About this file

This is a budgeting and cost analysis document for a five-year corrective maintenance and repair obligation for a campus-wide fire alarm system at a VA medical facility following system acceptance.

The project encompasses 22 buildings plus one parking garage with a new networked fire alarm system including two Fire Alarm Control Units, graphical workstations, digital voice evacuation, thousands of addressable devices, and interfaces with elevators, HVAC, fire pumps, generators, kitchen suppression, door controls, and sprinkler systems in a 24/7 hospital environment. The document provides recommended annual repair budgets ranging from $35,000 in Year 1 to $75,000 in Year 5, totaling $275,000 over five years (approximately 0.5%–0.8% of anticipated construction value). Typical annual repair costs are itemized by category, including detector replacements ($6,000), horn/strobes/speakers ($4,000), monitor/control modules ($5,000), NAC/SLC/network troubleshooting ($7,000), fiber/network communication repairs ($4,500), and miscellaneous service parts ($8,000), with a typical annual total of $45,000–$55,000. Labor expectations for a typical year total 475 hours annually across emergency service calls (120 hours), troubleshooting intermittent faults (90 hours), device replacement (110 hours), programming changes (35 hours), network diagnostics (40 hours), functional testing (60 hours), and documentation updates (20 hours). At a fully burdened labor rate of $145–$165 per hour, labor alone represents approximately $70,000 of effort, though actual expenditures are generally lower. For Design-Bid-Build contract budgeting purposes, the document recommends minimum acceptable budget of $250,000, a recommended budget of $300,000 (approximately $60,000 per year), or a conservative budget of $350,000 for contractor risk mitigation.

View the file

Other files

Show all 18

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Based on the design narrative, this project is significantly more complex than a typical commercial fire alarm installation. It includes:

22 buildings plus one parking garage

A new campus-wide networked fire alarm system

Two campus Fire Alarm Control Units (FACUs)

Graphical workstation with touchscreen and printer

Digital voice evacuation

Thousands of addressable devices

Interfaces with elevators, HVAC, fire pumps, generators, kitchen suppression, door controls, fire doors, sprinkler systems, etc.

24/7 hospital environment with defend-in-place sequencing in several patient care buildings.

Because this is a brand-new system, the first five years typically experience relatively few equipment failures. Most repairs involve damaged devices, construction impacts, nuisance alarms, lightning/transient damage, failed power supplies, batteries, notification appliances, network modules, or isolated detector failures rather than widespread equipment replacement.

Recommended Annual Repair Budget

Year Estimated Repair Budget

Year 1 $35,000

Year 2 $45,000

Year 3 $55,000

Year 4 $65,000

Year 5 $75,000

Five-Year Total: $275,000

This equates to roughly 0.5%–0.8% of the anticipated construction value of a campus-wide replacement system, which is consistent with industry experience for large healthcare campuses.

Typical Annual Repair Costs

VA.WAC Fire Alarm - 100% Bid S…

Repair Item Estimated Annual Cost

Detector replacements (damaged/failed) $6,000

Manual pull stations $1,000

Horn/strobes/speakers $4,000

Monitor/control modules $5,000

NAC/SLC/network troubleshooting $7,000

Power supplies/battery chargers $3,000

Replacement batteries $4,000

Graphic workstation repairs $2,500

Fiber/network communication repairs $4,500

Miscellaneous service parts $8,000

Typical Annual Total ≈ $45,000–55,000

Labor Expectations

A typical year might include:

Service Activity Estimated Hours

Emergency service calls 120 hrs

Troubleshooting intermittent faults 90 hrs

Device replacement 110 hrs

Programming changes 35 hrs

Network diagnostics 40 hrs

Functional testing after repairs 60 hrs

Documentation/as-built updates 20 hrs

Service Activity Estimated Hours

Total 475 hours/year

At an average fully burdened labor rate of $145–165/hour, labor alone represents approximately $70,000 of effort. However, actual annual expenditures are generally lower because many years require substantially fewer labor hours and not all contingencies materialize.

Typical Repairs Over Five Years

Large VA medical center campuses commonly experience:

Damaged smoke detectors from renovations

Speaker/strobe failures

Water-damaged devices

Failed monitor/control modules

Battery replacement outside scheduled maintenance

Fiber communication troubleshooting

Lightning or power surge damage

Graphic workstation hardware failures

Fire pump and generator interface issues

Elevator recall troubleshooting

Door holder failures

Replacement of damaged manual pull stations

These are generally isolated events rather than systemic failures on a new installation.

Budget Recommendation for Contracting

If this budget will be included in a VA Design-Bid-Build contract as the contractor's obligation to perform corrective repairs for five years after acceptance, I recommend budgeting:

Minimum acceptable: $250,000

Recommended: $300,000

Conservative (low risk to contractor): $350,000

A $300,000 allowance (approximately $60,000 per year) is a realistic figure for a 23-structure VA medical campus with a new networked addressable fire alarm system. It provides sufficient coverage for normal corrective maintenance and repairs while remaining well below the cost of a full-service maintenance contract that includes inspections, testing, and preventive maintenance.