This is a Combined Synopsis/Solicitation and Request for Quotation (RFQ) for painting services at the Southeast Louisiana Veterans Healthcare System (SLVHCS) located at 2400 Canal Street, New Orleans, Louisiana 70119. The Department of Veterans Affairs, Overton Brooks VA Medical Center (contracting office in Shreveport, LA 71101) is soliciting competitive quotes for touch-ups and minor wall repairs in patient wards during a period when the ward is unoccupied. The work scope includes surface preparation, minor wall repairs, painting (full-wall coverage where any touch-up is needed), cleanup, and removal/reinstallation of allowable wall items. The estimated labor requirement is up to 80 hours, with a maximum of three personnel onsite at any time, to be completed approximately 40 calendar days after award. Work hours are 7:00 AM–3:30 PM, Monday through Friday, excluding federal holidays.
This solicitation is a 100% Service-Disabled Veteran-Owned Small Business (SDVOSB) set-aside under NAICS Code 238320 (Painting and Wall Covering Contractors). All offerors must be registered and certified in SAM at the time of solicitation close and award. Quotes are due electronically to Contracting Officer Tiffany Conner at tiffany.conner@va.gov by Friday, June 30, 2026, at 10:00 AM Central Standard Time. Questions must be submitted via email no later than June 24, 2026, at 11:00 AM CST. The contract includes three line items: (1) labor up to 80 hours excluding lunch; (2) contractor-furnished materials, tools, and PPE; and (3) project management/supervision. Painters must have a minimum of five years of professional painting experience in healthcare environments, complete OSHA 10-hour construction safety training, and key personnel must demonstrate successful completion of at least three similar projects within the past three years. The contractor must submit a Quality Control Program within 14 calendar days of award and perform a minimum of three quality-control walkthroughs during the period of performance. Invoices must be submitted electronically upon completion and acceptance of services. Wage Determination 2015-5189 Rev 33 applies to this contract.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C25626Q0912 0003_1.docx | DOCX document | |
| 36C25626Q0912 0001_1.docx | DOCX document | |
| WD 2026.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
36C25626Q0912
| SUBJECT* |
| 629-26-3-639-0654 PAINTING SERVICES INPATIENT WARD (VA-26-00070928) 36C256-26-AP-3707 36C256-26-AP-3707 |
GENERAL INFORMATION
| CONTRACTING OFFICE’S ZIP CODE* |
| 71101 |
| SOLICITATION NUMBER* |
| 36C25626Q0912 |
| RESPONSE DATE/TIME/ZONE |
| 06-12-2026 10:00 CENTRAL TIME, CHICAGO, USA |
| ARCHIVE |
| 15 DAYS AFTER THE RESPONSE DATE |
| RECOVERY ACT FUNDS |
| N |
| SET-ASIDE |
| SDVOSBC |
| PRODUCT SERVICE CODE* |
| Z1FZ |
| NAICS CODE* |
| 238320 |
CONTRACTING OFFICE ADDRESS
Department of Veterans Affairs Overton Brooks VA Medical Center (90C) 510 East Stoner Avenue Shreveport LA 71101
POINT OF CONTACT*
Contracting Officer Tiffany Conner tiffany.conner@va.gov
(318) 990-4064
PLACE OF PERFORMANCE
| ADDRESS |
| Southeast Louisiana Veterans Healthcare System |
2400 Canal St.
New Orleans LA
| POSTAL CODE |
| 70119 |
| COUNTRY |
| US |
ADDITIONAL INFORMATION
AGENCY’S URL
URL DESCRIPTION
AGENCY CONTACT’S EMAIL ADDRESS
EMAIL DESCRIPTION
DESCRIPTION
This is a COMBINED SYNOPSIS/SOLICITATION for commercial items prepared in accordance with format in Subpart 12.6- Streamline Procedures for Evaluation and Solicitation for Commercial Item. This solicitation is issued under authority of FAR 13.5, Simplified Procedures for Certain Commercial Items, and the conduct of the procurement will be in accordance with FAR Parts 12 and 13 or some combination thereof.
The solicitation number is 36C25626Q0912_1 and is issued as a Request for Quotation (RFQ).
The proposed contract action is for Painting Services for Inpatient Ward for Southeast Louisiana Veterans Healthcare System located at 2400 Canal Street, New Orleans LA for which the Government intends to solicit competitive quotes. Interested persons may submit quotes, and all eligible quotes must be received prior to the response date listed on Contract Opportunities to be considered by the Government. This solicitation is 100% SDVOSB set-aside.
Applicable NAICS: 238320 Painting and Wall Covering Contractors
This solicitation document and incorporated provisions and clauses are those in effect through Federal Acquisition Circular FAC 2026-01 (eff.03/13/2026). Only emailed requests received directly from the requester will be accepted.
RESPONSES ARE DUE Friday, June 30, 2026, by 10:00 AM Central Standard Time (CST). Quotes are due electronically to primary tiffany.conner@va.gov no later than the response date listed on Contract Opportunities. Only electronic quotes will be considered.
Phone calls will not be accepted, all questions and or concerns after site visit must be submitted via email to tiffany.conner@va.gov NLT 11:00 AM Central Standard Time (CST) on June 24, 2026.
Point of contact for this solicitation is tiffany.conner@va.gov
All Inquires must be submitted electronically.
Combined Synopsis/Solicitation Notice Combined Synopsis/Solicitation Notice
| *= Required Field |
| Combined Synopsis/Solicitation Notice |
Combined Synopsis/Solicitation Notice
PAGE 1 OF
1. REQUISITION NO.
2. CONTRACT NO.
3. AWARD/EFFECTIVE DATE
4. ORDER NO.
5. SOLICITATION NUMBER
6. SOLICITATION ISSUE DATE
a. NAME
b. TELEPHONE NO. (No Collect Calls)
8. OFFER DUE DATE/LOCAL
TIME
9. ISSUED BY
CODE
10. THIS ACQUISITION IS
UNRESTRICTED OR
SET ASIDE:
% FOR:
SMALL BUSINESS
HUBZONE SMALL
BUSINESS
SERVICE-DISABLED
VETERAN-OWNED
SMALL BUSINESS
WOMEN-OWNED SMALL BUSINESS
(WOSB) ELIGIBLE UNDER THE WOMEN-OWNED
SMALL BUSINESS PROGRAM
EDWOSB
8(A)
NAICS:
SIZE STANDARD:
11. DELIVERY FOR FOB DESTINA-
TION UNLESS BLOCK IS
MARKED
SEE SCHEDULE
12. DISCOUNT TERMS
13a. THIS CONTRACT IS A
RATED ORDER UNDER
DPAS (15 CFR 700)
13b. RATING
14. METHOD OF SOLICITATION
RFQ
IFB
RFP
15. DELIVER TO
CODE
16. ADMINISTERED BY
CODE
17a. CONTRACTOR/OFFEROR
CODE
FACILITY CODE
18a. PAYMENT WILL BE MADE BY
CODE
TELEPHONE NO.
