2. Domiciliary Mold Remediation Protocol.pdf

PDF 453 KB Posted

Attached to
F108--WTX - Mold Remediation Federal contract opportunity
Solicitation number
36C25726Q0227
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 17

About this file

This is a Mold Remediation Protocol for wall cavity mold remediation work at the West Texas VA Health Care System facility located at 2400 S. Gregg in Big Spring, Texas. The client contact is Mr. Daron Moore at the facility address. The mold consultant is licensed under MAC-0293 with an expiration date of 04/01/2026, and a mold contractor will be identified to perform the work. Remediation dates are to be determined (TBD).

The protocol specifies remediation of approximately 129 square feet of wall (sheetrock and original insulation) in interior wall cavities across two primary areas: Domiciliary Room 103 and adjoining offices (105 sq. ft. of wall removal along the north wall and adjoining laterals extending 2 feet beyond visible damage), and Patient Rooms 152 & 154 (24 sq. ft. of wall removal along the common bedroom wall and adjoining laterals extending 2 feet beyond visible damage). The cause of damage is attributed to long-term overhead water intrusion in Room 103 and plumbing leaks in Rooms 152 & 154, with the owner responsible for addressing the underlying moisture intrusion issues. The contractor must be a currently licensed Texas mold remediation contractor adhering to TDLR guidelines and requirements. Work requirements include establishing negative pressure containment with minimum 2000 cfm negative air units, a single-stage decontamination unit with shower, TDLR-required signage, and PPE standards requiring half-face respirators with N-95 cartridges and full disposable suits. Decontamination activities include HEPA-vacuuming and wet-wiping of exposed structural elements with EPA-approved biocide, HVAC system cleaning, and removal/treatment of soft goods. Post-remediation sampling must achieve clearance per nationally recognized guidelines for mold spore levels comparing interior air and surface samples to exterior baseline samples, with specific criteria for Stachybotrys, Chaetomium, Penicillium/Aspergillus, and other spore types. Contractor responsibilities include daily activity logging, continuous recording of pressure differentials via manometer, proper waste disposal in double bags with biocide-wetted outer surfaces, and prevention of non-certified personnel entry post-remediation start until project clearance is achieved.

View the file

Other files for this federal contract opportunity

Other files attached to F108--WTX - Mold Remediation, newest first.
File Type Posted
Technical Q and A - 36C25726Q0227 - WTX - Mold Remediation.pdf PDF
1. Mold Survey Report.pdf PDF
3. DOM Floor Plan.pdf PDF
5. Sign-in.pdf PDF
4. DOM Mechanical Plans.pdf PDF
36C25726Q0227 0001_1.docx DOCX document
SF 30 36C25726Q0227 0001.pdf PDF
36C25726Q0227_1 v2.pdf PDF
36C25726Q0227_1.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TEXAS CONSULTING SERVICES

PO Box 9910 * Midland, Texas 79708

Phone: (432) 687-5455 * Fax: (432) 687-5456

Email:

info@texconsulting.net

Mold Remediation Protocol for:

CLIENT:

West Texas VA Health Care System

2400 S. Gregg

Big Spring, TX 79720

Attn: Mr. Daron Moore

PROJECT:

Domiciliary

Patient Room 152/154 & Domiciliary Room 103 Chief Office

Wall Cavity Mold Remediation

REMEDIATION DATES:

TBD

Mold Consultant

MAC-0293

License Number

Mold Contractor

License Number

Date

04/01/2026 .

Exp. Date

Date

Exp. Date

MEMBER

INDEX

TAB 1 PROTOCOL

TAB 2 FLOOR PLANS

TAB 1

REPORT

TEXAS CONSULTING SERVICES

SUMMARY EVALUATION MOLD PROTOCOL

LIMITATIONS AND REPRODUCTIONS

Texas Consulting Services makes no warranty, assurance, or guarantees that other Mold Containing

Materials (MCM) may not be in the structure in areas that were not covered by this inspection.

