36C25818Q0268-008.docx
DOCX document 14 KB Posted
- Solicitation number
- 36C25818Q0268
About this file
36C25818Q0268 Attachment 7 General Cleaning Semi Annual Checklist.docx
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C25818Q0268-017.pdf | ||
| 36C25818Q0268-012.docx | DOCX document | |
| 36C25818Q0268-016.docx | DOCX document | |
| 36C25818Q0268-010.docx | DOCX document | |
| 36C25818Q0268-002.docx | DOCX document | |
| 36C25818Q0268-013.pdf | ||
| 36C25818Q0268-018.docx | DOCX document | |
| 36C25818Q0268-005.docx | DOCX document | |
| 36C25818Q0268-003.docx | DOCX document | |
| 36C25818Q0268-015.pdf | ||
| 36C25818Q0268-001.docx | DOCX document | |
| 36C25818Q0268-004.docx | DOCX document | |
| 36C25818Q0268-014.pdf | ||
| 36C25818Q0268-007.docx | DOCX document | |
| 36C25818Q0268-011.docx | DOCX document | |
| 36C25818Q0268-006.docx | DOCX document | |
| 36C25818Q0268-009.docx | DOCX document | |
| 36C25818Q0268-000.docx | DOCX document |
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment #7
Semi-Annually Work Specifications Checklist
General Cleaning
| Work to completed |
| Completed By |
| Date |
1. Clean floor in Computer Room (RM146), and Label Room (RM185) on an as needed basis
2. Clean interior glass and windowsills. Clean exterior glass windows
3. Dust “mini” blinds on all windows
4. Dust empty shelves and warehouse pallet racking uprights in all warehouses
5. Clean doors, doorframes, window frames, picture frames, interior walls, light fixtures, fire extinguisher enclosures, and other wall mounted fixtures in all areas.
6. Clean and disinfect all light switches to prevent cross contamination.
7. Deep clean carpets and fabric chairs using extraction method. Spot treat chairs if necessary.
8. Scrub and re-wax floor in BPLS Laboratory cubical areas.
9. Scrub, seal, and wax concrete floors every other year. First application will be applied within four months of contract placement. Contractor must schedule appropriate time with COR.