Revised Bid Schedule SECTION B.pdf
PDF 195 KB Posted
- Attached to
- 6150--674A4-19-101 Replace Primary Medium Voltage Switchgear Federal contract opportunity
- Solicitation number
- 36C25722B0014
About this file
This bid schedule outlines pricing and specifications for the replacement of primary electrical medium voltage switchgear at the Doris Miller VA Medical Center in Waco, Texas. The base bid includes all labor, materials and equipment to replace the existing switchgear in Building 216. Five add alternates are provided to accommodate additional scope of work including replacing transformers and removing overhead conductors, capacitor banks and switchgear in other buildings. Pricing is requested for the base bid alone and cumulatively with each add alternate. The project duration is 365 calendar days from notice to proceed. This procurement is set aside solely for Service-Disabled Veteran-Owned Small Businesses and has an estimated value between $2-5 million.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 251010 ADVANCED UTILITY METERING SYSTEM_ADD1.pdf | ||
| Answers 36C25722B0014 Replace Primary MV Switchgear Waco VAMC RFI-Questions - 1-66.pdf | ||
| 261313 MEDIUM-VOLTAGE CIRCUIT BREAKER SWITCHGEAR_ADD1r1.pdf | ||
| 36C25722B0014 0006.docx | DOCX document | |
| SELF-PERFORMED CALCULATIONS.pdf | ||
| OSHA - EMR requirement.pdf | ||
| 36C25722B0014 0004.docx | DOCX document | |
| 36C25722B0014 0003.docx | DOCX document | |
| Pre-Bid site visit sign in sheet 674A4-19-101.pdf | ||
| 36C25722B0014 0002.docx | DOCX document | |
| 36C25722B0014 0001.docx | DOCX document | |
| Waco Electrical Feeder Drw.pdf | ||
| 36C25722B0014_1.docx | DOCX document | |
| 21-09-29-1908-7 VA-Switchgear_Sealed.pdf | ||
| 21-09-30_VA Switchgear Specifications_Sealed.pdf |
Show all 15
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION B – SCHDULE OF PRICES/DESCRIPTION
DESCRIPTION: Contractor shall provide all necessary labor, materials, equipment, and supervision to Replacement of Primary Electrical MV Switchgear located at the Doris Miller VAMC, 4800 Memorial Drive, Waco, Texas 76711. The work shall be in accordance with the provided specifications and drawings.
** NOTE: Award shall be made on the Base Bid unless the base bid is less than the allocated funding for the project. If the Base Bid is less than allocated funding, award shall be made, in order, on the basis of a Add Alternates beginning with Add Alternate #1 to accommodate allocated funding. Offerors must bid all items in order to be considered.
BASE BID:
ITEM UNIT TOTAL
NO. DESCRIPTION OF SERVICE QTY UNIT PRICE AMOUNT
BID:
0001 PROVIDE ALL NECESSARY 1 JB $___________ $_________
LABOR, MATERIALS, AND EQUIPMENT
NECESSARY FOR REPLACEMENT
SWITCHGEAR IN EXISTING BUILDING 216
AS SHOWN ON CONTRACT DOCUMENTS.
(SEE GENERAL REQUIREMENT 1.3 STATEMENT
OF BID ITEMS, PARAGRAPH A, BASE BID)
0002 COST OF PERFORMANCE AND 1 EA $___________ $_________
PAYMENT BONDS
**TOTAL PROJECT DURATION for Base Bid: 365 Calendar days from issuance of the Notice to Proceed to complete the project work.
Base Bid TOTAL (Line items 0001 & 0002) $____________
Base Bid + Bid Add Alternate #1:
0003 Base Bid: PROVIDE ALL NECESSARY 1 JB $___________ $_________
LABOR, MATERIALS, AND EQUIPMENT
NECESSARY FOR REPLACEMENT
SWITCHGEAR IN EXISTING BUILDING 216
AS SHOWN ON CONTRACT DOCUMENTS.