This report has been prepared on behalf of and for the exclusive use of the West Texas VA Health Care

System for use in the herein described mold remediation of the site located at 2400 S. Gregg in Big Spring, Texas. This report and findings contained herein shall not, in whole or in part, be disseminated or conveyed to any other party, nor used by any other party in whole or in part, without the express written consent of

Texas Consulting Services.

SCOPE OF INITIAL MOLD ASSESSMENT

1. Texas Consulting Services will not be responsible for any mold containing materials (MCM) that were not found in the mold inspection of the site due to areas that were inaccessible or concealed.

Since the inspection is limited to areas that are accessible to the inspector and not enclosed or otherwise concealed from the inspection process and additionally that non-destructive testing is performed during the inspection, the owner is advised that remediation or demolition may discover additional MCM on site.

2. This protocol is based on the MCM inspection of the site and visible evidence discovered upon site walk. The laboratories used are AIHA certified and Texas Consulting Services assumes these analyses are true and correct but will not be responsible for their content.

3. Any damages done to the site will be the responsibility of the site owner. Some damage will occur as a part of the inspection process such as, but not limited to, painted surfaces, holes in walls or other cosmetic damage. Texas Consulting Services will not be responsible for these damages.

4. Theft from the site will not be the responsibility of Texas Consulting Services.

5. This inspection/protocol is not a warranty as to the absence of MCM in the completed project.

6. Neither Texas Consulting Services, its employees nor representatives have had, presently have, or contemplate having any interest in the subject property or are associated in any way with any party to this project.

7. This report is accurate only for the test date and/or remediation dates. Factors not limited to increased moisture levels or other activities on site may increase or decrease the amount of

MCM’s. TCS assumed no responsibility or knowledge of such factors.

8. Texas Consulting Services is not responsible for any activities beyond the date of inspection and/or remediation unless specifically contracted and outlined to do so.

9. No verbal statements by the inspector are to be considered a part of this inspection or report.

REMEDIATION PROTOCOL

2400 S. Gregg – Midland, TX

JOB SITE DESCRIPTION

This is a federal, Veterans Administration Health Care facility in Big Spring, TX. The property is owned and operated by the same. The facility/building in question is approximately 30,000 sq. ft., stand-alone structure consisting of a brick exterior with a sheetrock interior build out. The interior consists of concrete floors, carpet, VCT, sheetrock walls, and lay-in ceiling. The area included in this remediation project is the interior side of the exterior, perimeter walls of the Domiciliary Chief Office 103 and the common wall between Patient Rooms 152 & 154. This consultant has not yet been provided with a copy of the OSHA compliant asbestos survey.

ASSUMPTIONS AND CLARIFICATIONS

Contractor must be a currently licensed Mold Remediation Contractor with adherence to all TDLR Mold

Remediation Guidelines including contractor supervisor licensure, worker training, insurance and refreshers. Owner/management will address exact cause of water damage. The cause of damage appears to be long term damage from overhead water intrusion in the Domiciliary Chief Office 103 and plumbing leaks in the common wall of Patient Room 152 & 154. These areas are being addressed by the VA to remedy the moisture intrusion issues. The goal of this project is to successfully remediate the areas described herein according to this protocol. As a means of insuring damage will not reoccur the owner will repair the moisture intrusion issues in the facility from various sources. Owner/management will arrange those repairs, TCS and environmental contractors do not assume any reconstruction responsibility or knowledge. Tenant and/or owner management will move all loose articles, books, sensitive filing cabinets, computers, etc from containment areas prior to remediation. Any objects not removed from the room will be covered with min. 6 mil poly prior to any remediation. Environmental contractors will not be responsible for moving computer equipment. Owner will replace any AC filters discarded during remediation. Owner is to provide OSHA compliant asbestos survey prior to start date of desired remediation.

PROTOCOL

Description: This remediation will involve a remediation of the following:

• Approximately 129 sq. ft. of wall (sheetrock and original insulation) in interior wall cavities as noted for the remediation areas. Decontamination will include wet-wiping of all exposed structural elements with EPA approved bio-cide, HEPA-vacuuming of all contained items such as remaining walls, exposed studs, footings, wall systems and any material left in the room. HVAC and mechanical duct/equipment cleaning to be performed as noted in specific areas.

