, the Contracting Officer may replace them and deduct the expense of the replacement from any amounts due or to become due to the Contractor.
(FAR 52.236-17)
1.14 AS-BUILT DRAWINGS
A. The contractor shall maintain two full size sets of as-built drawings which will be kept current during construction of the project, to include all contract changes, modifications and clarifications.
B. All variations shall be shown in the same general detail as used in the contract drawings. To insure compliance, as-built drawings shall be made available for the COR review, as often as requested.
C. Contractor shall deliver two approved completed sets of as-built drawings in the electronic version (scanned PDF) to the COR within 15 calendar days after each completed phase and after the acceptance of the project by the COR.
D. Paragraphs A, B, & C shall also apply to all shop drawings.
1.15 USE OF ROADWAYS
A. For hauling, use only established public roads and roads on Medical
Center property and, when authorized by the COR, such temporary roads which are necessary in the performance of contract work. Temporary roads shall be constructed and restoration performed by the Contractor at Contractor's expense. When necessary to cross curbing, sidewalks, or similar construction, they must be protected by well-constructed bridges.
1.16 RESIDENT ENGINEER'S FIELD OFFICE – NOT REQUIRED
1.17 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT
A. Use of installed mechanical and electrical equipment to provide heat, ventilation, plumbing, light and power will be permitted subject to written approval and compliance with the following provisions:
Grand Junction, CO 81501 Project No. 575-18-106
01 00 00 -14
1. Permission to use each unit or system must be given by COR in writing. If the equipment is not installed and maintained in accordance with the written agreement and following provisions, the
COR will withdraw permission for use of the equipment.
2. Units shall be properly lubricated, balanced, and aligned.
Vibrations must be eliminated.
3. Automatic temperature control systems for preheat coils shall function properly and all safety controls shall function to prevent coil freeze-up damage.
4. The air filtering system utilized shall be that which is designed for the system when complete, and all filter elements shall be replaced at completion of construction and prior to testing and balancing of system.
5. All components of heat production and distribution system, metering equipment, condensate returns, and other auxiliary facilities used in temporary service shall be cleaned prior to use; maintained to prevent corrosion internally and externally during use; and cleaned, maintained and inspected prior to acceptance by the Government.
B. Prior to final inspection, the equipment or parts used which show wear and tear beyond normal, shall be replaced with identical replacements, at no additional cost to the Government.
C. This paragraph shall not reduce the requirements of the mechanical and electrical specifications sections.
D. Any damage to the equipment or excessive wear due to prolonged use will be repaired replaced by the contractor at the contractor’s expense.
1.18 TEMPORARY USE OF EXISTING ELEVATORS
A. Use of existing elevators for handling building materials and
Contractor's personnel will be permitted subject to following provisions:
1. Contractor makes all arrangements with the COR for use of elevators.
Service elevator S3 will be made available for the Contractors use, coordinate with the COR. The COR will ascertain that elevators are in proper condition. Contractor may use elevators indicated by the
Grand Junction, CO 81501 Project No. 575-18-106
01 00 00 -15
COR for special nonrecurring time intervals when permission is granted. Personnel for operating elevators will not be provided by the Department of Veterans Affairs.
2. Contractor covers and provides maximum protection of following elevator components:
a. Entrance jambs, heads soffits and threshold plates.
b. Entrance columns, canopy, return panels and inside surfaces of car enclosure walls.
c. Finish flooring.
3. Government will accept hoisting ropes of elevator and rope of each speed governor if they are worn under normal operation. However, if these ropes are damaged by action of foreign matter such as sand, lime, grit, stones, etc., during temporary use, they shall be removed and replaced by new hoisting ropes at the contractors expense.
4. If brake lining of elevators are excessively worn or damaged during temporary use, they shall be removed and replaced by new brake lining.
5. All parts of main controller, starter, relay panel, selector, etc., worn or damaged during temporary use shall be removed and replaced with new parts, if recommended by elevator inspector after elevator is released by Contractor.
6. Place elevator in condition equal, less normal wear, to that existing at time it was placed in service of Contractor as approved by Contracting Officer.
1.19 TEMPORARY USE OF NEW ELEVATORS – NOT APPLICABLE
1.20 TEMPORARY TOILETS – NOT APPLICABLE
1.21 AVAILABILITY AND USE OF UTILITY SERVICES
A. The Government shall make all reasonably required amounts of utilities available to the Contractor from existing outlets and supplies, as specified in the contract. The amount to be paid by the Contractor for chargeable electrical services shall be the prevailing rates charged to
Grand Junction, CO 81501 Project No. 575-18-106
01 00 00 -16 the Government. The Contractor shall carefully conserve any utilities furnished without charge.
