This is a Request for Proposal (RFP) and associated solicitation documents for roof replacement services at the VA Dallas Campus. The Department of Veterans Affairs, Veterans Health Administration, Veterans Integrated Service Network 17 is seeking proposals to replace roofs on Building TT-49 (and associated structures) at 4500 South Lancaster Road, Dallas, Texas 75216. The project involves replacing TPO roofs, built-up bituminous roofs, and EPDM roofs with mechanical fastening, new decking, flashing, gutters, downspouts, and waterproofing systems. The estimated contract value is between $100,000 and $250,000. The contractor must provide all labor, equipment, materials, tools, and supervision, complete work within 40 hours of start time, and obtain pre-construction approval from the Contracting Officer's Representative (COR). A mandatory site visit occurred on February 2, 2026, at 1:00 PM CST, with Requests for Information (RFI) due by February 7, 2026, and responses issued by February 13, 2026.

This procurement is set aside exclusively for Service-Disabled Veteran-Owned Small Businesses (SDVOSBs) registered and verified in the SBA's Vendor Information Pages. Proposals are due by February 23, 2026, at 1:00 PM CST via email to miguel.gonzalez4@va.gov, with separate price and technical/past performance documents limited to two 5MB emails. Award will be made to the responsible SDVOSB offeror whose proposal provides the best value based on two evaluation factors: Past Performance (requiring two federal, state, local government, or private contract references of similar scope and size, with CPARS evaluations or Past Performance Questionnaires submitted directly by clients) and Price. The contractor must comply with prevailing wage requirements under the Davis-Bacon Act for Dallas County, Texas, obtain performance and payment bonds, demonstrate an Experience Modification Rate (EMR) of 1.0 or less, have no more than three serious or one repeat/willful OSHA violations in the past three years, and limit subcontracting to 85 percent for general construction (performing at least 15 percent with verified SDVOSBs). Additional requirements include OSHA 30 and 10-hour certifications, financial responsibility documentation, compliance with VA safety and infection control standards, daily site inspections, weekly work schedules, a one-year warranty, and adherence to VHA directives and construction guidelines. The performance period is 90 days from Notice to Proceed.

View the file

Other files

File Type Posted
36C25726Q0221 0004.docx DOCX document
36C25726Q0221 0003.docx DOCX document
Sign in sheet - BLDG TT-49 Replace Roof.pdf PDF
36C25726Q0221 0002.docx DOCX document
36C25726Q0221 0001.docx DOCX document
Attachment 4 - PCRA - Bldg. 2 - 5th Floor.pdf PDF
Attachment 3 - PCRA - TT 49.pdf PDF
Attachment 2 - PCRA - Bldg. 2.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. SOLICITATION NUMBER

2. TYPE OF SOLICITATION

3. DATE ISSUED

PAGE OF PAGES

4. CONTRACT NUMBER

5. REQUISITION/PURCHASE REQUEST NUMBER

6. PROJECT NUMBER

7. ISSUED BY

CODE

8. ADDRESS OFFER TO

a. NAME

b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date) 12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

12b. CALENDAR DAYS

13. ADDITIONAL SOLICITATION REQUIREMENTS:

STANDARD FORM 1442 (REV. 8/2014)

STANDARD FORM 1442

Prescribed by GSA-FAR (48 CFR) 52.236-1(d)

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

SOLICITATION

SOLICITATION

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

9. FOR INFORMATION

CALL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

SEALED BID (IFB)

NEGOTIATED (RFP)

11. The Contractor shall begin performance within ____________ calendar days and complete it within calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See _____________________________).

YES

NO

a.

Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________ (hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.

b.

An offer guarantee is, is not required.

c.

All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d.

Offers providing less than _______________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

none 36C25726Q0221 X 01-23-2026 549-26-871 36C257 Department of Veterans Affairs Network Contract Office 17 1901 Veterans Memorial Dr. Bldg. 171 Temple

TX

76504 Department of Veterans Affairs Network Contract Office 17 1901 Veterans Memorial Dr. Bldg. 171 Temple

TX

76504 Miguel Gonzalez

(915) 282-1732 36C25726Q0221 - TT-49 Roof Replacement

The contractor shall be responsible for providing all labor, materials, equipment, and supervision needed for the project as specified in the Statement of Work, plans and specifications.

Site Visit: February 2, 2026, at 1 pm CST. Meet in Engineering Building 9.

RFI's due by February 7, 2026, at 1:00 pm CST. RFI's shall be submitted to miguel.gonzalez4@va.gov.

RFI responses shall be annotated as an amendment to the solicitation by the close of business, February 13, 2026.

This project is being solicited as a request for proposal (RFP) under NAICS 238160. See “Instruction to Offeror” for additional information.

Note: This requirement is set-aside for SDVOSB's. In order to be eligible for award SDVOSB's must be registered and be a verified in the Vendor Information Pages (www.veterans.certify.sba.gov)

Proposal is due no later than February 23, 2026, by 1:00pm CST. Proposal is to be submitted by email to miguel.gonzalez4@va.gov.

