36C25718R0612-0003000.docx

DOCX document 28 KB Posted

Attached to
VISN17 Equipment Site Prep IDIQ Federal contract opportunity
Solicitation number
36C25718R0612
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 17

About this file

36C25718R0612 0003 36C25718R0612 0003.docx

View the file

Other files for this federal contract opportunity

Other files attached to VISN17 Equipment Site Prep IDIQ, newest first.
File Type Posted
36C25718R0612-0005000.docx DOCX document
36C25718R0612-0004000.docx DOCX document
36C25718R0612-0003001.pdf PDF
36C25718R0612-0002000.docx DOCX document
36C25718R0612-0002001.pdf PDF
36C25718R0612-0001000.docx DOCX document
36C25718R0612-001.docx DOCX document
36C25718R0612-002.pdf PDF
36C25718R0612-000.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE

7. ADMINISTERED BY

2.

AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER

3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE

OF PAGES

10A. MODIFICATION OF

CONTRACT/ORDER NUMBER

10B. DATED

BPA NO.

1. CONTRACT ID CODE

FACILITY CODE

CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV.

11/2016) is required to sign this document and return ___________ copies to the issuing office.

is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO:

Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITE M 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES

SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR

43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes r eference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS

ENTERED INTO

PURSUANT TO AUTHORITY OF:

D. OTHER

BY

Contractor

16C. DATE SIGNED

14.

DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME

AND TITLE OF SIGNER

16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30

PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS

OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer) 10-17-2018

NONE

36C257 Department of Veterans Affairs Network Contracting Office 17 2002 Scott Blvd.

Temple TX 76504 Department of Veterans Affairs Network Contracting Office 17 2002 Scott Blvd.

Temple TX 76504 To all Offerors/Bidders

36C25718R0612 09-06-2018

X X X

11/01/2018 @ 1:00PM CST

X The purpose of this amendment is to provide awnsers to questions received. See continuation page(s) and conformed solicitation (attached)

Additionally, this amendment extends proposal due date to 11/01/2018 @1:00PM CST.

All other terms and conditions remain unchanged.

Lindsey Hooge Contracting Officer

VA-VHA-SAOW-2016-50A02FFF

CONTINUATION PAGE

VISN17 Equipment Site Preparation IDIQ Questions and VA Response IDIQ Questions Q1: For Item “3. Factor 3: PRICE EVALUATION APPROACH Fixed Price: Fixed Price: The Government will evaluate offers by adding the total of all line item prices for the “seed project”. The Total Evaluated Price will be that sum.”

We have not found a Schedule B or any other document that tells us how to list the “total of all line items prices”. Does the VA intend to publish a pricing document?

A1: SEED PROJECT SCHEDULE: Changes in Blue per Amendment 0003 (See conformed solicitation)

CLIN
Unit
Unit Price
Qty
Description
Item Net Cost
0001
JB
1
Contractor shall provide all equipment, labor, material, transportation and supervision to for Site Prep for Radiology Room 257 in accordance with the SOW
0002
JB
1
Payment and Performance Bonds

Q2: For Item “PERSONNEL REQUIREMENTS: B. Primary Personnel” on page 9 of 89.

This paragraph lists Appendix I and Appendix 2. We cannot find any items listed as Appendix 1 or Appendix 2 in the solicitation. Please provide clarification.

A2: “PERSONNEL REQUIREMENTS: B. Primary Personnel” on page 9 of 89, is hereby changed entirely from:

PERSONNEL REQUIREMENTS:

A. Contractor Program Manager: The Contractor will designate an individual to serve as the Program Manager between the Contractor’s organization and the Government. This individual must have an overall knowledge of facility design, construction and administration. The Program Manager will have the authority to negotiate and accept Task Orders on the Contractors behalf and will have a technical and administrative knowledge of Task Orders in progress and completed.

B. Primary Personnel: The personnel identified in Appendix I of this Article are the primary individuals to perform key functions under the contract. Any primary personnel, other than those listed, shall meet the requirements listed in Appendix II of this Article, and shall be approved by the Contracting Officer.

To: Changes in Blue per Amendment 0003 (See conformed solicitation)

PERSONNEL REQUIREMENTS:

A. Contractor Program Manager: The Contractor will designate an individual to serve as the Program Manager between the Contractor’s organization and the Government. This individual must have an overall knowledge of facility design, construction and administration. The Program Manager will have the authority to negotiate and accept Task Orders on the Contractors behalf and will have a technical and administrative knowledge of Task Orders in progress and completed.