(SEE GENERAL REQUIREMENT 1.3 STATEMENT
OF BID ITEMS, PARAGRAPH A, BASE BID
0004 AND ADD TO INCLUDE ADD ALTERNATE #1: 1 JB $__________ $_________
PROVIDE ALL NECESSARY LABOR, MATERIALS,
AND EQUIPMENT NECESSARY FOR REPLACEMENT
OF FOUR (4) TRANSFORMERS, T18, T24, T160 AND T-159.
(SEE GENERAL REQUIREMENT 1.3 STATEMENT
OF BID ITEMS, PARAGRAPH B, BASE BID,
ITEMS ADD ALTERNATE #1)
0005 COST OF PERFORMANCE AND 1 EA $___________ $_________
PAYMENT BONDS
**TOTAL PROJECT DURATION for both the Base Bid and Bid Alterante #1: 365 Calendar days from issuance of the Notice to Proceed to complete the project work.
Base Bid + Bid Alternate #1 TOTAL (Line items 0003, 0004 & 0005) $____________
Base Bid + Bid Add Alternate #1 + Bid Add Alternate #2
0006 Base Bid: PROVIDE ALL NECESSARY 1 JB $___________ $_________
LABOR, MATERIALS, AND EQUIPMENT
NECESSARY FOR REPLACEMENT
SWITCHGEAR IN EXISTING BUILDING 216
AS SHOWN ON CONTRACT DOCUMENTS.
(SEE GENERAL REQUIREMENT 1.3 STATEMENT
OF BID ITEMS, PARAGRAPH A, BASE BID
0007 AND ADD TO INCLUDE ADD ALTERNATE #1: 1 JB $__________ $_________
PROVIDE ALL NECESSARY LABOR, MATERIALS,
AND EQUIPMENT NECESSARY FOR REPLACEMENT
OF THREE (3) TRANSFORMERS.
(SEE GENERAL REQUIREMENT 1.3 STATEMENT
OF BID ITEMS, PARAGRAPH B, BASE BID,
ITEMS ADD ALTERNATE #1)
0008 AND ADD TO INCLUDE ADD ALTERNATE #2: 1 JB $__________ $_________
REMOVE EXISTING OVERHEAD CONDUCTORS, ELEC.
POLES AND INTERCONNECTING WIRE. POLE FOUNDATIONS
REMOVED TO 3’-0” BELOW EXISTING GROUND LEVEL.
(SEE GENERAL REQUIREMENT 1.3 STATEMENT
OF BID ITEMS, PARAGRAPH B, BASE BID,
ITEMS ADD ALTERNATE #2)
0009 COST OF PERFORMANCE AND 1 EA $___________ $_________
PAYMENT BONDS
**TOTAL PROJECT DURATION for both the Base Bid and Bid Alterante #1: 365 Calendar days from issuance of the Notice to Proceed to complete the project work.
Base Bid + Bid Alternate #1 + Bid Alternate #2 TOTAL (Line items 0006, 0007, 0008& 0009) $____________
Base Bid + Bid Add Alternate #1 + Bid Add Alternate #2 + Bid Add Alternate #3
0010 Base Bid: PROVIDE ALL NECESSARY 1 JB $___________ $_________
LABOR, MATERIALS, AND EQUIPMENT
NECESSARY FOR REPLACEMENT
SWITCHGEAR IN EXISTING BUILDING 216
AS SHOWN ON CONTRACT DOCUMENTS.
(SEE GENERAL REQUIREMENT 1.3 STATEMENT
OF BID ITEMS, PARAGRAPH A, BASE BID
0011 AND ADD TO INCLUDE ADD ALTERNATE #1: 1 JB $___________ $_________
PROVIDE ALL NECESSARY LABOR, MATERIALS,
AND EQUIPMENT NECESSARY FOR REPLACEMENT
OF THREE (3) TRANSFORMERS.
(SEE GENERAL REQUIREMENT 1.3 STATEMENT
OF BID ITEMS, PARAGRAPH B, BASE BID,
ITEMS ADD ALTERNATE #1)
0012 AND ADD TO INCLUDE ADD ALTERNATE #2: 1 JB $__________ $_________
REMOVE EXISTING OVERHEAD CONDUCTORS, ELEC.