Tentative Schedule: TBD

Environmental Contractor: TBD

Post-Remediation Sampling: Minimum 1 containment air sample, 1 containment surface sample, 1 interior non-contained air sample, minimum 1 exterior air sample. These shall be performed after a laser particulate screening and visual assessment. Laser particulate screening and visual assessment may be used to determine whether tear-down may occur before receiving objective surface and air measurements from licensed TDLR laboratory.

Details: Tenant to move all furnishings from remediation area during remediation. Items left in the room will be covered with min. 6 mil poly and wet wiped prior to post-remediation sampling.

Specific Requirements: Items 1-7 below apply to all remediation areas as scoped.

1. This project is to be isolated to the Domiciliary Room 103 area (with adjoining offices) and Patient

Rooms 152 & 154 of the Domiciliary. This is a single phase activity.

2. Remediation location breakdown is as follows with a detailed drawing included in this protocol:

LOCATION DESCRIPTION

SQ. FT. OF

INTERIOR WALLS

REMEDIATION

DATES

DOMICILIARY ROOM

103 & ADJOINING

OFFICES

REMOVE 105 SQ. FT.

OF WALL ALONG

NORTH WALL &

ADJOINING

LATERALS TO 2’

BEYOND DAMAGE

105 SQ. FT. TBD

PATIENT ROOMS

152 & 154

REMOVE 24 SQ. FT.

OF WALL ALONG

BEDROOM

COMMON WALL

AND ADJOINING

LATERALS TO 2’

BEYOND DAMAGE

24 SQ. FT. TBD

3. Contractor is responsible for TDLR notification, TDLR licensure and insurance requirements adhering to TDLR requirements and Big Spring VA mandates.

4. Contractor is to block off all supply and return ducts in containment of Area B.

5. Contractor is to construct minimum single stage decontamination unit with a shower (no water).

Contractor will establish negative pressure relative to the interior of the facility using at minimum one

2000 cfm negative air unit(s) in containment. Exhaust will be to the exterior when/where possible, otherwise interior exhaust will be acceptable. Containment will be constructed of minimum 6 mil poly from floor to ceiling immediately surrounding the south and east walls.

6. Contractor will post TDLR required signs including black letter with yellow background reading at minimum “Mold Remediation In Progress”.

7. PPE for personnel in all removal activities including preparation shall be at minimum half-face respirator with N-95 or equivalent cartridge. Gloves not required but full disposable suiting required in containment at all times by workers and to be discarded in the decontamination unit prior to exit from containment.

DOMICILIARY ROOM 103 – Includes Reception, Chief Office and adjoining offices in this vicinity labeled Provider Office and Clinical Coordinator according to layout

8. Chief Office - North Wall - Remove and discard sheetrock/exposed insulation from floor to ceiling in height along north wall and 2' perpendicular cut running south from the north wall.

9. Remove all ceiling tile in the Chief Office, adjoining offices and reception to remain.

10. All carpet in the area including adjoining the Chief Office is to be removed and discarded.

11. All containment walls, exposed ducting, and covered material left in containment, etc.: HEPA-vacuum or wet wipe with EPA approved biocide. Heavy cleaning concentration shall include but not be limited to the flooring and exposed all cavities.

12. If further mold and/or water damage is found, please contact TCS immediately. Special inspection of the exposed wall cavities of perimeter and adjoining/perpendicular walls to determine if remediation of those walls is necessary as well. Owner and consultant will be notified immediately if any additional fungal/water damage is discovered or suspect.

13. All components of the HVAC system servicing this area to be cleaned using HEPA and mechanical means with an EPA biocide approved cleaning of coils and pans.

14. Remove and discard all exposed insulation and sheetrock in the common wall of Room 152 & 154, bedroom side only, to 4’ in height. Adjoining laterals at bathroom and exterior wall to be removed 2’ beyond any visible damage and equal in height to common wall (as shown in drawings).

15. All soft goods in the rooms (mattress, bedding, etc) to be HEPA cleaned or discarded. Owner discretion. Consultant would recommend disposal.