X 52.211-10 X 13:00

CST

02-23-2026 X

14. NAME AND ADDRESS OF OFFEROR

15. TELEPHONE NUMBER

16. REMITTANCE ADDRESS

CODE

FACILITY CODE

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

AMENDMENT

NUMBER

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE

21. ITEMS ACCEPTED:

22. AMOUNT

23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

ITEM

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c)( 41 U.S.C. 3304(a) (

26. ADMINISTERED BY

27. PAYMENT WILL BE MADE BY

PHONE:

FAX:

28. NEGOTIATED AGREEMENT

29. AWARD

Your Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.

shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME OF CONTRACTING OFFICER

TO SIGN

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE

BY

OFFER

AWARD

STANDARD FORM 1442 (REV. 8/2014) BACK

(Include ZIP Code) (Include area code) (Include only if different than Item 14.)

(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each) (Type or print) (4 copies unless otherwise specified) (Type or print) (Type or print) (Contractor is required to sign this document and return _______ copies to issuing office.)

(Contractor is not required to sign this document.)

(Must be fully completed by offeror) (To be completed by Government)

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

36C257 Department of Veterans Affairs Network Contracting Office 17 1901 Veterans Memorial Dr. Bldg. 171 Temple

TX

76504 none Financial Services Center (FSC) Department of Veterans Affairs P.O. Box 149971 Austin

TX

78714-8971 Miguel Gonzalez

VA-VHA-RPOW-2025-0045

Table of Contents

PART I - THE SCHEDULE1
SECTION A - SOLICITATION/CONTRACT FORM1
A.1 SF 1442 SOLICITATION, OFFER, AND AWARD (Construction, Alteration, or Repair)1
A.2 SF 1442 SOLICITATION, OFFER, AND AWARD (CONSTRUCTION, ALTERATION, OR REPAIR)– BACK2
A.3 STATEMENT OF WORK5
A.4 PRICE/COST SCHEDULE13
A.5 OFFEROR’S SELF PERFORMED ESTIMATED CALCULATIONS13
A.6 SPECIAL STANDARD OF RESPONSIBILITY14
A.7 INSTRUCTIONS TO OFFERORS14
A.8 PAST PERFORMANCE EVALUATION QUESTIONNAIRE17
INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS20
2.1 52.216-1 TYPE OF CONTRACT (DEVIATION) (NOV 2025)20
2.2 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014)20
2.3 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014)20
2.4 52.240-90 SECURITY PROHIBITIONS AND EXCLUSIONS REPRESENTATIONS AND CERTIFICATIONS (NOV 2025) (DEVIATION)21
2.5 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)25
REPRESENTATIONS AND CERTIFICATIONS27
GENERAL CONDITIONS28
4.1 52.204-19 INCORPORATION BY REFERENCE OF REPRESENTATIONS AND CERTIFICATIONS (DEC 2014)28
4.2 52.219-14 LIMITATIONS ON SUBCONTRACTING (OCT 2022)28
4.3 52.219-28 POSTAWARD SMALL BUSINESS PROGRAM REREPRESENTATION (JAN 2025)30
4.4 52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (OCT 2022)33
4.5 52.228-13 ALTERNATIVE PAYMENT PROTECTIONS (JULY 2000)38
4.6 52.240-91 SECURITY PROHIBITIONS AND EXCLUSIONS (NOV 2025) (DEVIATION)39
4.7 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)48
4.8 52.222-36 EQUAL OPPORTUNITY FOR WORKERS WITH DISABILITIES (JUN 2020)49
4.9 VAAR 852.219-75 VA NOTICE OF LIMITATIONS ON SUBCONTRACTING—CERTIFICATE OF COMPLIANCE FOR SERVICES AND CONSTRUCTION (JAN 2023) (DEVIATION)50
4.10 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV 2018)52
4.11 VAAR 852.236-71 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (APR 2019)53
4.12 VAAR 852.236-80 SUBCONTRACTS AND WORK COORDINATION (APR 2019)54
4.13 VAAR 852.242-70 GOVERNMENT CONSTRUCTION CONTRACT ADMINISTRATION (OCT 2020)55
4.14 VAAR 852.242-71 ADMINISTRATIVE CONTRACTING OFFICER (OCT 2020)56
4.15 VAAR 852.243-70 CONSTRUCTION CONTRACT CHANGES—SUPPLEMENT (SEP 2019)56
GENERAL STANDARDS58
WAGE DETERMINATIONS58

A.3 STATEMENT OF WORK

VANTHCS Building TT – 49 Roof Replacement Dallas VA Campus

AT 4500 S. LANCASTER ROAD, DALLAST TX 75216

A. GENERAL GUIDANCE

1. Title of Project: VANTHCS Building TT – 49 Roof Repairs Project No. 549-26-871, Dallas VAMC, Dallas, Tx.

Scope of Work: Provide all labor, equipment, materials, tools, and supervision to Replace the below list of Roofs. This condition is affecting patients’ care areas. Replace roofs to prevent water ingress through roof into building. The buildings listed below are located on the VA Dallas Campus at 4500 South Lancaster Rd, Dallas, Texas 75216. The C&A requirements do not apply, and a Security Accreditation Package is not required.

· TPO Roofs

· Prep area for replacement per VA TIL Section 07 54 23

· Replacement per VA TIL Section 07 54 23

· Clean site daily, haul away debris

· Mechanically fasten 60mil TPO over existing roof system, starting at low eaves, with laps running along the length of building.

· Secure perimeter with termination Bar and recommended fasteners.

· Flash over all roof penetrations using GAF Detail membrane.

· Provide relief cuts at all building joints and provide for building expansion, to either side of joints.

· Replace Decking add .5” coverboard

· Remove existing R-Panels & wood Decking below

· Fabricate & install new edge metal to direct water away from leading edge

· Provide overhead fall protection as required.