POLES AND INTERCONNECTING WIRE. POLE FOUNDATIONS
REMOVED TO 3’-0” BELOW EXISTING GROUND LEVEL.
(SEE GENERAL REQUIREMENT 1.3 STATEMENT
OF BID ITEMS, PARAGRAPH B, BASE BID,
ITEMS ADD ALTERNATE #2)
0013 AND ADD TO INCLUDE ADD ALTERNATE #3: 1 JB $__________ $_________
REMOVE EXISTING CAPACITOR BANK, REMOVE EXISTING
MAIN SWITCHGEAR, BLDG. 133 AND BLDG. 133 FOUNDATION
DOWN TO 3’-0” BELOW EXISTING GROUND ELEVATION.
(SEE GENERAL REQUIREMENT 1.3 STATEMENT
OF BID ITEMS, PARAGRAPH B, BASE BID,
ITEMS ADD ALTERNATE #3)
0014 COST OF PERFORMANCE AND 1 EA $___________ $_________
PAYMENT BONDS
**TOTAL PROJECT DURATION for both the Base Bid and Bid Alterante #1: 365 Calendar days from issuance of the Notice to Proceed to complete the project work.
Base Bid + Bid Alternate #1 + Bid Alternate #2 + Bid Alternate #3 TOTAL (Line items 0010, 0011, 0012, 0013 & 0014) $____________
Base Bid + Bid Add Alternate #1 + Bid Add Alternate #2 + Bid Add Alternate #3 + Bid Add Alternate #4
0015 Base Bid: PROVIDE ALL NECESSARY 1 JB $___________ $_________
LABOR, MATERIALS, AND EQUIPMENT
NECESSARY FOR REPLACEMENT
SWITCHGEAR IN EXISTING BUILDING 216
AS SHOWN ON CONTRACT DOCUMENTS.
(SEE GENERAL REQUIREMENT 1.3 STATEMENT
OF BID ITEMS, PARAGRAPH A, BASE BID
0016 AND ADD TO INCLUDE ADD ALTERNATE #1: 1 JB $___________ $_________
PROVIDE ALL NECESSARY LABOR, MATERIALS,
AND EQUIPMENT NECESSARY FOR REPLACEMENT
OF THREE (3) TRANSFORMERS.
(SEE GENERAL REQUIREMENT 1.3 STATEMENT
OF BID ITEMS, PARAGRAPH B, BASE BID,
ITEMS ADD ALTERNATE #1)
0017 AND ADD TO INCLUDE ADD ALTERNATE #2: 1 JB $__________ $_________
REMOVE EXISTING OVERHEAD CONDUCTORS, ELEC.
POLES AND INTERCONNECTING WIRE. POLE FOUNDATIONS
REMOVED TO 3’-0” BELOW EXISTING GROUND LEVEL.
(SEE GENERAL REQUIREMENT 1.3 STATEMENT
OF BID ITEMS, PARAGRAPH B, BASE BID,
ITEMS ADD ALTERNATE #2)
0018 AND ADD TO INCLUDE ADD ALTERNATE #3: 1 JB $__________ $_________
REMOVE EXISTING CAPACITOR BANK, REMOVE EXISTING
MAIN SWITCHGEAR, BLDG. 133 AND BLDG. 133 FOUNDATION
DOWN TO 3’-0” BELOW EXISTING GROUND ELEVATION.
(SEE GENERAL REQUIREMENT 1.3 STATEMENT
OF BID ITEMS, PARAGRAPH B, BASE BID,
ITEMS ADD ALTERNATE #3)
0019 AND ADD TO INCLUDE ADD ALTERNATE #4: 1 JB $__________ $_________
REMOVE THREE COOLING TOWERS AND ASSOCIATED
CONCRETE AND PIPING TO B216.
(SEE GENERAL REQUIREMENT 1.3 STATEMENT
OF BID ITEMS, PARAGRAPH B, BASE BID,
ITEMS ADD ALTERNATE #4)
0020 COST OF PERFORMANCE AND 1 EA $___________ $_________
PAYMENT BONDS
**TOTAL PROJECT DURATION for both the Base Bid and Bid Alterante #1: 365 Calendar days from issuance of the Notice to Proceed to complete the project work.