UEI:
EFT:
PHONE:
FAX:
17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT SUCH ADDRESS IN OFFER 18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a UNLESS BLOCK BELOW IS CHECKED
SEE ADDENDUM
19.
20.
21.
22.
23.
24.
ITEM NO.
SCHEDULE OF SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
(Use Reverse and/or Attach Additional Sheets as Necessary)
25. ACCOUNTING AND APPROPRIATION DATA
26. TOTAL AWARD AMOUNT (For Govt. Use Only) 27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1, 52.212-4. FAR 52.212-3 AND 52.212-5 ARE ATTACHED. ADDENDA
ARE
ARE NOT ATTACHED.
27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA
ARE
ARE NOT ATTACHED
28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN _______________
29. AWARD OF CONTRACT: REF. ___________________________________ OFFER
COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND
DATED ________________________________. YOUR OFFER ON SOLICITATION
DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY
(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE
ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED
SET FORTH HEREIN IS ACCEPTED AS TO ITEMS:
30a. SIGNATURE OF OFFEROR/CONTRACTOR 31a. UNITED STATES OF AMERICA (SIGNATURE OF CONTRACTING OFFICER) 30b. NAME AND TITLE OF SIGNER (TYPE OR PRINT) 30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER (TYPE OR PRINT) 31c. DATE SIGNED
AUTHORIZED FOR LOCAL REPRODUCTION
(REV. NOV 2021)
PREVIOUS EDITION IS NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.212
7. FOR SOLICITATION
INFORMATION CALL:
STANDARD FORM 1449
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES
OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, & 30
629-26-3-639-0654 36C25626Q0912 06-15-2026 Tiffany Conner n/a 06-30-2026 10am
CDT
Department of Veterans Affairs Network Contracting Office 16 510 East Stoner Ave.
Shreveport LA 71101 X X 238320 $19 Million N/A X Department of Veterans Affairs The Southeast Louisiana Veterans Healthcare System (SLVHCS) 2400 Canal Street New Orleans LA 70119 Department of Veterans Affairs Network Contracting Office 16 510 East Stoner Ave.
Shreveport LA 71101
FSC e-Invoice Payment http://www.fsc.va.gov/fsc/einvoice.asp Invoice Setup Information 1-877-489-6135 Invoice must be submitted electronically
See CONTINUATION Page The Southeast Louisiana Veterans Healthcare System (SLVHCS) requires painting services within the inpatient ward.
All responses are due by 06/30/2026 at 10:00am CST.
Any questions are to be submitted via email to Tiffany Conne r tiffany.conner@va.gov by 06/24/2026 at 11:00am CST.
This solicitation is 100% Set-Aside for SDVOSB's.
All Offerors must be registered/certified SAM at the time of solicitation close and award.
All work is to be performed at:
2400 Canal Street, New Orleans, LA, 70119.
Wage Determination 2015-5189 Rev 33 Applies See CONTINUATION Page 629-3660162-639-851100-2543 0100501X8 X X Contracting Officer Page 1 of Table of Contents
| SECTION A | 4 |
| A.1 SF 1449 SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES | 4 |
| SECTION B - CONTINUATION OF SF 1449 BLOCKS | 7 |
| B.1 CONTRACT ADMINISTRATION DATA | 7 |
| B.2 PRICE/COST SCHEDULE | 18 |
| ITEM INFORMATION | 18 |
| SECTION C - CONTRACT CLAUSES | 19 |
| C.1 52.212-4 CONTRACT TERMS AND CONDITIONS—COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES (NOV 2023) | 19 |
| C.2 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998) | 25 |
| C.3 52.209-10 PROHIBITION ON CONTRACTING WITH INVERTED DOMESTIC CORPORATIONS (NOV 2015) | 25 |
| C.4 52.222-42 STATEMENT OF EQUIVALENT RATES FOR FEDERAL HIRES (MAY 2014) | 26 |
| C.5 52.222-50 COMBATING TRAFFICKING IN PERSONS (NOV 2025) (DEVIATION) | 26 |
| C.6 52.222-90 ADDRESSING DEI DISCRIMINATION BY FEDERAL CONTRACTORS (DEVIATION APR 2026) | 34 |
| C.7 52.226-8 ENCOURAGING CONTRACTOR POLICIES TO BAN TEXT MESSAGING WHILE DRIVING (MAY 2024) | 35 |
| C.8 52.232-33 PAYMENT BY ELECTRONIC FUNDS TRANSFER—SYSTEM FOR AWARD MANAGEMENT (OCT 2018) | 36 |
| C.9 52.232-40 PROVIDING ACCELERATED PAYMENTS TO SMALL BUSINESS SUBCONTRACTORS (MAR 2023) | 38 |
| C.10 52.233-3 PROTEST AFTER AWARD (AUG 1996) ALTERNATE I (JUN 1985) | 38 |
| C.11 52.233-4 APPLICABLE LAW FOR BREACH OF CONTRACT CLAIM (OCT 2004) | 39 |
| C.12 52.240-91 SECURITY PROHIBITIONS AND EXCLUSIONS (NOV 2025) (DEVIATION) | 39 |
| C.13 VAAR 852.203-70 COMMERCIAL ADVERTISING (MAY 2018) | 49 |
| C.14 VAAR 852.219-74 VA NOTICE OF TOTAL SET-ASIDE FOR CERTIFIED VETERAN-OWNED SMALL BUSINESSES (JAN 2023) (DEVIATION) | 49 |
| C.15 VAAR 852.219-75 VA NOTICE OF LIMITATIONS ON SUBCONTRACTING—CERTIFICATE OF COMPLIANCE FOR SERVICES AND CONSTRUCTION (JAN 2023) (DEVIATION) | 52 |
| C.16 VAAR 852.242-71 ADMINISTRATIVE CONTRACTING OFFICER (OCT 2020) | 54 |
| C.17 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV 2018) | 54 |
| SECTION D - CONTRACT DOCUMENTS, EXHIBITS, OR ATTACHMENTS | 56 |
| SECTION E - SOLICITATION PROVISIONS | 57 |
| E.1 52.212-1 INSTRUCTIONS TO OFFERORS—COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES (SEP 2023) | 57 |
| ADDENDUM to FAR 52.212-1 INSTRUCTIONS TO OFFERORS—COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES | 61 |
| E.2 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998) | 63 |
| E.3 52.240-90 SECURITY PROHIBITIONS AND EXCLUSIONS REPRESENTATIONS AND CERTIFICATIONS (NOV 2025) (DEVIATION) | 63 |
SECTION B - CONTINUATION OF SF 1449 BLOCKS
B.1 CONTRACT ADMINISTRATION DATA
1. Contract Administration: All contract administration matters will be handled by the following individuals:
a. CONTRACTOR:
b. GOVERNMENT: Contracting Officer 36C256 Department of Veterans Affairs Network Contracting Office 16 510 East Stoner Ave.