B. The Contractor, at Contractor's expense and in a workmanlike manner, in compliance with code and as satisfactory to the Contracting Officer, shall install and maintain all necessary temporary connections and distribution lines, and all meters required to measure the amount of electricity used for the purpose of determining charges. Before final acceptance of the work by the Government, the Contractor shall remove all the temporary connections, distribution lines, meters, and associated paraphernalia and repair restore the infrastructure as required.
1.22 NEW TELEPHONE EQUIPMENT – NOT APPLICABLE
1.23 TESTS – NOT APPLICABLE
1.24 INSTRUCTIONS
A. Contractor shall furnish Operations and Maintenance manuals (hard copies and electronic) and verbal instructions when required by the various sections of the specifications and as hereinafter specified.
B. Manuals: Operations and Maintenance manuals and one compact disc (four hard copies and one electronic copy each) for each separate piece of equipment shall be delivered to the COR coincidental with the delivery of the equipment to the job site. Manuals shall be complete, detailed guides for the maintenance and operation of equipment. They shall include complete information necessary for starting, adjusting, maintaining in continuous operation for long periods of time and dismantling and reassembling of the complete units and sub-assembly components. Manuals shall include an index covering all component parts clearly cross-referenced to diagrams and illustrations. Illustrations shall include "exploded" views showing and identifying each separate item. Emphasis shall be placed on the use of special tools and instruments. The function of each piece of equipment, component, accessory and control shall be clearly and thoroughly explained. All necessary precautions for the operation of the equipment and the reason for each precaution shall be clearly set forth. Manuals must reference the exact model, style and size of the piece of equipment and system being furnished. Manuals referencing equipment similar to but of a
Grand Junction, CO 81501 Project No. 575-18-106
01 00 00 -17 different model, style, and size than that furnished will not be accepted.
C. Instructions: Contractor shall provide qualified, factory-trained manufacturers' representatives to give detailed training to assigned
Department of Veterans Affairs personnel in the operation and complete maintenance for each piece of equipment. All such training will be at the job site. These requirements are more specifically detailed in the various technical sections. Instructions for different items of equipment that are component parts of a complete system, shall be given in an integrated, progressive manner. All instructors for every piece of component equipment in a system shall be available until instructions for all items included in the system have been completed.
This is to assure proper instruction in the operation of inter-related systems. All instruction periods shall be at such times as scheduled by the COR and shall be considered concluded only when the COR is satisfied in regard to complete and thorough coverage. The contractor shall submit a course outline with associated material to the COR for review and approval prior to scheduling training to ensure the subject matter covers the expectations of the VA and the contractual requirements. The Department of Veterans Affairs reserves the right to request the removal of, and substitution for, any instructor who, in the opinion of the COR, does not demonstrate sufficient qualifications in accordance with requirements for instructors above.
1.25 GOVERNMENT-FURNISHED PROPERTY – NOT APPLICABLE
1.26 RELOCATED ITEMS
A. Contractor shall disconnect, dismantle as necessary, remove and reinstall in current/existing location, all existing equipment and items indicated by symbol "R" or otherwise shown to be relocated by the
Contractor. Storage within the active work area and phase is at the
Contractors discretion, with approval by the COR. Remedy of any damage or misuse of the equipment, furniture, or items is the responsibility of the contractor, at no cost to the owner.
B. Perform relocation of such equipment or items at such times and in such a manner as directed by the COR.
Grand Junction, CO 81501 Project No. 575-18-106
01 00 00 -18
C. Suitably cap existing service lines, such as steam, condensate return, water, drain, gas, air, vacuum and/or electrical, at the main whenever such lines are disconnected from equipment to be relocated. Remove abandoned lines in finished areas and cap as specified herein before under paragraph "Abandoned Lines".
D. Provide all mechanical and electrical service connections, fittings, fastenings and any other materials necessary for assembly and installation of relocated equipment; and leave such equipment in proper operating condition.
E. All service lines such as noted above for relocated equipment shall be in place at point of relocation ready for use before any existing equipment is disconnected. Make relocated existing equipment ready for operation or use immediately after reinstallation.
1.27 STORAGE SPACE FOR DEPARTMENT OF VETERANS AFFAIRS EQUIPMENT – NOT
APPLICABLE – CONTRACTOR TO PROVIDE ALL STORAGE SPACE
1.28 CONSTRUCTION SIGN – NOT USED
1.29 SAFETY SIGN
A. Provide a Safety Sign where directed by COR. Face of sign shall be 19 mm (3/4 inch) thick exterior grade plywood. Provide two 100 mm by 100 mm (four by four inch) posts extending full height of sign and 900 mm
(three feet) into ground. Set bottom of sign level at 1200 mm (four feet) above ground.
B. Paint all surfaces of Safety Sign and posts with one prime coat and two coats of white gloss paint. Letters and design shall be painted with gloss paint of colors noted.