· Install 6” Gutters & 3” x 4” downspouts along eaves

· Apply Built-up Bituminous Waterproofing

· Replace Flashing

· Apply coating and seal

· Built-up Bituminous Roofing

· Prep area for repair per 07 51 00

· All roof coatings shall have a minimum biobased content of 20% in accordance with ASTM D6866 for certification purposes

· Comply with the recommendations of the NRCA “Roofing and Waterproofing Manual” applicable to built-up roofing for storage, handling and installation.

· EPDM Roof

· Prep area per VA TIL Section 07 53 23

· Please provide daily progress reports to CCR, detailing completed tasks and overall progression. Include any identified issues or potential maintenance concerns for future reference.

· Contractor will provide PORTA POTTY for workers to use while on VA property

· Provide OSHA 30 Supervisor Cards, 10 hour OSHA Cards for Non-Supervisors

0.a. CONTRACTOR RESPONSIBILITIES: The Contractor shall exercise extreme care to avoid damaging Government property such as docks, buildings, and equipment. Any damage to Government property by the Contractor shall be repaired by the Contractor to its original condition at no additional cost to the Government. The Contractor shall ensure that all materials are new, free from defects, imperfections and asbestos free (NO ASBESTOS CONTAINING MATERIALS SHALL BE USED ON THIS PROJECT). If replacement dock levels are required vendor shall provide in like kind (USA Made)
BLDG. TT – 49TPO ROOF
0.b. SCHEDULE OF WORK: The Contractor shall notify the Contracting Officer’s Representative prior to start of work. The Contractor shall schedule work through the COR. The Contractor shall coordinate work with COR NLT 3 days before starting work. Work shall be complete within 40 hours of work start. Other contractors may be working in the same area performing other work. The contractor shall execute work in a manner so as not to impede other contract work. The contractor to work on the roofs concurrently based on roof type and adjacencies.

1. Hours of Work: All work shall be performed between 7:00am and 5:00pm (CST) M-F unless an alternative work schedule is approved by the COR. Federal Holidays are excluded from this schedule.

Federal holidays observed by VANTHCS are:

Labor Day Columbus Day Veteran’s Day Juneteenth Day Thanksgiving Day New Year’s Day Martin Luther King Day President's Day Memorial Day Independence Day Christmas Day

Response time:

a. Contractors shall respond by phone during normal business hours or within (30) minutes after normal business hours.

b. If the problem cannot be corrected by phone or by remote diagnostics the contractor will dispatch a technician to arrive not later than 4 business hours after the call is placed. Uptime commitment shall be 95%.

Performance Period: 90 Days from NTP.

Post construction conference (PreCon) meeting is required and contractor attendance is mandatory.

C. SPECIFIC MANDATORY TASKS AND ASSOCIATED DELIVERABLES:

Repairs within 24hrs pending availability of parts.

D. CHANGES TO THE STATEMENT OF WORK

There shall be no changes to the statement of work.

E. REQUIREMENTS:

The Contractor shall coordinate access to the facility work site with the delegated Contracting Officer's Representative (COR). To minimize disruptions and scheduling of high traffic work areas, Contractor is responsible for submitting an access plan to the COR to assist with minimizing disruption in high traffic areas. This plan must be submitted to the COR for review and approval prior to commencement of work in identified area.

The Contractor shall submit all change order request to the Contracting Officer.

1. The Contractor shall visit the site to determine the full extent of the work. Failure to inspect the site will not constitute grounds for a claim after contract award.

2. Disposal of materials removed under this contract at an approved disposal site in accordance with all local, state, and federal laws, regulations, and guidelines are the Contractor’s sole responsibility. The contractor shall adhere to all OSHA requirements concerning removal, transporting, and disposal of the material.

3. All fire and safety rules and regulations are applicable; Latest OSHA Standards have to be met including but not limited to Construction Safety Guidebook (VHA Center for Engineering & Occupational Safety & Health).

4. The Contractor shall be responsible for obtaining any licenses and permits and complying with any laws, codes, and regulations applicable to the execution of this work as required Federally and by the State of Texas.

5. The contractor shall warrantee work to be free of defects and workmanship for a period of 1 year from date of acceptance.

6. The Contracting Officer and Contracting Officer Representative reserves the right to conduct any inspections or perform any tests deemed necessary at any time during the execution of the contract to determine conformance with the requirements of these specifications.

7. The Contracting Officer reserves the right to conduct any inspections or perform any tests deemed necessary at any time during the execution of the contract to determine conformance with the requirements of these specifications.

8. If chemicals are to be used anywhere in this contract, the chemical must first be approved by the Safety Service here at the VA and MSDS must be obtained.

9. Prior to and during work, the Contractor shall comply with requirements within the VHA Directive 7715 Safety and Health During Construction found at web link http://vaww.ceosh.med.va.gov/01CS/Pages/documents/7715_D_2017-04-06.pdf.

10. Contractors shall conduct preliminary inspections of work site, identify pre-existing site conditions, and coordinate with the COR before performing work in the designated areas.

11. All infection control and safety requirements shall be complied with such as general cleaning, minimizing dust penetrations, secure tools and/or sharp items and adhere to OSHA construction regulations.

12. Prior to commencing and during work, the Contractor shall comply with ALL requirements contained within VANTXHCS Construction Safety Accident Prevention Plan.