16. All non-porous surfaces in the rooms to be HEPA vacuumed and cleaned using an EPA approved biocide.

17. All components of the HVAC system servicing this area to be cleaned using HEPA and mechanical means with an EPA biocide approved cleaning of coils and pans.

Items 18-21 apply to all remediation areas as scoped.

18. Perform post-remediation monitoring with at least 24 hour settling period after remediation is complete and passed contractor visual. Please see the Post Remediation Sampling and Criteria section of this protocol for guidelines and criteria for analyzing these results. After the containment has passed final clearance inspection, spray all exposed surfaces with EPA approved biocide. This includes the concrete foundation surface, and structural members in contact with the concrete. Exposed studs and interior of exposed wall cavities shall be sealed with anti-microbial paint such as Kilz, Fosters 40-20, etc. with a minimum effective period of 7-10 years.

PATIENT ROOMS 152/154

19. A manometer shall verify negative pressure in the contained areas during the entire remediation until final clearance is achieved. This scrubbing shall be performed during all activities of remediation and should be left on for objective post-remediation sampling. These shall run for a minimum of 24 hours before running post remediation sampling after removal is complete.

20. Perform clearance sampling as noted for these areas.

21. Contractor will not tear down containment until written clearance is issued by Consultant.

POST REMEDIATION SAMPLING AND CRITERIA

The contractor should contact the consulting company chosen to perform Post Remediation Clearances a minimum of 48 hours prior to completion of remediation to schedule clearance testing.

Post Remediation Clearance testing will be performed while walk-in enclosures and containments are in place. Devices used to provide negative pressure barriers will remain in use, along with any dehumidifiers or other climate control devices. Any critical barriers applied to openings will remain in place. Contractor may choose to ask for clearance of individual containments but must do so in writing a minimum of 48 hours in advance of containment completion and allow for a minimum of 24 hours of negative pressure HEPA-filtration scrubbing before post-remediation sampling is performed.

Consultant and Contractor will take photos of the completed work for documentation and inclusion in the Passed Final

Clearance Report.

The consultant will perform a visual assessment which will include:

• Determine if all mold contaminated materials identified in the investigation have been removed.

• The containment area(s) and staging area is free of dust and debris.

• All surfaces must be clean. Air sampling may not be performed during or immediately after a rain event.

• The work has been completed in compliance with the remediation protocol and remediation work plan.

Owner/management will provide written proof that a solution for the cause of the water/fungal damage is being sought, repaired and implemented prior to reconstruction and post-remediation sampling. If the visual assessment passes, air sampling will be conducted. Air sampling for mold will be performed using Air O Cell, Allergenco, Versa Trap 37 mm Spore Trap, or similar cassettes. Surface sampling will be performed using a nationally recognized surface lift method.

Prior to sampling, licensed consultant shall perform a laser particulate scan to determine if particle levels in the size range for mold/fungi spores is equal to or less than that of the same measurements in exterior air at the time of measurement. If particle levels are higher than exterior levels, further investigation may be necessary. This scan must be satisfactory prior to air and surface sampling.

One air and one surface sample from a hard surface will be collected in each enclosure/containment. One outside sample will be collected at about the same time outside the building. Outside sampling will be used for comparison. A minimum of two air samples and three surface samples from hard surfaces will be collected from random areas of the staging area during the post remediation sampling at about the same time (within ½ hour) of the sampling in each containment and the baseline exterior sample. Outside sampling will be used for comparison. Air sampling shall be performed in the normal breathing space of occupancy and/or in the remediated wall cavities of the perimeter of the facility.

If the areas do not pass the visual inspection, steps must be taken to correct the deficiencies. Then the area must be re-cleaned, inspected, and tested.

At the conclusion of air sampling, HEPA filter air machines and dehumidifiers (if in use) will be left in operation until analytical results confirm the remediation has been successfully completed and the contractor and owner have received verification of clearance in writing.