Base Bid + Bid Alternate #1 + Bid Alternate #2 + Bid Alternate #3 + Bid Alternate #4 TOTAL (Line items 0015, 0016, 0017, 0018, 0019 & 0020) $____________
Base Bid + Bid Add Alternate #1 + Bid Add Alternate #2 + Bid Add Alternate #3 + Bid Add Alternate #4 + Bid Add Alternate #5
0021 Base Bid: PROVIDE ALL NECESSARY 1 JB $___________ $_________
LABOR, MATERIALS, AND EQUIPMENT
NECESSARY FOR REPLACEMENT
SWITCHGEAR IN EXISTING BUILDING 216
AS SHOWN ON CONTRACT DOCUMENTS.
(SEE GENERAL REQUIREMENT 1.3 STATEMENT
OF BID ITEMS, PARAGRAPH A, BASE BID
0022 AND ADD TO INCLUDE ADD ALTERNATE #1: 1 JB $___________ $_________
PROVIDE ALL NECESSARY LABOR, MATERIALS,
AND EQUIPMENT NECESSARY FOR REPLACEMENT
OF THREE (3) TRANSFORMERS.
(SEE GENERAL REQUIREMENT 1.3 STATEMENT
OF BID ITEMS, PARAGRAPH B, BASE BID,
ITEMS ADD ALTERNATE #1)
0023 AND ADD TO INCLUDE ADD ALTERNATE #2: 1 JB $__________ $_________
REMOVE EXISTING OVERHEAD CONDUCTORS, ELEC.
POLES AND INTERCONNECTING WIRE. POLE FOUNDATIONS
REMOVED TO 3’-0” BELOW EXISTING GROUND LEVEL.
(SEE GENERAL REQUIREMENT 1.3 STATEMENT
OF BID ITEMS, PARAGRAPH B, BASE BID,
ITEMS ADD ALTERNATE #2)
0024 AND ADD TO INCLUDE ADD ALTERNATE #3: 1 JB $__________ $_________
REMOVE EXISTING CAPACITOR BANK, REMOVE EXISTING
MAIN SWITCHGEAR, BLDG. 133 AND BLDG. 133 FOUNDATION
DOWN TO 3’-0” BELOW EXISTING GROUND ELEVATION.
(SEE GENERAL REQUIREMENT 1.3 STATEMENT
OF BID ITEMS, PARAGRAPH B, BASE BID,
ITEMS ADD ALTERNATE #3)
0025 AND ADD TO INCLUDE ADD ALTERNATE #4: 1 JB $__________ $_________
REMOVE THREE COOLING TOWERS AND ASSOCIATED
CONCRETE AND PIPING TO B216.
(SEE GENERAL REQUIREMENT 1.3 STATEMENT
OF BID ITEMS, PARAGRAPH B, BASE BID,
ITEMS ADD ALTERNATE #4)
0026 AND ADD TO INCLUDE ADD ALTERNATE #5: 1 JB $__________ $_________
CAP AND REMOVE ALL CHILLED WATER PIPING,
PUMPS, SUPPORTS, AND HANGERS IN B-216.
(SEE GENERAL REQUIREMENT 1.3 STATEMENT
OF BID ITEMS, PARAGRAPH B, BASE BID,
ITEMS ADD ALTERNATE #5)
0027 COST OF PERFORMANCE AND 1 EA $___________ $_________
PAYMENT BONDS
**TOTAL PROJECT DURATION for both the Base Bid and Bid Alterante #1: 365 Calendar days from issuance of the Notice to Proceed to complete the project work.
Base Bid + Bid Alternate #1 + Bid Alternate #2 + Bid Alternate #3 + Bid Alternate #4 + Bid Alternate #5 TOTAL (Line items 0021, 0022, 0023, 0024, 0025, 0026 & 0027) $____________
File details come from the government source that posted it. Updated .