This is a Questions and Answers document for a chiller rental and maintenance services solicitation at the Central Arkansas Veterans Healthcare System. The document clarifies that the chiller will remain on-site year-round but operate only 6 months per year, being winterized during the off-season. The system requires a 40-degree Fahrenheit chilled water supply, with 4160V/139 amps power availability.

Key technical details include that the government prefers a 1000-ton chiller and towers configuration over split systems, no remote monitoring is required, and electrical connections must be performed by a licensed contractor. Contractors are responsible for submitting maintenance plans for winterized periods and providing delivery, installation, and start-up timelines in their technical quotes. The contractor will handle initial setup in the first year and decommissioning in the final year, with annual winterization/de-winterization services during intermediate years. Questions were also answered regarding electrical specifications and maintenance scheduling during the standdown periods.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions & Responses

Question 1. Sir, upon reviewing this project scope and bid form. I am trying to confirm you are asking for a 6month rental agreement and leaving the chiller onsite and out of use the remaining

6 months? Or are you looking to rent this chiller for an entire year?

If this is only a 6-month rental period, we would have to pull this chiller at the end of the 6month period to be rented elsewhere through the winter and reconnected at the beginning of the next summer.

Response 1. The operational status of the chiller shall be 6-months of the year and the other 6-months shall be winterized and sit on-site until start up the following ordering period (See

Section B.4 (1) of SOW/Solicitation. The initial set-up would be the first year of the contract and the decommission would be the last year of the contact. The end of the base year contract and the middle years would just need a startup/unwinterized and a standdown/winterized of the equipment.

Question 2. Will the chiller/tower/pumps be removed and reinstalled at the end of cooling season each year and stored? Or will everything remain in place and just be winterized/shut down at the end of each cooling season?

Response 2. See Response 1

Question 3. What is the required supply and return water temperature(s)?

Response 3: Government maintain a 40-degree Fahrenheit chilled water supply into the building. Return water temps vary depending on the heat load of the building.

Question 4. What is the total available/allocated house power amperage at 4160V for the

Chiller(s) and Cooling Tower?

Response 4: 4160V with 139 amps

Question 5. Due to high utilization on Chillers during the warmer season and based on the total amps available at 4160V, is there an option, if necessary, to utilize (1) 500 Ton Air Cooled

Chiller and (1) 500 Ton Water Cooled Chiller?

Response 5: In the past the 1000-ton chiller and towers have worked best for the government. Contractor can submit with technical quote how option will still meet the government requirement. Contractor technical quote for option shall stay within the VA power requirements of 4160v and no more than 139 amps.

Question 6. Is there a need for remote monitoring on the Chiller(s) and/or Cooling Tower? If so, can you please provide specific remote monitoring capabilities required?

Response 6: No, there is no need for remote monitoring.

Question 7. During and throughout the rental duration, what dates are available for scheduled maintenance?

Response 7: Contractor shall submit with technical quote its plan for scheduled maintenance during the standdown/winterized periods.

Question 8. In regard to electrical connections, will this be the responsibility of the VA personnel to orchestrate or will the electrical connections require an electrical contractor?

Response 8: Government has the 4160V cable that is Safed by a lock-out/tag-out in the electrical vault. The electrical connections and testing of the cable to the electrical distribution panel is the responsibility of the license contractor per Section E-1 (4)(a)(ii)(2) of the solicitation.

Question 9. What is the duration for the installation and start-up process?

Response 9: Contractor shall submit with its Technical Quote per Section E-1 (4)(a)(i)(3) of the solicitation, its delivery, installation, and start-up time to be competitively evaluated.

Question 10. One of our prospective contractors has requested additional technical details regarding the amp size of the existing 4160V breaker. Could you please provide this information or direct us?

Response 10: 4160V with 139 amps