When addressing clearance criteria, it is important to note that the ACGIH (American Conference of Governmental

Industrial Hygienists) has not set a Threshold Limit Value (TLV) for microbial/fungi contamination and OSHA has not set a Time Weighted Average (TWA). It is also not expected that either will be addressed due to difficulties in establishing levels that result in health problems or what is normal (which varies greatly in different areas and seasons).

The Department of State Health Services (TDLR), OSHA, or EPA do not address or recognize “toxic” mold but recognize the hazard only by the size of contiguous growth. The industry standard is to compare exterior spore levels and types to those found in the interior of the building. Recently, the Mould and Bacteria Reviews printed a nationally recognized guideline for analyzing numerical data of non-viable and viable mould air samples. These are the standards by which the air in this building will be judged for clearance purposes and are summarized later in this section. However, clearance criteria for surface samples will be accordingly:

1. Any concentration (rare, medium or high) on the surface lifts of the following spore species will be determined as unsatisfactory and will warrant further investigation and/or remediation:

Stachybotrys and Chaetomium

2. Rare concentrations on the surface lifts of the following spore species will be determined as satisfactory and will not prohibit the consultant from issuing clearance: Aspergillus/Penicillium, Cladosporium, Bipolaris, Basidiospores, Ascospores, Alternaria, hyphal fragment or unidentifiable spores. Medium or High concentrations on a surface lift of this spore type will constitute a failed clearance. In addition, other spore types identified in exterior air counts at the same time of surface sampling but not included in this paragraph will be deemed acceptable in rare concentrations other than Stachybotrys and Chaetomium.

3. Medium concentrations on the surface lifts of the following spore types will be determined as satisfactory if found present during exterior air sampling during the same time period of surface sampling (within ½ hour) and will not prohibit the consultant from issuing clearance:

Cladosporium, Bipolaris, Basidiospores, Ascospores, Alternaria, hyphal fragment or unidentifiable spores. In addition, any other naturally occurring spore type identified in the exterior air at the time of air sampling will be scientifically analyzed to determine whether presence on the surface lift is acceptable in this concentration unless otherwise precluded in item

#1 of this section.

4. High counts of any spore type identified on a surface lift will warrant further investigation and/or remediation.

This surface sampling criteria may only be superceded or excluded only if sound scientific reasoning is provided in writing to both contractor and owner and the owner approves of this exclusion prior to the tear down of any enclosure/containment.

Clearance criteria for analytical air samples shall be in accordance with the Guidelines for Interpretation of

Numerical Data of Non-viable Airborne Mould Samples (located also in Appendix A of this report) as outlined in the April 2005 Issue #5, Part 1 and shall constitute a nationally recognized standard. These criteria are summarized in the following:

Guidelines for Interpretation of Numerical Data of Non-viable

Airborne Mould Samples

For a comprehensive assessment of the sample results, all the six steps require to be followed where applicable.

1. Consider the concentrations of spore types which may reach high concentrations in the outside environment (for example Ascospores, Alternaria/Ulocladium, Basidiospores, Cladosporium).

• If the total concentration of these spore types in the indoor air is lower than or equal to 1 to 1.4 times the outside concentration, i.e., Ic ≤ Oc x 1 (+0.4), then indoor source is unlikely (background level).

• If the total concentration of these spore types in the indoor air is lower than or equal to

1.6 (± 0.4) times the outside concentration, i.e., Ic ≤ Oc x 1.6 (± 0.4), then indoor source is possible and further investigations are required.

• If the total concentration of these spore types in the indoor air is more than twice the concentration in outside air, i.e., Ic > Oc x 2, then indoor source is likely and immediate further investigations are required.

2. Consider the concentration of Penicillium/Aspergillus spore types.

• If the difference in concentration between indoor air and outside air is lower than or equal to 300 spores/m3, i.e., Ic - Oc ≤ 300, then indoor source is unlikely (background level).

• If the difference in concentration between indoor air and outside air is greater than 300 spores/m3 but lower than or equal to 800 spores/m3 i.e., Ic - Oc > 300 ≤ 800, then indoor source is possible and further investigations are required.