Shreveport LA 71101
2. CONTRACTOR REMITTANCE ADDRESS: All payments by the Government to the contractor will be made in accordance with:
| [X] |
| 52.232-33, Payment by Electronic Funds Transfer—System For Award Management, or |
| [] |
| 52.232-36, Payment by Third Party |
3. INVOICES: Invoices shall be submitted in arrears:
| a. Quarterly | [] |
| b. Semi-Annually | [] |
| c. Other | [X] Upon Completion and Acceptance of Services |
4. GOVERNMENT INVOICE ADDRESS: All Invoices from the contractor shall be submitted electronically in accordance with VAAR Clause 852.232-72 Electronic Submission of Payment Requests.
ACKNOWLEDGMENT OF AMENDMENTS: The offeror acknowledges receipt of amendments to the Solicitation numbered and dated as follows:
| AMENDMENT NO |
| DATE |
PERFORMANCE WORK STATEMENT (PWS)
PAINTING SERVICES – INPATIENT WARDS
SOUTHEAST LOUISIANA VETERANS’ HEALTHCARE SYSTEM (SLVHCS)
2400 CANAL STREET, NEW ORLEANS, LA 70119
PART 1 – GENERAL INFORMATION
1.1 General
SLVHCS requires contracted painting services to complete touch-ups and minor wall repairs in the Patient Wards. The wards is unoccupied during the period of performance, allowing work to be completed without impacting patient care or operations.
1.2 Description of Services
The Contractor shall furnish all labor, supervision, equipment, tools, and non-paint materials required to perform surface preparation, minor wall repairs, and painting (including full-wall touch-ups where any touch-up is needed), cleanup, restoration of areas, and removal/reinstallation of allowable wall items in accordance with this PWS.
1.3 Background
The healthcare system currently has only one available in-house painter; a second painter is out on medical leave. Due to system-wide workload demands, the ward cannot be refreshed in the timeframe needed using internal resources.
1.4 Summary of Work
Scope includes surface repairs, preparation, and painting across patient rooms, corridors, doorframes, and support areas of the Inpatient Building Ward. Because the ward is vacant, the work can be performed efficiently and safely. Estimated labor: up to 80 hours.
1.5 Justification
Completing aesthetic work while the ward is vacant prevents future disruption to patient care, supports Environment of Care (EOC) expectations, and ensures readiness.
1.6 Period of Performance (POP)
Work must be completed approximately thirty (40) calendar days after award.
1.7 Scope and Constraints
• Labor Hours: Up to 80 hours, excluding lunch breaks, with no more than three (3) personnel onsite at any time. Labor hours are at standard rates.
• Surfaces to Paint: Sheet rock (gypsum board) walls and metal framing components (including metal door frames) only.
• Minor Wall Repair: Patch/fill/sand and prepare substrates; apply two (2) coats of paint on all repaired areas.
• Full-Wall Painting: Where any touch-up is performed, paint the entire wall corner-to-corner/edge-to-edge (spot-patching alone is not permitted).
• Allowable Removals: Remove and reinstall framed artwork or decorative items; do not remove TV monitors or medical equipment monitors.
• Protection: Prevent any visible paint splatter on headwalls, outlets, rails, switches, and wall-mounted devices; use masking and coverings to protect adjacent finishes.
• Pre-Work Space Readiness: Confirm the condition/readiness of each space before work begins daily; report deficiencies to the COR and commence work only after COR acknowledgement.
• Daily Check-In/Out: All staff shall check in and out each day with the COR or designee.
• QC Walkthroughs: Perform a minimum of three (3) quality-control walkthroughs during the entire period of performance; document and provide upon request.
• Parking: Onsite parking is permitted per VA Police instructions.
• Rework: Any deficient work shall be corrected at no cost to the Government.
1.5 General Information
1.5.1 Quality Control
The Contractor shall develop and maintain an effective Quality Control Program (QCP) to ensure services conform to this PWS, including procedures to identify, prevent, and ensure non-recurrence of defective services. The QCP shall be delivered to the COR within 14 calendar days of contract award. After acceptance of the QCP, any proposed change to the QC system requires written acceptance by the Contracting Officer (CO/KO).
1.5.2 Quality Assurance
The Government will inspect and evaluate Contractor performance to ensure services meet requirements. The COR will conduct surveillance via direct observation, weekly or bi-weekly inspections, and by investigating customer complaints.
1.5.3 Hours of Operation
Work shall be performed 7:00 AM–3:30 PM, Monday–Friday, excluding Federal holidays or facility closures due to local or national emergencies, administrative closings, or similar Government-directed closings. The Contractor shall maintain an adequate workforce for uninterrupted performance and check in with the COR (or designated lead) prior to starting work each day.
1.5.4 Place of Performance
2400 Canal Street, New Orleans, LA 70119.
1.5.5 Security Requirements
The onsite lead must have or obtain a non-PIV ID card; renewal is annual. All Contractor personnel must receive visitor badges from VA Police Service to enter the building.
1.5.5.1 Physical Security
Safeguard all Government information and property provided for Contractor use; secure facilities at the close of each work period.
1.5.5.2 Key Control
Establish and implement methods to ensure all Government-issued keys/key cards are not lost or used by unauthorized persons; no duplication permitted. Include key control procedures in the QCP, including turn-in of keys by personnel who no longer require access and immediate reporting of lost or duplicate keys/key cards to the CO.