13. Contractor shall provide a work schedule to include location, time, and number of workers weekly until the completion of the project. This schedule requires advance notice and approval, therefore, it shall be provided to the COR in advance, a minimum of one week or sooner, for review and approval prior to commencement of work.

14. Contractors shall conduct preliminary inspection of worksite, identify ANY preexisting damage, and notify VA personnel before performing work in the designated area.

15. A Construction Crane plan will be mandatory prior to start of work, if a Construction Crane is needed to complete the roof replacement

16. Contractors shall follow VANTXHCS’ Infection Control standards.

17. Contractor shall follow VANTXHCS' Construction Safety guidelines.

18. Contractor shall follow VANTXHCS’ Patient Safety requirements.

All work shall comply with applicable VA specifications found at www.cfm.va.gov/til/spec.asp.

F. TRAVEL

None

G. CONFIDENTIALITY AND NONDISCLOSURE:

N/A

H. CONTRACTOR PERSONNEL SECURITY REQUIREMENTS:

All Contractors are required to sign in with BLDG 9 (214-875-1005). Visitor’s badges will always be obtained and always worn while on VA property.

I. GENERAL INFORMATION SYSTEM SECURITY

Contractors, contractor personnel, subcontractors, and subcontractor personnel shall be subject to the same Federal laws, regulations, standards, and VA Directives and Handbooks as VA and VA personnel regarding information and information system security.

1. ACCESS TO VA INFORMATION AND VA INFORMATION SYSTEMS

a. A contractor/subcontractor shall request logical (technical) or physical access to VA information and VA information systems for their employees, subcontractors, and affiliates only to the extent necessary to perform the work specified in the contract, agreement, or task order.

b. All contractors, subcontractors, and third-party associates working with VA information are subject to the same investigative requirements as those of VA appointees or employees who have access to the same types of information. The level and process of background security investigations for contractors must be in accordance with VA Directive and Handbook 0710, Personnel Suitability and Security Program. The Office for Operations, Security, and Preparedness is responsible for these policies and procedures.

c. Contract personnel who require access to national security programs must have a valid security clearance. National Industrial Security Program (NISP) was established by Executive Order 12829 to ensure that cleared U.S. defense industry contract personnel safeguard the classified information in their possession while performing work on contracts, programs, bids, or research and development efforts. The Department of Veterans Affairs does not have a Memorandum of Agreement with Defense Security Service (DSS). Verification of a Security Clearance must be processed through the Special Security Officer located in the Planning and National Security Service within the Office of Operations, Security, and Preparedness.

d. Custom software development and outsourced operations must be located in the U.S. to the maximum extent practical. If such work are proposed to be performed abroad and are not disallowed by other VA policy or mandates, the contractor/subcontractor must state where all non-U.S. services are provided and detail a security plan, deemed to be acceptable by VA, specifically to address mitigation of the resulting problems of communication, control, data protection, and so forth. Location within the U.S. may be an evaluation factor.

e. The contractor or subcontractor must notify the Contracting Officer immediately when an employee working on a VA system or with access to VA information is reassigned or leaves the contractor or subcontractor’s employ. The Contracting Officer must also be notified immediately by the contractor or subcontractor prior to an unfriendly termination.

2. VA INFORMATION CUSTODIAL LANGUAGE

a. Information made available to the contractor or subcontractor by VA for the performance or administration of this contract or information developed by the contractor/subcontractor in performance or administration of the contract shall be used only for those purposes and shall not be used in any other way without the prior written agreement of the VA. This clause expressly limits the contractor/subcontractor's rights to use data as described in Rights in Data

- General, FAR 52.227-14(d) (1).

b. VA information should not be co-mingled, if possible, with any other data on the contractors/subcontractor’s information systems or media storage systems in order to ensure VA requirements related to data protection and media sanitization can be met. If co-mingling must be allowed to meet the requirements of the business need, the contractor must ensure that VA’s information is returned to the VA or destroyed in accordance with VA’s sanitization requirements. VA reserves the right to conduct on site inspections of contractor and subcontractor IT resources to ensure data security controls, separation of data and job duties, and destruction/media sanitization procedures are in compliance with VA directive requirements.

c. Prior to termination or completion of this contract, contractor/subcontractor must not destroy information received from VA, or gathered/created by the contractor in the course of performing this contract without prior written approval by the VA. Any data destruction done on behalf of VA by a contractor/subcontractor must be done in accordance with National Archives and Records Administration (NARA) requirements as outlined in VA Directive 6300, Records and Information Management and its Handbook 6300.1 Records Management Procedures, applicable VA Records Control Schedules, and VA Handbook 6500.1, Electronic Media Sanitization. Self-certification by the contractor that the data destruction requirements above have been met must be sent to the VA Contracting Officer within 30 days of termination of the contract.

d. The contractor/subcontractor must receive, gather, store, back up, maintain, use, disclose and dispose of VA information only in compliance with the terms of the contract and applicable Federal and VA information confidentiality and security laws, regulations and policies. If Federal or VA information confidentiality and security laws, regulations and policies become applicable to the VA information or information systems after execution of the contract, or if NIST issues or updates applicable FIPS or Special Publications (SP) after execution of this contract, the parties agree to negotiate in good faith to implement the information confidentiality and security laws, regulations and policies in this contract.