C. Maintain sign and remove it when directed by COR .
D. Standard Detail Drawing Number SD10000-02(Found on VA TIL) of safety sign showing required legend and other characteristics of sign is attached hereto and is made a part of this specification.
E. Post the number of accident free days on a daily basis.
1.30 PHOTOGRAPHIC DOCUMENTATION
A. During the construction period through completion, provide photographic documentation of construction progress and at selected milestones
Grand Junction, CO 81501 Project No. 575-18-106
01 00 00 -19 including electronic storage and remote access to the documentation, as per these specifications.
B. Photographic documentation elements:
1. Each digital image shall be taken with a minimum size of 4 megapixels (MP) capable of producing 200x250mm (8 x 10 inch) prints.
2. Construction progress for all trades shall be tracked at pre-determined intervals, but not less than once every thirty (30) calendar days (“Progressions”). Progression documentation shall track the interior construction of the building.
3. As-built finished conditions of the interior of each building including floors, ceilings and walls shall be documented at completion of each trade, or just prior complete of the phase, or both, as directed by the COR. Overlapping photographic techniques shall be used to insure maximum coverage. Label all photographic files by phase and room number/ specific location (“patient room” alone is not sufficient for identification).
4. In event a greater or lesser number of images than specified above are required by the COR, adjustment in contract price will be made in accordance with clause entitled "CHANGES" (FAR 52.243-4 and VAAR
852.236-88).
C. Images shall be taken must show distinctly, at as large a scale as possible, all parts of work embraced in the picture.
D. Coordination of photo shoots is accomplished through COR. Contractor shall also attend construction team meetings as necessary. Contractor’s operations team shall provide regular updates regarding the status of the documentation, including photo shoots concluded, the availability of new Progressions or Exact-Builts viewable on-line and anticipated future shoot dates.
E. Contractor shall provide all on-line domain/web hosting, security measures, and redundant server back-up of the documentation.
F. Contractor shall provide technical support related to using the system or service.
Grand Junction, CO 81501 Project No. 575-18-106
01 00 00 -20
G. Upon completion of the project, final copies of the documentation (the
“Permanent Record”) with the indexing and navigation system embedded
(and active) shall be provided in an electronic media format, typically a DVD or external hard-drive. Permanent Record shall have Building
Information Modeling (BIM) interface capabilities. On-line access terminates upon delivery of the Permanent Record.
1.31 FINAL ELEVATION DIGITAL IMAGES – NOT USED
1.32 HISTORIC PRESERVATION – NOT APPLICABLE
1.33 VA TRIRIGA CPMS – NOT USED
- - - E N D - - -
Grand Junction, CO 81501 Project No. 575-18-106
02-01-15
01 32 16.15 - 1
SECTION 01 32 16
PROJECT SCHEDULES
PART 1- GENERAL
1.1 DESCRIPTION:
A. The Contractor shall develop a Critical Path Method (CPM) plan and schedule demonstrating fulfillment of the contract requirements
(Project Schedule) and shall keep the Project Schedule up-to-date in accordance with the requirements of this section and shall utilize the plan for scheduling, coordinating and monitoring work under this contract (including all activities of subcontractors, equipment vendors and suppliers). Conventional Critical Path Method (CPM) technique shall be utilized to satisfy both time and cost applications.
1.2 CONTRACTOR'S REPRESENTATIVE:
A. The Contractor shall designate an authorized representative responsible for the Project Schedule including preparation, review and progress reporting with and to the Contracting Officer's Representative (COR).
B. The Contractor's representative shall have direct project control and complete authority to act on behalf of the Contractor in fulfilling the requirements of this specification section.
C. The Contractor’s representative shall have the option of developing the project schedule within their organization or to engage the services of an outside consultant. If an outside scheduling consultant is utilized, Section 1.3 of this specification will apply.
1.3 COMPUTER PRODUCED SCHEDULES
A. The contractor shall provide monthly, to the Department of Veterans
Affairs (VA), all computer-produced time/cost schedules and reports generated from monthly project updates. This monthly computer service will include: up to five different reports (inclusive of all pages) available within the user defined reports of the scheduling software approved by the Contracting Officer; a listing of all project schedule changes, and associated data, made at the update and an electronic file of this data; and the resulting monthly updated schedule in PDM format.
These must be submitted with and substantively support the contractor’s monthly payment request and the signed look ahead report. The COR shall identify the five different report formats that the contractor shall provide.
Grand Junction, CO 81501 Project No. 575-18-106
02-01-15
01 32 16.15 - 2
B. The contractor shall be responsible for the correctness and timeliness of the computer-produced reports. The Contractor shall also responsible for the accurate and timely submittal of the updated project schedule and all CPM data necessary to produce the computer reports and payment request that is specified.
C. The VA will report errors in computer-produced reports to the
Contractor’s representative within ten calendar days from receipt of reports. The Contractor shall reprocess the computer-produced reports and associated diskette(s), when requested by the Contracting Officer’s representative, to correct errors which affect the payment and schedule for the project.