1.5.5.2.1 Lost/Duplicated Keys
When non-master keys are lost/duplicated, the Contractor shall, upon CO notification, re-key or replace affected locks; the Government may perform the work and deduct cost from payment due the Contractor. If a master key is lost/duplicated, the Government will replace all locks and keys for that system and deduct the total cost from payment due the Contractor.
1.5.5.2.2 Key Usage Prohibition
Prohibit use of Government-issued keys/key cards by persons other than Contractor employees; prohibit opening locked areas for non-authorized persons unless approved by the CO.
1.5.5.3 Lock Combinations
Ensure lock combinations are not revealed to unauthorized persons; change combinations when personnel no longer require access; include these procedures in the QCP.
1.5.6 Special Qualifications (Painting)
• Painters shall have a minimum of five (5) years of professional painting experience, including wall repair, drywall patching, and finish applications in healthcare environments.
• All onsite personnel shall have completed OSHA 10-hour construction safety training.
• Qualification of Painters (Journeyman): Use only qualified journeyman painters for mixing and application on exposed surfaces. Submit evidence that key personnel have successfully performed surface preparation and coating application on at least three (3) similar projects within the past three (3) years (résumés, project descriptions, references, completion documents).
1.5.7 Post Award Conference / Periodic Progress Meetings
Attend post award conference(s) convened by the Contracting Officer in accordance with FAR Subpart 42.5; periodic meetings may be held to review performance; there is no additional cost to the Government.
1.5.8 Key Personnel
Provide an onsite lead and an alternate designated in writing to the CO; both shall have full authority to act for the Contractor on daily operations and be available during onsite work hours.
1.5.9 Identification of Contractor Employees
Contractor personnel shall identify themselves as contractors in meetings, when answering Government telephones, and in documents/reports; ensure documents are suitably marked to disclose contractor participation.
1.5.10 Contractor Travel
Not Applicable.
1.5.11 Organizational Conflict of Interest (OCI)
Contractor personnel may have access to proprietary/source selection information; the Contractor shall notify the CO of any actual/potential OCI and promptly submit a mitigation plan. If the CO determines an OCI cannot be satisfactorily avoided or mitigated, the CO may implement remedies, including prohibiting participation in subsequent related requirements.
PART 2 – DEFINITIONS & ACRONYMS
Definitions
• Contractor: Supplier/vendor awarded a contract to provide specific supplies/services to the Government.
• Contracting Officer (CO): Person with authority to enter, administer, or terminate contracts and make related determinations on behalf of the Government; the only individual who can legally bind the Government.
• Contracting Officer’s Representative (COR): Government employee appointed by the CO to administer the contract; may provide technical direction within scope; cannot change contract terms or funding.
• Defective Service: Service output that does not meet the performance standard of the PWS.
• Deliverable: Any item that can be physically delivered, including reports or meeting minutes.
• Key Personnel: Contractor personnel designated as essential for contract performance; may be required under the PWS.
• Physical Security: Actions that prevent loss or damage of Government property.
• Quality Assurance (QA): Government procedures verifying services meet acceptable standards.
• Quality Assurance Surveillance Plan (QASP): Written plan specifying surveillance methodology for Contractor performance.
• Quality Control (QC): Measures taken by the Contractor to assure the quality of products/services meets contract requirements.
• Subcontractor: Party entering into a contract with a prime Contractor; Government does not have privity of contract with the subcontractor.
• Workday: Number of hours per day the Contractor provides services under the contract.
• Work Week: Monday through Friday, unless specified otherwise.
Acronyms CFR, CONUS, COR, COTS, FAR, HIPAA, KO, OCI, ODC, PIPO, POC, PRS, PWS, QA, QAP, QASP, QC, QCP, TE.
PART 3 – GOVERNMENT-FURNISHED PROPERTY & SERVICES
• Services: Government will coordinate access to ensure patient care is not impacted.
• Utilities: Government provides available utilities; Contractor shall instruct employees in conservation and avoid waste.
• Materials: Paint (color, type, sheen) is Government-furnished; Contractor shall ensure proper mixing and color matching to existing finishes.
• Equipment: Government will not provide Contractor tools/equipment.
PART 4 – CONTRACTOR-FURNISHED ITEMS & RESPONSIBILITIES
• General: Contractor shall furnish all supplies, equipment, ladders, PPE, protective coverings, and consumables required to perform the work that are not Government-furnished.
• Identification/Access: Contractor personnel shall obtain visitor badges daily and comply with VA Police procedures.
• Check-In/Out: Contractor personnel must check in and out daily with the COR or designee.
• QC Walkthroughs: Perform ≥ 3 QC walkthroughs during the PoP; document and submit upon request.
• Rework/Damage: Correct defective work at no cost; Contractor is liable for any Government property damage and shall restore conditions to match existing.
• Parking: Onsite parking as permitted by VA Police.
PART 5 – SPECIFIC TASKS / EXECUTION REQUIREMENTS
Job Conditions A. Safety
• Comply with safety regulations and manufacturer’s instructions for storage, handling, and application.
• Protect personnel and property from hazards (falls, injuries, toxic fumes, fire, explosion, etc.).
• Place soiled rags/waste in approved metal containers and remove offsite daily.
B. Atmospheric & Surface Conditions
• Do not apply coatings when:
– Air/substrate is < 3°C (5°F) above dew point.
– Air/substrate is < 10°C (50°F) or > 35°C (95°F) unless pre-approved in writing by the COR and manufacturer; never exceed manufacturer recommendations.
– Relative humidity > 85%, or surfaces are damp/wet unless permitted by manufacturer instructions.
• Maintain interior temperatures per manufacturer requirements until coatings dry to a hard, durable finish.
3.2 Inspection
• Examine areas and conditions where painting/finishing will be applied; do not proceed until unsatisfactory conditions are corrected to permit proper installation; report issues to the COR prior to beginning work each day.
3.3 General Workmanship Requirements
• Application shall be by brush or roller; spray only with written COR approval.
• Furnish and maintain a painting schedule indicating timing of coats for each area/surface.
• Protect work and adjacent materials with suitable coverings; remove paint spots and debris; leave areas clean.
• Remove/protect hardware, accessories, device plates, lighting fixtures, and factory-finished items or provide in-place protection; reinstall with skilled trades after paint cures.