e. The contractor/subcontractor shall not make copies of VA information except as authorized and necessary to perform the terms of the agreement or to preserve electronic information stored on contractor/subcontractor electronic storage media for restoration in case any electronic equipment or data used by the contractor/subcontractor needs to be restored to an operating state. If copies are made for restoration purposes, after the restoration is complete, the copies must be appropriately destroyed.

f. If VA determines that the contractor has violated any of the information confidentiality, privacy, and security provisions of the contract, it shall be sufficient grounds for VA to withhold payment to the contractor or third party or terminate the contract for default or terminate for cause under Federal Acquisition Regulation (FAR) part 12.

g. If a VHA contract is terminated for cause, the associated BAA must also be terminated and appropriate actions taken in accordance with VHA Handbook 1600.01, Business Associate Agreements. Absent an agreement to use or disclose protected health information, there is no business associate relationship.

h. The contractor/subcontractor must store, transport, or transmit VA sensitive information in an encrypted form, using VA-approved encryption tools that are, at a minimum, FIPS 140-2 validated.

i. The contractor/subcontractor’s firewall and Web services security controls, if applicable, shall meet or exceed VA’s minimum requirements. VA Configuration Guidelines are available upon request.

j. Except for uses and disclosures of VA information authorized by this contract for performance of the contract, the contractor/subcontractor may use and disclose VA information only in two other situations: (i) in response to a qualifying order of a court of competent jurisdiction, or (ii) with VA’s prior written approval. The contractor/subcontractor must refer all requests for, demands for production of, or inquiries about, VA information and information systems to the VA contracting officer for response.

k. Notwithstanding the provision above, the contractor/subcontractor shall not release VA records protected by Title 38 U.S.C. 5705, confidentiality of medical quality assurance records and/or Title 38 U.S.C. 7332, confidentiality of certain health records pertaining to drug addiction, sickle cell anemia, alcoholism or alcohol abuse, or infection with human immunodeficiency virus. If the contractor/subcontractor is in receipt of a court order or other requests for the above-mentioned information, that contractor/subcontractor shall immediately refer such court orders or other requests to the VA contracting officer for response.

J. For service that involves the storage, generating, transmitting, or exchanging of VA sensitive information but does not require C&A or an MOU-ISA for system interconnection, the contractor/subcontractor must complete a Contractor Security Control Assessment (CSCA) on a yearly basis and provide it to the COTR.

A.4 PRICE/COST SCHEDULE

ITEM INFORMATION

ITEM NUMBER
DESCRIPTION OF SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
0001
TT-49 Roof Repair
1.00
JB
$________
$________

The contractor shall provide all labor, equipment, tools, materials, supplies and supervision to repair roof TT - 49 in accordance with the Statement of Work.

0002
Payment Bond
1.00
EA
$________
$________

The contractor shall provide all labor, equipment, tools, materials, supplies and supervision to repair roof TT - 49 in accordance with the Statement of Work.

GRAND TOTAL
$________

Page 1 of Page 1 of

A.5 OFFEROR’S SELF PERFORMED ESTIMATED CALCULATIONS

INSTRUCTIONS FOR CALCULATION OF SELF-PERFORMED WORK IAW “Limitations on Subcontracting” (VAAR 852.219-10)

OFFEROR’S SELF PERFORMED ESTIMATED CALCULATIONS

At the time of proposal Offeror’s are required to complete.

a) Offeror’s total proposed price: $ __________

b) Amount projected to be paid to non VIP listed SDVOSBs: $ __________

c) Offeror’s percentage of estimated Non VIP work (b/a X 100 = %) __________%

d) Offeror’s percentage of estimated self-performed work (100 – c = %) __________%

A/E-Services. In the case of a contract for services (except construction), it will not pay more than 50% of the amount paid by the government to it to firms that are not VIP-listed VOSBs.

General construction. In the case of a contract for general construction, it will not pay more than 85% of the amount paid by the government to it to firms that are not VIP-listed SDVOSBs.

Special trade contractors. In the case of a contract for special trade contractors, it will not pay more than 75% of the amount paid by the government to it to firms that are not VIP-listed SDVOSBs.

A.6 SPECIAL STANDARD OF RESPONSIBILITY

Solicitation Submittal Requirements:

The Offeror shall submit the following information: (For a partnership or joint venture, the following submittal requirements are required for each Contractor who is part of the partnership or joint venture and for the entity itself. EMR shall not be submitted for subcontractors.)

1. OSHA or EPA Violation(s):

Offerors shall provide Summary of Work-Related Injuries and Illnesses, affirming that the Offeror has no more than three serious, or one repeat, or one willful OSHA or EPA violation(s) in the past 3 years.

1. Experience Modification Rate (EMR):

Offerors shall provide documentation to show that the offeror has an Experience Modification Rate (EMR) of equal to or less than 1.0.

1. Limitation on Subcontracting:

IAW VAAR 852.219-74 each offeror will review the clause and complete the certificate included in the clause. This certificate will be complete prior to solicitation closing and submitted with the proposal documents. Failure to comply with this requirement will result in removal of proposal for consideration for award.

A.7 INSTRUCTIONS TO OFFERORS

PART I - INSTRUCTIONS, CONDITIONS AND NOTICES TO OFFERORS

PART I/SECTION A – REQUEST FOR PROPOSAL

This is a Request for Proposal in accordance with FAR Part 13. Potential offerors must follow all instructions in order to be compliant with the solicitation.

It is the responsibility of the offeror to verify that their offer is complete. The offeror is responsible for submitting all required forms and documents with the offer.