B. Technical Services: The contractor will have as part of their team technical design professionals to provide additional design and infrastructure assessment services that are required by the stakeholders or are a result of existing conditions.

Q3: In regard to Pricing evaluation, will pricing realism be evaluated by the Government?

A3: No.

Q4: What is the wage determination for this project, there is one shown towards the end of the RFQ but it says to verify with the CO?

A4: Clarification, wage determination included in the solicitation is applicable to the Seed Project Only, each Task Order issued against the IDIQ will include the applicable most recent wage determination for the area in which the work is to be completed.

Q5: Does the Government want an entire SF 330 prepared and embedded within the proposal? Or is the intent to receive resumes in the format of Section E in the SF330?

A5: Resumes shall be in the format of Section E of the SF330, an actual SF330 is not required.

Q6: After reviewing the associated documents, we have not identified an Appendix I or II. Can this be provided to ensure our proposed personnel meet requirements?

A6: See answer above for Q2.

VISN17 Equipment Site Preparation IDIQ Questions and VA Response Seed Project Questions Q1. Are the medical gas outlets on the plan north wall to remain or be relocated?

A1. Med gas will remain.

Q2. The emergency receptacles are circuited to panel EQ2E. Is this an equipment branch panel? If so is the intent to leave the receptacles circuited as they are or to re-circuit them to a critical branch panel. If the intent is to re-circuit them to a critical branch panel, where is this panel located and does it have space / capacity to serve the receptacles?

A2. Panel EQ2E is an equipment branch fed from electrical closet rm. 262. Receptacles will remain as they are.

Q3. The lighting is circuited to panel EQ2E. Is this an equipment branch panel? If so is the intent to leave the lighting circuited as it is or to re-circuit to a critical branch panel. If the intent is to re-circuit to a critical branch panel, where is this panel located and does it have space / capacity to serve the receptacles?

A3. Same as above.

Q4. There is no normal lighting in the room. Is the intent to leave all lighting on emergency power or to circuit a portion of the lights to normal power? If normal power, where is the normal lighting panel serving this area and does it have space / capacity to serve the proposed lights?

A4. Normal power is located in the same electrical closet.

Q5. What size is the existing circuit breaker referenced in item #39 on page 36 to be re-used for the new imaging equipment?

A5. 4/0 wire, 225 amp, 80 amp trip unit.

Q6. Item #37 on page 36 requires installing supplemental duct work within the site if necessary. There is no duct work on the site and heating and cooling are provided by two radiators and a single exposed fan coil unit that will not support duct work. Please clarify.

A6. FCU will service this room. No ductwork will be required.

Q7. Lighting:

Are the existing lighting fixtures to remain?

Are they to be removed and reinstalled after equipment is replaced or just remain?

Are there any new lighting fixtures to be added?

A7: Please reference items 40 & 41 in the SOW.

Q8: Power 240/120v single phase 3-wire:

The existing sub panel in room 257 is a 100 amp single phase 240 volt panel and is full.

Is this existing sub panel to remain and be re-used? Yes Are the existing circuits in the sub panel to be demolished? No Are the existing circuit breakers in the sub panel to be re-used? Yes A8: It is on the Equipment Branch. This also feeds power to rm. 256 outlets.

Q9: Power 480/277v 3-phase 4-wire:

In room 257, there are 2 enclosed 480v 3-phase circuit breakers, one is marked “spare” and the other is marked Siemens Generator. Are either or both of these going to become available after demolition? No. New panel and breakers to be used.

What is the trip rating or circuit rating of these two breakers/circuits? Use new breakers.

Will we be able to re-use or utilize these existing enclosed breakers and their associated circuits? No A9: New panel and breakers to be used.

Q10: HVAC:

Are the existing HVAC circuits to remain?

Are there going to be any new HVAC circuits required? If so, what are the new HVAC phase, voltage and amperage requirements?

A10:

Are the existing HVAC circuits to remain? Yes Are there going to be any new HVAC circuits required? If so, what are the new HVAC phase, voltage and amperage requirements? No

Q11: The prints/SOW shows to remove the strut system, lights, ceiling grid, VAV box and all ductwork and save for reinstallation. Our question is - why? The modifications required do not necessitate that work to be done.

A11: If the modifications do not require removal of items, ie., fan coil unit, structural struts, etc., we agree they should be left in place. The SOW spells out new items to be installed.

See attached document: 36C25718R0612 - Conformed Solicitation (Amendment 0003).