• For walls adjacent to electrical panel boxes, remove covers/doors, paint separately, and reinstall after fully dry.
• Apply only under adequate illumination; ensure smooth flow with no runs, sags, holidays, brush marks, air bubbles, or excessive roller stipple.
• Apply at coverage to fully hide substrate; if show-through occurs, apply additional coats at no added cost until uniform finish is achieved.
• Allow each coat to dry per manufacturer instructions before applying the next.
• Touch up suction/hot spots in plaster prior to second coat.
• Do not paint behind frameless mirrors adhered with mastic.
3.4 Surface Preparation
A. General
• Contractor is responsible for finished appearance; thoroughly clean, sand, de-gloss, patch, smooth, and touch up prime coats applied under other sections; broom clean spaces prior to painting; ensure surfaces are dry, clean, and smooth.
• See other sections for specified surface conditions and prime coats.
• Perform prep/cleaning strictly per manufacturer instructions and as specified herein for each substrate.
• Clean surfaces with materials/methods compatible with substrate/finish; remove all cleaning residues; do not use solvents, acid, or steam on concrete/masonry; schedule cleaning to prevent dust/contaminants from landing on wet coatings.
E. Gypsum Plaster and Gypsum Board
• Remove efflorescence, loose/chalking plaster, and disbonded finishing materials.
• Remove dust, dirt, and contamination that can deter paint adhesion.
• Fill holes/cracks/depressions with CID-A-A-1272A filler; finish flush with adjacent surface and match texture; patch holes > 25 mm (1 inch) per applicable plaster/gypsum board repair standards.
3.5 Paint Preparation
• Thoroughly mix materials for uniform color and pigment dispersion.
• Do not thin unless necessary for application and permitted by manufacturer; use only manufacturer-specified thinners/quantities.
• Remove paint skins; strain through a commercial paint strainer.
• Mix two-component/two-part coatings precisely per manufacturer instructions.
• Use manufacturer-approved tinting pigments for exact color match.
3.6 Application
• Beginning surface preparation or painting constitutes acceptance of substrate conditions.
• Unless otherwise specified, apply three (3) coats: prime, body, finish; when the two coats over primer are the same, the first is the body coat, the second is the finish coat.
• Apply each coat evenly and ensure complete coverage.
• Allow ≥ 48 hours between coats unless manufacturer permits otherwise and COR approves.
• Apply by brush or roller; spray only with written COR approval for new or existing occupied spaces.
– Apply paints specifically required by manufacturer to be sprayed using appropriate equipment.
– Where spraying is approved, mask/enclose areas with airtight barriers (polyethylene) and seal all edges/seams; protect motors, controls, telephone/electrical equipment, sterilizer fronts, and other prefinished items.
• Do not paint operable items (access doors/panels, window sashes, overhead doors) in the closed position (except overhead roll-up doors/shutters).
Refinishing Existing Painted Surfaces
• Clean, patch, and repair existing surfaces per Surface Preparation; no telegraphing of lines, ridges, flakes through new finishes—sand smooth and refinish until acceptable to COR.
• Remove/reinstall items as specified under General Workmanship Requirements.
• Remove incompatible existing finishes or apply separation coats to prevent interaction between non-compatible coatings.
• For patched/replaced areas, apply spot primer and body coats as specified for new work.
• Where surfaces are not scheduled for complete repainting, apply finish coat to the nearest break in plane (corner, reveal, frame).
• In altered existing rooms/areas with stained/natural finished wood, clean and touch up abraded surfaces; apply one (1) coat of MPI 31 (Polyurethane, Moisture-Cured, Clear Gloss) to the entire surface.
• Refinish areas to match adjoining work unless scheduled otherwise.
• Seal knots/pitch streaks with MPI 36 (Knot Sealer) before refinishing.
• Sand/dull glossy surfaces prior to painting.
• Feather-sand existing coatings at transitions so differences are not visible after completion.
PART 6 – QUALITY CONTROL / QUALITY ASSURANCE
Contractor QC
• Maintain the QCP; conduct three (3) QC walkthroughs over the PoP; document inspections and corrective actions; correct deficiencies promptly; provide documentation upon request.
• QCP is due 7 days after award; KO approves changes in writing.
Government QA
• The COR performs inspections/surveillance via direct observation, weekly/bi-weekly inspections, and complaint investigation, ensuring services meet this PWS.
PART 7 – QUALITY ASSURANCE SURVEILLANCE PLAN (QASP)
Surveillance Methods (Narrative)
• Deliverables Review: Verify daily check-in/out logs, QC walkthrough documentation, deficiency correction logs, and closeout records for completeness, accuracy, and timeliness.
• Periodic Site Visits/Inspections: Confirm proper preparation, repairs, paint application (two coats on repaired areas), and protection of fixtures.
• Random Visual Checks/Tests: Verify full coverage, color/sheen match, absence of splatter/defects, and compliance with full-wall painting requirement.
• Staff Feedback Surveys: Collect end-user/staff satisfaction feedback post-completion.
• Reports Review: Review monthly progress reports (if applicable within PoP) and the final completion report for compliance with performance standards and contract requirements.
Performance Requirements Summary (PRS) / QASP Table
| Performance Objective |
| Performance Standard |
| AQL |
| Surveillance Method |
| Incentives / Disincentives |
| Prep, repairs, and painting |
| Per PWS; two coats on repaired areas; no defects/splatter |
| 100% |
| COR inspections; QC records |
| Rework at no cost to Government |
| Daily check‑in/out |
| All personnel check in/out each day |
| 100% |
| COR verification |
| Documented noncompliance; may affect past performance |
| QC walkthroughs |
| ≥ 3 walkthroughs over PoP |
| 100% |
| Review QC docs; COR verify |
| Corrective action request if missed |
| Fixture/equipment protection |
| Zero paint splatter/damage |
| 100% |
| Random inspections |
| Rework/repair at Contractor cost |
PART 8 – DELIVERABLES & SUBMITTALS
• Quality Control Program (QCP): Due to COR within 14 calendar days of award; revisions require KO written acceptance.
• Painting Schedule: Planned dates for prime/body/finish coats by area; maintain current throughout the project.
• Daily Check-In/Out Logs: Personnel roster/time logs.
• QC Walkthrough Records: At least three documented walkthroughs over PoP, with deficiencies and corrective actions.
• Pre-Work Space Readiness Log: Daily confirmation and COR acknowledgement of space readiness.