The Government will award a single contract resulting from this solicitation to a responsible SDVOSB offeror whose offer conforming to the solicitation will be most advantageous to the Government based on Past Performance and Price.

I.1A JOINT VENTURES

If submitting an offer as a joint venture as defined by P.L. 109-461 AND Department of Veterans Affairs I.L. 049-06-4, http://www.vetbiz.gov/library/jtventure.pdf , an offeror must provide a copy of the joint venture agreement specific to the project that is consistent with the percentage of required work and net proceed. Additionally, the offeror must provide a breakdown or labor of which is to be performed by the SDVOSB firm and that which is performed by the small business joint venture firm and that which is sub-contracted. All Joint Ventures will be required to be registered and verified as an entity in VETBIZ.

I.2A SELECTION CRITERIA/ PROPOSAL PREPARATION INSTRUCTIONS

Quotes will be evaluated in accordance with FAR 13.106 Simplified Acquisition Procedures Award will be made based on the following factors:

Factor 1 – Past Performance Factor 2-- Price Offerors are encouraged to provide their best offers with the past performance information requested for evaluation. The Government, based on the offered material presented, will award to the offeror that best demonstrates to be most advantageous for the Government.

Factor 1 - Past Performance: Offerors shall provide past performance information on two (2) federal, state, local government or private contract of similar type, scope, size and complexity. If a completed Contractor Performance Assessment Reporting System (CPARS) evaluation is available, it shall be submitted with the quote. The Government may also evaluate recent and relevant past performance, based upon sources available to the contracting officer that may include Past Performance Information Retrieval System (PPIRS), Federal Awardee Performance and Integrity Information System (FAPIIS) and Electronic Subcontract Reporting System (eSRS). IF THE OFFEROR CANNOT PROVIDE A CPARS FOR PROJECTS LISTED IN FACTOR 1, then the offeror shall submit Past Performance Questionnaires (PPQ).

Completed PPQs should be submitted directly from your client via email to miguel.gonzalez4@va.gov. If you have any questions, please contact Miguel Gonzalez at miguel.gonzalez4@va.gov. If the offeror is unable to contact a client for a project(s) before closing date, the offeror should complete and submit with the quote the first page of the PPQ, which will provide contract and client information for the respective project(s). Offerors should follow-up with clients/references to ensure timely submittal of questionnaires.

Basis of Evaluation: Past Performance will be evaluated in accordance with FAR 13.106-2 and award will be made to the offeror presenting the best value to the Government.

Factor 2 - Price: Offerors shall provide pricing as requested in the Schedule of Service identified within the SF1442 The Government will award a contract resulting from this solicitation to the responsible offeror whose offer conforming to the solicitation will be most advantageous to the Government, price and other factors considered.

SAFETY

(a) Solicitation Submittal Requirements:

The Offeror shall submit the following information: (For a partnership or joint venture, the following submittal requirements are required for each Contractor who is part of the partnership or joint venture and for the entity itself. EMR shall not be submitted for subcontractors.)

(1) OSHA or EPA Violation(s):

Offerors shall provide Summary of Work-Related Injuries and Illnesses, affirming that the Offeror has no more than three serious, or one repeat, or one willful OSHA or EPA violation(s) in the past 3 years

(2) Experience Modification Rate (EMR):

Offerors shall provide documentation to show that the offeror has an Experience Modification Rate (EMR) of equal to or less than 1.0.

PART I/SECTION B - INSTRUCTIONS, CONDITIONS AND NOTICES TO OFFERORS

I.1B COST RANGE: Between $100,000 and $250,000 If a product is manufactured to metric dimensions and those dimensions exceed the tolerance specified in the inch-pound units, a request should be made to the Contracting Officer to determine if the product is acceptable. The Contracting Officer, in concert with the Contracting Officer’s Representative (COR), will accept or reject the product.

I.2B REQUESTS FOR INFORMATION:

All requests for information must be submitted in writing to the Contracting Officer for action no later than the date shown in Block 10 of the Standard Form 1442, Solicitation, Offer and Award.

I.3B PROPOSAL REQUIREMENTS

General – Proposal shall be submitted in response to this solicitation. Proposal shall be submitted via email to miguel.gonzalez4@va.gov. Emails are limited to five (5) MB. The quote, in its entirety, shall not exceed two emails (one email for price, and one email for technical/past performance) of 5MB each. Price shall be in a separate electronic document from the technical and past performance portions of the quote. Failures to submit in the format required and clearly address those factors may result in rejection of the offer. Further details on electronic submission are outlined below. Offerors shall include all required Representations and Certifications and complete their registration in System for Award Management (SAM). See FAR 52.204-7 and 52.204-8, of this solicitation.

Proposal shall be received by 1:00 PM Central Standard Time on February 23, 2026. There will be no public opening. Submit quotes to: miguel.gonzalez4@va.gov.

A.8 PAST PERFORMANCE EVALUATION QUESTIONNAIRE

Your Company Letterhead

Date:_________________
To:______________________________________

We have listed your firm as a reference for the work we have performed for you as listed below. Our firm has submitted a proposal under a project advertised by the Department of Veterans Affairs- Central Texas Health Care System, VA North Texas Health Care System, Dallas, Texas.