• If the difference in concentration between indoor air and outside air is more than 800 spores/m3, i.e., Ic - Oc > 800, then indoor source is likely and further investigations are required immediately.

3. Consider the concentration of Chaetomium spp.

• If the concentration in indoor air is lower or equal to the concentration in outside air, i.e., Ic ≤ Oc, then indoor source is unlikely (background level).

• If the difference in concentration between indoor air and outside air is lower than or equal to 5 spores, i.e., Ic - Oc ≤ 5, then indoor source is possible and further investigations are required.

• If the difference in concentration between indoor air and outside air exceeds 5 spores, i.e., Ic - Oc > 5, then indoor source is likely and further investigations are required immediately.

4. Consider the concentration of Stachybotrys spp.

• If the concentration in indoor air is lower or equal to the concentration in outside air, i.e., Ic ≤ Oc, then indoor source is unlikely (background level).

• If the difference in concentration between indoor air and outside air is not more than 2 spores, i.e., Ic - Oc ≤ 2, then indoor source is possible and further investigations are required.

• If the difference in concentration between indoor air and outside air exceeds 2 spores, i.e., Ic - Oc > 2, then indoor source is likely and further investigations are required immediately.

5. Consider the concentration of various other unidentified fungal spores that do not belong to the basidiospore or ascospore types.

• If the difference in concentration between indoor air and outside air is not more than 600 spores/m3, i.e., Ic - Oc ≤ 600, then indoor source is unlikely (background level).

• If the difference in concentration between indoor air and outside air is greater than 600 spores/m3 but not more than 800 spores/m3, i.e., Ic - Oc > 600 ≤ 800, then indoor source is possible and further investigations are required.

• If the difference in concentration between indoor air and outside air is exceeds 800 spores/m3, i.e., Ic - Oc > 800, then indoor source is likely and further investigations are required immediately.

6. Consider the concentration of hyphal fragments.

• If the difference in concentration between indoor air and outside air does not exceed 150 fragments/m3, i.e., Ic - Oc ≤ 150, then indoor source is unlikely (background level).

• If the difference in concentration between indoor air and outside air is greater than 150 fragments/m3 but not more than 300 fragments/m3, i.e., Ic – Oc > 150 ≤ 300, then indoor source is possible and further investigations are required.

• If the difference in concentration between indoor air and outside air exceeds 300 fragments/m3, i.e., Ic - Oc > 300, then indoor source is probable and further investigations are required immediately.

When the indoor source is considered unlikely, the containments and staging area shall be considered satisfactory and will pass clearance. If further investigations are required, further cleaning and/or remediation will occur and re-clearance sampling will be performed.

When clearance is achieved, an acceptable encapsulant may be applied to seal and protect the building materials. Then the remaining polyethylene sheeting can be HEPA vacuumed, wet wiped, and removed for proper disposal.

RECOMMEDED SCOPE OF WORK FOR CONTRACTOR

The work consists of furnishing all parts, labor, and materials as required (except as indicated otherwise in specifications) and performing all work in strict accordance with the plans and specifications for Mold

Containing Materials (MCM) for the site located 2400 S. Gregg in Big Spring, Texas.

Work shall include but not be limited to: preparation, mold removal, Full Containment Method (with decontamination unit and continuously recorded pressure differentials), mold decontamination of walls, floors, ceilings, any objects in containment area, removal and disposal of mold debris.

PROJECT OBJECTIVES

1. Before beginning any work, the Contractor shall provide Consultant with a copy of their Work Plan

(letterhead cover on this protocol is acceptable), and Material Safety Data Sheets for any chemicals to be used.

2. Contractor shall be responsible for establishing and maintaining a respiratory program for all personnel. This includes respiratory fit checks in accordance with OSHA regulations.

3. Contractor shall keep a daily log of all activities pertaining to this project and furnish a copy of this log to the Consultant after the project has passed final clearance.

4. Contractor shall remove all Mold Containing Materials (MCM’s) from areas described in Scope of

Work, Drawings, and this Report.