• Waste Disposal Records: Evidence of daily removal of rags/flammable waste.
• Final Completion Report: Areas completed, materials used, corrective actions, and confirmation of compliance with PWS/QASP.
• Warranty of Workmanship: Duration per CO direction (if applicable).
PART 9 – PLACE OF PERFORMANCE
2B Patient Ward, SLVHCS, 2400 Canal Street, New Orleans, LA 70119.
PART 10 – HOURS OF OPERATION
7:00 AM–3:30 PM, Monday–Friday, excluding Federal holidays or facility closures due to emergencies/administrative directives; adequate workforce must be maintained; daily check-in required with COR before work begins.
CONTRACT LINE ITEM NUMBER (CLIN) SCHEDULE
| CLIN |
| Description |
| Qty |
| Unit |
| 001 |
| Labor – up to 80 hours (NTE), excluding lunch; max 3 workers |
| 80 |
| Hours |
| 002 |
| Contractor‑furnished materials, tools, PPE, consumables |
| 1 |
| Lot |
| 003 |
| Project management / supervision |
| 1 |
| Job |
SIGN-OFF & CLOSEOUT
• Final Walkthrough: Contractor and COR perform joint inspection; deficiencies corrected prior to acceptance.
• Closeout Package: Submit QCP final updates, QC logs, painting schedule (as-built), corrective action records, and final report.
• Acceptance: CO issues final acceptance upon COR recommendation.
B.2 PRICE/COST SCHEDULE
ITEM INFORMATION
| ITEM NUMBER |
| DESCRIPTION OF SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
| 1.00 |
| JB |
| __________________ |
| __________________ |
Employee tools Contract Period: Base POP Begin: 07-01-2026 POP End: 08-10-2026 PRINCIPAL NAICS CODE: 811210 - Electronic and Precision Equipment Repair and Maintenance PRODUCT/SERVICE CODE: Z1EB - Maintenance of Maintenance Buildings LOCAL STOCK NUMBER: Line 1
| 40.00 |
| HR |
| __________________ |
| __________________ |
Project Manager
POP Begin: 07-01-2026 POP End: 08-10-2026 PRINCIPAL NAICS CODE: 811210 - Electronic and Precision Equipment Repair and Maintenance PRODUCT/SERVICE CODE: Z1FZ - Maintenance of Other Residential Buildings LOCAL STOCK NUMBER: Line 2
| 80.00 |
| HR |
| __________________ |
| __________________ |
Painter
POP Begin: 07-01-2026 POP End: 08-10-2026 PRINCIPAL NAICS CODE: 811210 - Electronic and Precision Equipment Repair and Maintenance PRODUCT/SERVICE CODE: Z1FZ - Maintenance of Other Residential Buildings LOCAL STOCK NUMBER: Line 3
| GRAND TOTAL |
| __________________ |
36C25626Q0912
Page 1 of Page 1 of Page 1 of Page 1 of
SECTION C - CONTRACT CLAUSES
C.1 52.212-4 CONTRACT TERMS AND CONDITIONS—COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES (NOV 2023)
(a) Inspection/Acceptance. The Contractor shall only tender for acceptance those items that conform to the requirements of this contract. The Government reserves the right to inspect or test any supplies or services that have been tendered for acceptance. The Government may require repair or replacement of nonconforming supplies or reperformance of nonconforming services at no increase in contract price. If repair/replacement or reperformance will not correct the defects or is not possible, the Government may seek an equitable price reduction or adequate consideration for acceptance of nonconforming supplies or services. The Government must exercise its post-acceptance rights—
(1) Within a reasonable time after the defect was discovered or should have been discovered; and
(2) Before any substantial change occurs in the condition of the item, unless the change is due to the defect in the item.
(b) Assignment. The Contractor or its assignee may assign its rights to receive payment due as a result of performance of this contract to a bank, trust company, or other financing institution, including any Federal lending agency in accordance with the Assignment of Claims Act (31 U.S.C. 3727). However, when a third party makes payment (e.g., use of the Governmentwide commercial purchase card), the Contractor may not assign its rights to receive payment under this contract.
(c) Changes. Changes in the terms and conditions of this contract may be made only by written agreement of the parties.
(d) Disputes. This contract is subject to 41 U.S.C. chapter 71, Contract Disputes. Failure of the parties to this contract to reach agreement on any request for equitable adjustment, claim, appeal or action arising under or relating to this contract shall be a dispute to be resolved in accordance with the clause at Federal Acquisition Regulation (FAR) 52.233-1, Disputes, which is incorporated herein by reference. The Contractor shall proceed diligently with performance of this contract, pending final resolution of any dispute arising under the contract.
(e) Definitions. The clause at FAR 52.202-1, Definitions, is incorporated herein by reference.
(f) Excusable delays. The Contractor shall be liable for default unless nonperformance is caused by an occurrence beyond the reasonable control of the Contractor and without its fault or negligence such as, acts of God or the public enemy, acts of the Government in either its sovereign or contractual capacity, fires, floods, epidemics, quarantine restrictions, strikes, unusually severe weather, and delays of common carriers. The Contractor shall notify the Contracting Officer in writing as soon as it is reasonably possible after the commencement of any excusable delay, setting forth the full particulars in connection therewith, shall remedy such occurrence with all reasonable dispatch, and shall promptly give written notice to the Contracting Officer of the cessation of such occurrence.
(g) Invoice.
(1) The Contractor shall submit an original invoice and three copies (or electronic invoice, if authorized) to the address designated in the contract to receive invoices. An invoice must include—
(i) Name and address of the Contractor;
(ii) Invoice date and number;
(iii) Contract number, line item number and, if applicable, the order number;
(iv) Description, quantity, unit of measure, unit price and extended price of the items delivered;
(v) Shipping number and date of shipment, including the bill of lading number and weight of shipment if shipped on Government bill of lading;
(vi) Terms of any discount for prompt payment offered;
(vii) Name and address of official to whom payment is to be sent;
(viii) Name, title, and phone number of person to notify in event of defective invoice; and
(ix) Taxpayer Identification Number (TIN). The Contractor shall include its TIN on the invoice only if required elsewhere in this contract.
(x) Electronic funds transfer (EFT) banking information.
(A) The Contractor shall include EFT banking information on the invoice only if required elsewhere in this contract.