1.4 THE COMPLETE PROJECT SCHEDULE SUBMITTAL
A. Within 30 calendar days after receipt of Notice to Proceed, the
Contractor shall submit for the Contracting Officer's review; three blue line copies of the interim schedule on sheets of paper 765 x 1070 mm (30 x 42 inches) and an electronic file in the previously approved
CPM schedule program. The submittal shall also include three copies of a computer-produced activity/event ID schedule showing project duration; phase completion dates; and other data, including event cost.
Each activity/event on the computer-produced schedule shall contain as a minimum, but not limited to, activity/event ID, activity/event description, duration, budget amount, early start date, early finish date, late start date, late finish date and total float. Work activity/event relationships shall be restricted to finish-to-start or start-to-start without lead or lag constraints. Activity/event date constraints, not required by the contract, will not be accepted unless submitted to and approved by the Contracting Officer. The contractor shall make a separate written detailed request to the Contracting
Officer identifying these date constraints and secure the Contracting
Officer’s written approval before incorporating them into the network diagram. The Contracting Officer’s separate approval of the Project
Schedule shall not excuse the contractor of this requirement. Logic events (non-work) will be permitted where necessary to reflect proper logic among work events but must have zero duration. The complete working schedule shall reflect the Contractor's approach to scheduling the complete project. The final Project Schedule in its original form shall contain no contract changes or delays which may have been
Grand Junction, CO 81501 Project No. 575-18-106
02-01-15
01 32 16.15 - 3 incurred during the final network diagram development period and shall reflect the entire contract duration as defined in the bid documents.
These changes/delays shall be entered at the first update after the final Project Schedule has been approved. The Contractor should provide their requests for time and supporting time extension analysis for contract time as a result of contract changes/delays, after this update, and in accordance with Article, ADJUSTMENT OF CONTRACT
COMPLETION.
D. Within 30 calendar days after receipt of the complete project interim
Project Schedule and the complete final Project Schedule, the
Contracting Officer or his representative, will do one or both of the following:
1. Notify the Contractor concerning his actions, opinions, and objections.
2. A meeting with the Contractor at or near the job site for joint review, correction or adjustment of the proposed plan will be scheduled if required. Within 14 calendar days after the joint review, the Contractor shall revise and shall submit copies of the revised Project Schedule, copies of the revised computer-produced activity/event ID schedule as revised electronic files as specified by the Contracting Officer. The revised submission will be reviewed by the Contracting Officer and, if found to be as previously agreed upon, will be approved.
E. The approved baseline schedule and the computer-produced schedule(s) generated there from shall constitute the approved baseline schedule until subsequently revised in accordance with the requirements of this section.
F. The Complete Project Schedule shall contain approximately 36 work activities/events.
1.5 WORK ACTIVITY/EVENT COST DATA
A. The Contractor shall cost load all work activities/events except procurement activities. The cumulative amount of all cost loaded work activities/events (including alternates) shall equal the total contract price. Prorate overhead, profit and general conditions on all work activities/events for the entire project length. The contractor shall generate from this information cash flow curves indicating graphically the total percentage of work activity/event dollar value scheduled to
Grand Junction, CO 81501 Project No. 575-18-106
02-01-15
01 32 16.15 - 4 be in place on early finish, late finish. These cash flow curves will be used by the Contracting Officer to assist him in determining approval or disapproval of the cost loading. Negative work activity/event cost data will not be acceptable, except on VA issued contract changes.
B. The Contractor shall cost load work activities/events for guarantee period services, test, balance and adjust various systems in accordance with the provisions in Article, FAR 52.232 – 5 (PAYMENT UNDER
FIXED-PRICE CONSTRUCTION CONTRACTS) and VAAR 852.236 – 83 (PAYMENT
UNDER FIXED-PRICE CONSTRUCTION CONTRACTS).
C. In accordance with FAR 52.236 – 1 (PERFORMANCE OF WORK BY THE
CONTRACTOR) and VAAR 852.236 – 72 (PERFORMANCE OF WORK BY THE
CONTRACTOR), the Contractor shall submit, simultaneously with the cost per work activity/event of the construction schedule required by this
Section, a responsibility code for all activities/events of the project for which the Contractor's forces will perform the work.
D. The Contractor shall cost load work activities/events for all BID ITEMS including ASBESTOS ABATEMENT. The sum of each BID ITEM work shall equal the value of the bid item in the Contractors' bid.
1.6 PROJECT SCHEDULE REQUIREMENTS
A. Show on the project schedule the sequence of work activities/events required for complete performance of all items of work. The Contractor
Shall:
1. Show activities/events as:
a. Contractor's time required for submittal of shop drawings, templates, fabrication,…