5. Contractor shall insure that no individual is exposed to MCM’s in excess of levels shown in these specifications.

6. Contractor shall use a continuous recording manometer to document the pressure differential between the containment and the environment. The continuously recording manometer shall be used from the time the containment is ready for remediation work to begin until the project has passed final clearance. A negative pressure differential must be maintained during this time. The manometer recording shall be given to the Consultant after the project has passed final clearance.

7. Contractor shall insure that no mold contamination occurs outside any containment erected by

Contractor.

8. Contractor shall insure that all mold waste is disposed of in accordance with these specifications, no special disposal requirements other than those bagging requirements spelled out herein and offsite disposal in approved landfill. No manifesting necessary.

9. Contractor shall be responsible for preventing non-certified persons from entering the containment area after remediation has started and until the project passes final clearance.

10. Contractor is responsible for obtaining all required permits if any.

DESCRIPTION OF WORK

1. Contractor must field verify types, locations, quantities, and access to MCM’s and any special or unusual circumstances.

2. The purpose of this project is to completely remove all specified mold materials from the structure, floors and areas as scoped herein located at 2400 S. Gregg in Big Spring, TX.

MOLD REMEDIATION CONTRACTOR’S CHECKLIST – APPLICABLE TO

ALL REMEDIATION AREAS SCOPED

NOTE: The Contractor is responsible for removal of Mold Containing Materials from the areas indicated as necessary in this report. Project drawings are not to scale and are only meant to give a general idea of the work. Each Contractor is responsible for his or her own measurements and assessments of the total work involved.

1. Post notices (OSHA, EEOC, MSDS, etc.) at the jobsite that are required by city, county, state and/or federal law.

2. Post a copy each person’s current respirator fit test and training certification(s) at the jobsite in the job book.

3. Contractor shall photo-document containment areas prior to and after completing phase work.

4. Decon area shall consist of at minimum a one stage decontamination unit per EPA Table II Guidelines.

5. Contractor shall provide MSDS for any and all chemicals used for decontamination purposes in the facility before beginning work.

6. A minimum of one neg-air unit must be operating during preparation of the containment. Consultant may field request more units in non-contained areas as well as contained areas.

7. Tyvek/equivalent disposable environmental suits and half-face or full-face masks must be worn during the remediation.

8. Turn off and/or block air conditioning system in contained areas if possible.

9. Put critical barriers on all air conditioning intakes and exhausts if possible. Consultant will determine whether duct cleaning is needed in addition to that performed in Phase One of this protocol based on objective data obtained during or after first area remediated or any other phase following. Consultant may alter these requirements on site in writing to contractor.

10. HEPA-vacuum or wet wipe with biocide all furnishings and curtains in the containment area, remove and store in a clean area or wrap in poly and leave in containment.

11. Prepare the containment area. Preparation of containment includes critical barriers, negative pressurization with HEPA-filtered exhaust (exhaust ducted to outside of containment), a decontamination unit, and a continuous recording manometer. The decontamination unit may be of single stage type with additional stages if contractor chooses or finds necessary. If no asbestos inspection of the property has been made, personnel should assume that any sheetrock, flooring, etc., that is removed contains asbestos.

12. After this point, all personnel entering the containment area must use decon when leaving the containment.

13. Dispose of any carpet that has been wet and has had mold growing on it. HEPA-vac all remaining carpet and flooring if any is left in containment or immediately adjoining containment. Wet wipe or

HEPA-vac all walls and floors inside the containment as well as any contents left inside containment by tenant. Cover any carpet that remains in containment.

14. Double bag all waste, and wet wipe the outside of the outer bag before removing from the containment. Any waste that cannot be bagged must be wrapped in two layers of poly and the outer layer of poly must be wet wiped before removing from the containment.

15. Contractor will be responsible for lining all pathways to the exterior with poly to protect flooring during each phase.

16. Wet wipe with EPA approved biocide or HEPA-vac all exposed walls and floor.

17. Spray EPA approved biocide and/or approved lockdown on all exposed surfaces AFTER clearance has been achieved.

18. Neg-air machines must run a minimum of 24 hours before clearance samples are taken unless

Consultant field verifies this is not necessary through particulate count or visual examination.

TAB 2