(B) If EFT banking information is not required to be on the invoice, in order for the invoice to be a proper invoice, the Contractor shall have submitted correct EFT banking information in accordance with the applicable solicitation provision, contract clause (e.g., 52.232-33, Payment by Electronic Funds Transfer—System for Award Management, or 52.232-34, Payment by Electronic Funds Transfer—Other Than System for Award Management), or applicable agency procedures.
(C) EFT banking information is not required if the Government waived the requirement to pay by EFT.
(2) Invoices will be handled in accordance with the Prompt Payment Act (31 U.S.C. 3903) and Office of Management and Budget (OMB) prompt payment regulations at 5 CFR part 1315.
(h) Patent indemnity. The Contractor shall indemnify the Government and its officers, employees and agents against liability, including costs, for actual or alleged direct or contributory infringement of, or inducement to infringe, any United States or foreign patent, trademark or copyright, arising out of the performance of this contract, provided the Contractor is reasonably notified of such claims and proceedings.
(i) Payment.—
(1) Items accepted. Payment shall be made for items accepted by the Government that have been delivered to the delivery destinations set forth in this contract.
(2) Prompt payment. The Government will make payment in accordance with the Prompt Payment Act (31 U.S.C. 3903) and prompt payment regulations at 5 CFR part 1315.
(3) Electronic Funds Transfer (EFT). If the Government makes payment by EFT, see 52.212-5(b) for the appropriate EFT clause.
(4) Discount. In connection with any discount offered for early payment, time shall be computed from the date of the invoice. For the purpose of computing the discount earned, payment shall be considered to have been made on the date which appears on the payment check or the specified payment date if an electronic funds transfer payment is made.
(5) Overpayments. If the Contractor becomes aware of a duplicate contract financing or invoice payment or that the Government has otherwise overpaid on a contract financing or invoice payment, the Contractor shall—
(i) Remit the overpayment amount to the payment office cited in the contract along with a description of the overpayment including the—
(A) Circumstances of the overpayment (e.g., duplicate payment, erroneous payment, liquidation errors, date(s) of overpayment);
(B) Affected contract number and delivery order number, if applicable;
(C) Affected line item or subline item, if applicable; and
(D) Contractor point of contact.
(ii) Provide a copy of the remittance and supporting documentation to the Contracting Officer.
(6) Interest.
(i) All amounts that become payable by the Contractor to the Government under this contract shall bear simple interest from the date due until paid unless paid within 30 days of becoming due. The interest rate shall be the interest rate established by the Secretary of the Treasury as provided in 41 U.S.C. 7109, which is applicable to the period in which the amount becomes due, as provided in (i)(6)(v) of this clause, and then at the rate applicable for each six-month period as fixed by the Secretary until the amount is paid.
(ii) The Government may issue a demand for payment to the Contractor upon finding a debt is due under the contract.
(iii) Final decisions. The Contracting Officer will issue a final decision as required by 33.211 if—
(A) The Contracting Officer and the Contractor are unable to reach agreement on the existence or amount of a debt within 30 days;
(B) The Contractor fails to liquidate a debt previously demanded by the Contracting Officer within the timeline specified in the demand for payment unless the amounts were not repaid because the Contractor has requested an installment payment agreement; or
(C) The Contractor requests a deferment of collection on a debt previously demanded by the Contracting Officer (see 32.607-2).
(iv) If a demand for payment was previously issued for the debt, the demand for payment included in the final decision shall identify the same due date as the original demand for payment.
(v) Amounts shall be due at the earliest of the following dates:
(A) The date fixed under this contract.
(B) The date of the first written demand for payment, including any demand for payment resulting from a default termination.
(vi) The interest charge shall be computed for the actual number of calendar days involved beginning on the due date and ending on—
(A) The date on which the designated office receives payment from the Contractor;
(B) The date of issuance of a Government check to the Contractor from which an amount otherwise payable has been withheld as a credit against the contract debt; or
(C) The date on which an amount withheld and applied to the contract debt would otherwise have become payable to the Contractor.
(vii) The interest charge made under this clause may be reduced under the procedures prescribed in FAR 32.608-2 in effect on the date of this contract.
(j) Risk of loss. Unless the contract specifically provides otherwise, risk of loss or damage to the supplies provided under this contract shall remain with the Contractor until, and shall pass to the Government upon:
(1) Delivery of the supplies to a carrier, if transportation is f.o.b. origin; or
(2) Delivery of the supplies to the Government at the destination specified in the contract, if transportation is f.o.b. destination.
(k) Taxes. The contract price includes all applicable Federal, State, and local taxes and duties.
(l) Termination for the Government's convenience. The Government reserves the right to terminate this contract, or any part hereof, for its sole convenience. In the event of such termination, the Contractor shall immediately stop all work hereunder and shall immediately cause any and all of its suppliers and subcontractors to cease work. Subject to the terms of this contract, the Contractor shall be paid a percentage of the contract price reflecting the percentage of the work performed prior to the notice of termination, plus reasonable charges the Contractor can demonstrate to the satisfaction of the Government using its standard record keeping system, have resulted from the termination. The Contractor shall not be required to comply with the cost accounting standards or contract cost principles for this purpose. This paragraph does not give the Government any right to audit the Contractor's records. The Contractor shall not be paid for any work performed or costs incurred which reasonably could have been avoided.
(m) Termination for cause. The Government may terminate this contract, or any part hereof, for cause in the event of any default by the Contractor, or if the Contractor fails to comply with any contract terms and conditions, or fails to provide the Government, upon request, with adequate assurances of future performance. In the event of termination for cause, the Government shall not be liable to the Contractor for any amount for supplies or services not accepted, and the Contractor shall be liable to the Government for any and all rights and remedies provided by law. If it is determined that the Government improperly terminated this contract for default, such termination shall be deemed a termination for convenience.
(n) Title. Unless specified elsewhere in this contract, title to items furnished under this contract shall pass to the Government upon acceptance, regardless of when or where the Government takes physical possession.
(o) Warranty. The Contractor warrants and implies that the items delivered hereunder are merchantable and fit for use for the particular purpose described in this contract.
(p) Limitation of liability. Except as otherwise provided by an express warranty, the Contractor will not be liable to the Government for consequential damages resulting from any defect or deficiencies in accepted items.
(q) Other compliances. The Contractor shall comply with all applicable Federal, State and local laws, executive orders, rules and regulations applicable to its performance under this contract.