In accordance with Federal Acquisition Regulations (FAR), they will evaluate our firm's past performance. Your candid response to the attached questionnaire will assist the evaluation team in this process. We understand that you have a busy schedule and your participation in this evaluation is greatly appreciated. Please complete the enclosed questionnaire as thoroughly as possible. Space is provided for comments. Complete confidentiality will be maintained. Only one response from each office is required.

Please send your completed questionnaire to the following address to arrive NOT LATER THAN February 23, 2026 at 1pm CST.

DO NOT return them to our company.

Email to: Miguel.Gonzalez4@va.gov Subject: 36C25726Q0221 - TT-49 Roof Replacement If you have questions regarding the attached questionnaire, or require assistance, please contact the Contracting Officer at Miguel.Gonzalez4@va.gov Thank you for your assistance.

Signature and Title

1. How would you rate the Offeror’s compliance with the contract requirements?

EVGSMUN (circle one)
REMARKS:

1. How would you rate the effectiveness of the Offeror’s on-site management?

EVGSMUN (circle one)
REMARKS:

1. How would you rate the Offeror’s use of appropriate personnel for contract requirements?

EVGSMUN (circle one)
REMARKS:
1. How would you rate the Offeror’s timeliness in submission of schedule?Reports? Submittals?
EVGSMUN (circle one)
REMARKS:

1. How would you rate the Offeror’s adherence to the construction schedule?

EVGSMUN (circle one)
REMARKS:

1. How would you rate the Offeror’s responsiveness towards safety issues?

EVGSMUN (circle one)
REMARKS:

1. How would you rate the Offeror’s ability to effectively deal with the customer and other Government personnel?

EVGSMUN (circle one)
REMARKS:

1. How would you rate the Offeror’s cooperativeness in solving problems and negotiating changes?

EVGSMUN (circle one)
REMARKS:

1. How would you rate the Offeror’s abilities to address any financial difficulties (i.e., payment of subcontractors and/or vendors, labor disputes, etc.)?

EVGSMUN (circle one)
REMARKS:
1. How would you rate the Offeror’s responsiveness to cure notices, showcause letters, suspension of payment, or termination notices?
EVGSMUN (circle one)
REMARKS:

1. As the end user/customer, how would you rate your satisfaction with the end product?

EVGSMUN (circle one)
REMARKS:

1. How would you rate the Offeror’s overall performance on this project?

EVGSMUN (circle one)
REMARKS:

1. Would you recommend or use this contractor again?

EVGSMU(circle one)
REMARKS:

INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS

2.1 52.216-1 TYPE OF CONTRACT (DEVIATION) (NOV 2025)

The Government contemplates award of a Firm-Fixed-Price contract resulting from this solicitation.

(End of Provision)

2.2 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014) (a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements, of this solicitation.

(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.

(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.

(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.

(End of Provision)

2.3 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014)

(a) Definitions. "Commercially available off-the-shelf (COTS) item," "construction material," "domestic construction material," and "foreign construction material," as used in this provision, are defined in the clause of this solicitation entitled "Buy American—Construction Materials" (Federal Acquisition Regulation (FAR) clause 52.225-9).

(b) Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of the clause at FAR 52.225-9 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.

(c) Evaluation of offers.

(1) The Government will evaluate an offer requesting exception to the requirements of the Buy American statute, based on claimed unreasonable cost of domestic construction material, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(3)(i) of the clause at FAR 52.225-9.

(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.

(d) Alternate offers.

(1) When an offer includes foreign solicitation in paragraph (b)(2) of the clause at FAR 52.225-9, the offeror also may submit an alternate offer based on use of equivalent domestic construction material.

(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of the clause at FAR 52.225-9 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.

(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of the clause at FAR 52.225-9 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic construction material, and the offeror shall be required to furnish such domestic construction material. An offer based on use of the foreign construction material for which an exception was requested—

(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or

(ii) May be accepted if revised during negotiations.

(End of Provision)

2.4 52.240-90 SECURITY PROHIBITIONS AND EXCLUSIONS REPRESENTATIONS AND CERTIFICATIONS (NOV 2025) (DEVIATION)

(a) Definitions. As used in this provision— Backhaul, covered article, covered telecommunications equipment or services, critical technology, FASCSA order, Intelligence community, interconnection arrangements, national security system, roaming, sensitive compartmented information, sensitive compartmented information system, source, and substantial or essential component have the meanings provided in the clause 52.240-91, Security Prohibitions and Exclusions.

Business operations means engaging in commerce in any form, including by acquiring, developing, maintaining, owning, selling, possessing, leasing, or operating equipment, facilities, personnel, products, services, personal property, real property, or any other apparatus of business or commerce.

Marginalized populations of Sudan means—

(1) Adversely affected groups in regions authorized to receive assistance under section 8(c) of the Darfur Peace and Accountability Act (Pub. L. 109-344) (50 U.S.C. 1701 note); and

(2) Marginalized areas in Northern Sudan described in section 4(9) of such Act.

Restricted business operations means business operations in Sudan that include power production activities, mineral extraction activities, oil-related activities, or the production of military equipment, as those terms are defined in the Sudan Accountability and Divestment Act of 2007 (Pub. L. 110-174). Restricted business operations do not include business operations that the person (as that term is defined in Section 2 of the Sudan Accountability and Divestment Act of 2007) conducting the business can demonstrate—

(1) Are conducted under contract directly and exclusively with the regional government of southern Sudan;

(2) Are conducted under specific authorization from the Office of Foreign Assets Control in the Department of the Treasury, or are expressly exempted under Federal law from the requirement to be conducted under such authorization;

(3) Consist of providing goods or services to marginalized populations of Sudan;

(4) Consist of providing goods or services to an internationally recognized peacekeeping force or humanitarian organization;

(5) Consist of providing goods or services that are used only to promote health or education; or

(6) Have been voluntarily suspended.