(r) Compliance with laws unique to Government contracts. The Contractor agrees to comply with 31 U.S.C. 1352 relating to limitations on the use of appropriated funds to influence certain Federal contracts; 18 U.S.C. 431 relating to officials not to benefit; 40 U.S.C. chapter 37, Contract Work Hours and Safety Standards; 41 U.S.C. chapter 87, Kickbacks; 49 U.S.C. 40118, Fly American; and 41 U.S.C. chapter 21 relating to procurement integrity.
(s) Order of precedence. Any inconsistencies in this solicitation or contract shall be resolved by giving precedence in the following order:
(1) The schedule of supplies/services.
(2) The Assignments, Disputes, Payments, Invoice, Other Compliances, Compliance with Laws Unique to Government Contracts, and Unauthorized Obligations paragraphs of this clause;
(3) The clause at 52.212-5.
(4) Addenda to this solicitation or contract, including any license agreements for computer software.
(5) Solicitation provisions if this is a solicitation.
(6) Other paragraphs of this clause.
(7) The Standard Form 1449.
(8) Other documents, exhibits, and attachments
(9) The specification.
(t) [Reserved]
(u) Unauthorized Obligations.
(1) Except as stated in paragraph (u)(2) of this clause, when any supply or service acquired under this contract is subject to any End User License Agreement (EULA), Terms of Service (TOS), or similar legal instrument or agreement, that includes any clause requiring the Government to indemnify the Contractor or any person or entity for damages, costs, fees, or any other loss or liability that would create an Anti-Deficiency Act violation (31 U.S.C. 1341), the following shall govern:
(i) Any such clause is unenforceable against the Government.
(ii) Neither the Government nor any Government authorized end user shall be deemed to have agreed to such clause by virtue of it appearing in the EULA, TOS, or similar legal instrument or agreement. If the EULA, TOS, or similar legal instrument or agreement is invoked through an “I agree” click box or other comparable mechanism (e.g., “click-wrap” or “browse-wrap” agreements), execution does not bind the Government or any Government authorized end user to such clause.
(iii) Any such clause is deemed to be stricken from the EULA, TOS, or similar legal instrument or agreement.
(2) Paragraph (u)(1) of this clause does not apply to indemnification by the Government that is expressly authorized by statute and specifically authorized under applicable agency regulations and procedures.
(v) Incorporation by reference. The Contractor’s representations and certifications, including those completed electronically via the System for Award Management (SAM), are incorporated by reference into the contract.
(End of Clause) ADDENDUM to FAR 52.212-4 CONTRACT TERMS AND CONDITIONS—COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES Clauses that are incorporated by reference (by Citation Number, Title, and Date), have the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available.
The following clauses are incorporated into 52.212-4 as an addendum to this contract:
(End of Addendum to 52.212-4)
C.2 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):
https://www.acquisition.gov/browse/index/far https://www.va.gov/oal/library/vaar/
(End of Clause)
| FAR Number |
| Title |
| Date |
| 52.203-17 |
| CONTRACTOR EMPLOYEE WHISTLEBLOWER RIGHTS |
| NOV 2023 |
| 52.204-13 |
| SYSTEM FOR AWARD MANAGEMENT—MAINTENANCE (DEVIATION) |
| NOV 2025 |
| 52.203-19 |
| PROHIBITION ON REQUIRING CERTAIN INTERNAL CONFIDENTIALITY AGREEMENTS OR STATEMENTS |
| JAN 2017 |
C.3 52.209-10 PROHIBITION ON CONTRACTING WITH INVERTED DOMESTIC CORPORATIONS (NOV 2015)
(a) Definitions. As used in this clause— Inverted domestic corporation means a foreign incorporated entity that meets the definition of an inverted domestic corporation under 6 U.S.C. 395(b), applied in accordance with the rules and definitions of 6 U.S.C. 395(c).
Subsidiary means an entity in which more than 50 percent of the entity is owned—
(1) Directly by a parent corporation; or
(2) Through another subsidiary of a parent corporation.
(b) If the contractor reorganizes as an inverted domestic corporation or becomes a subsidiary of an inverted domestic corporation at any time during the period of performance of this contract, the Government may be prohibited from paying for Contractor activities performed after the date when it becomes an inverted domestic corporation or subsidiary. The Government may seek any available remedies in the event the Contractor fails to perform in accordance with the terms and conditions of the contract as a result of Government action under this clause.
(c) Exceptions to this prohibition are located at 9.108-2.
(d) In the event the Contractor becomes either an inverted domestic corporation, or a subsidiary of an inverted domestic corporation during contract performance, the Contractor shall give written notice to the Contracting Officer within five business days from the date of the inversion event.
(End of Clause)
| FAR Number |
| Title |
| Date |
| 52.222-19 |
| CHILD LABOR—COOPERATION WITH AUTHORITIES AND REMEDIES (DEVIATION) |
| MAR 2026 |
| 52.222-41 |
| SERVICE CONTRACT LABOR STANDARDS (DEVIATION) |
| NOV 2025 |
C.4 52.222-42 STATEMENT OF EQUIVALENT RATES FOR FEDERAL HIRES (MAY 2014)
In compliance with the Service Contract Labor Standards statute and the regulations of the Secretary of Labor (29 CFR Part 4), this clause identifies the classes of service employees expected to be employed under the contract and states the wages and fringe benefits payable to each if they were employed by the contracting agency subject to the provisions of 5 U.S.C.5341 or 5332.
This Statement is for Information Only:
It is not a Wage Determination
| Employee Class |
| Monetary Wage-Fringe Benefits |
(End of Clause)
C.5 52.222-50 COMBATING TRAFFICKING IN PERSONS (NOV 2025) (DEVIATION)
(a) Definitions. As used in this clause- Agent means any individual, including a director, an officer, an employee, or an independent contractor, authorized to act on behalf of the organization.
Coercion means-
(1) Threats of serious harm to or physical restraint against any person;
(2) Any scheme, plan, or pattern intended to cause a person to believe that failure to perform an act would result in serious harm to or physical restraint against any person; or
(3) The abuse or threatened abuse of the legal process.
Commercial sex act means any sex act on account of which anything of value is given to or received by any person.
Commercially available off-the-shelf (COTS) item—
(1) Means any item of supply (including construction material) that is—
(i) A commercial product (as defined in paragraph (1) of the definition of "commercial product" at Federal Acquisition Regulation (FAR) 2.101;
(ii) Sold in substantial quantities in the commercial…