Sensitive technology—

(1) Means hardware, software, telecommunications equipment, or any other technology that is to be used specifically—

(i) To restrict the free flow of unbiased information in Iran; or

(ii) To disrupt, monitor, or otherwise restrict speech of the people of Iran; and

(2) Does not include information or informational materials the export of which the President does not have the authority to regulate or prohibit pursuant to section 203(b)(3) of the International Emergency Economic Powers Act (50 U.S.C. 1702(b)(3)).

(b) Procedures.

(1) Covered telecommunications and video surveillance. The Offeror shall review the list of excluded parties in the System for Award Management (SAM) at https://www.sam.gov for entities excluded from receiving federal awards for “covered telecommunications equipment or services.”

(2) FASCSA Orders.

(i) The Offeror shall search in SAM for the phrase “FASCSA order” for any covered article, or any products or services produced or provided by a source, if there is an applicable FASCSA order described in paragraph (e) of FAR 52.240-91, Security Prohibitions and Exclusions.

(ii) The Offeror shall review the solicitation for any FASCSA orders that are not in SAM but are effective and apply to the solicitation and resultant contract (see FAR 40.204-1(c)(2)).

(iii) FASCSA orders issued after the date of solicitation do not apply unless added by an amendment to the solicitation.

(c) Covered telecommunications equipment or services representations. By submission of its offer, the Offeror represents that, after conducting a reasonable inquiry (that looks at any information in the Offeror’s possession but does not need to include an internal or third-party audit)—

(1) It will not provide covered telecommunications equipment or services to the Government in the performance of any contract, subcontract or other contractual instrument resulting from this solicitation, except as waived by the solicitation, or as disclosed in paragraph (g); and

(2) It does not use covered telecommunications equipment or services, or use any equipment, system, or service that uses covered telecommunications equipment or services, except as waived by the solicitation, or as disclosed in paragraph (g).

(d) FASCSA Representation. By submission of this offer, the offeror represents that it has conducted a reasonable inquiry, and that the offeror does not propose to provide or use in response to this solicitation any covered article, or any products or services produced or provided by a source, if the covered article or the source is prohibited by an applicable FASCSA order in effect on the date the solicitation was issued, except as waived by the solicitation, or as disclosed in paragraph (g). A reasonable inquiry will look at any information in the offeror’s possession but does not need to include an internal or third-party audit.

(e) Sudan certification. By submission of its offer, the offeror certifies, after conducting a reasonable inquiry (that looks at any information in the offeror’s possession but does not need to include an internal or third-party audit), that the offeror does not conduct any restricted business operations in Sudan.

(f) Iran Representation and Certifications.

(1) Except as provided in paragraph (f)(2) of this provision or if a waiver has been granted in accordance with FAR 40.203-3, the offeror, after conducting a reasonable inquiry (that looks at any information in the offeror’s possession but does not need to include an internal or third-party audit), by submission of its offer—

(i) Represents, to the best of its knowledge and belief, that the offeror does not export any sensitive technology to the government of Iran or any entities or individuals owned or controlled by, or acting on behalf or at the direction of, the government of Iran;

(ii) Certifies that the offeror, or any person (as defined at section 15 of the Iran Sanctions Act of 1996, Pub. L. 104-172, 50 U.S.C. 1701 note) owned or controlled by the offeror, does not engage in any activities for which sanctions may be imposed under section 5 of the Act. These sanctioned activities are in the areas of development of the petroleum resources of Iran, production of refined petroleum products in Iran, sale and provision of refined petroleum products to Iran, and contributing to Iran’s ability to acquire or develop certain weapons or technologies; and

(iii) Certifies that the offeror, and any person owned or controlled by the offeror, does not knowingly engage in any transaction that exceeds $15,000 with Iran’s Revolutionary Guard Corps or any of its officials, agents, or affiliates, the property and interests in property of which are blocked pursuant to the International Emergency Economic Powers Act (50 U.S.C. 1701 et seq.) (see OFAC’s Specially Designated Nationals and Blocked Persons List at https://www.treasury.gov/resource-center/sanctions/SDN-List/Pages/default.aspx)

(2) Exception for trade agreements. The representation and certification requirements of paragraph (f)(1) of this provision do not apply if—

(i) This solicitation includes a trade agreements notice or certification (e.g., 52.225-6, Trade Agreements Certificate); and

(ii) The offeror has certified that all the offered products to be supplied are designated country end products or designated country construction material.

(iii) The offeror shall email questions concerning sensitive technology to the Department of State at CISADA106@state.gov.

(g) Disclosure.

(1) If the Offeror is not able to represent compliance with the prohibitions in paragraphs (c) or (d), then the Offeror shall disclose within 72 hours to the contracting office identified in paragraph (g)(2) the following information for each product or service not compliant:

(i) Contract number and order number, if applicable;

(ii) Identification of whether this disclosure relates to paragraph (c) on covered telecommunication equipment or services, or to paragraph (d) on FASCSA orders;

(iii) A description of the products or services that the Contractor identifies or has reason to suspect is prohibited (include brand; model number, such as the original equipment…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .