36C25624R0109 - ICRA - Inpatient Wards isolation Rooms Exhaust System ICRA FINAL .pdf
PDF 132 KB Posted
- Solicitation number
- 36C25624R0109
About this file
This document is an Infection Control Risk Assessment (ICRA) for a construction project to upgrade the inpatient wards isolation rooms exhaust system at the Overton Brooks VA Medical Center. The ICRA classifies the project as a Type C activity with a moderate amount of dust and debris, and designates the patient risk group as High Risk, requiring Class IV precautions. The ICRA outlines the specific construction activities covered, including removal of drywall, dry sanding, and other invasive work. It mandates infection control documents for the project due to the high-risk patient population. The related federal contract opportunity, solicitation number 36C25624R0109, is for the Z1DA--CON Project 667-25-125 to upgrade the isolation wards room exhaust system, issued by the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 16.
View the file
Other files
Show all 25
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Overton Brooks VA Medical Center Infection Prevention & Control
Step One: Circle the Construction Project Activity Type (A-D). PROJECT: Upgrade Inpatient Wards Isolation
Rooms Exhaust System 667-25-125
Type A
Inspection and non-invasive activities. Includes but is not limited to:
• Removal of ceiling tile for visual inspection-limited to 1 tile/50 square feet with limited exposure time.
• Limited building system maintenance (e.g., pneumatic tube station, HVAC, fire suppression system, electrical and carpentry work to include painting without sanding) that does not create dust or debris.
• Clean plumbing activity limited in nature.
Type B
Small-scale, short duration activities; minimal dust and debris. Includes but not limited to:
• Work conducted above the ceiling (e.g., prolonged inspection/repair of firewalls and barriers, install conduit/cabling, & access to mechanical and/or electrical chase spaces).
• Fan shutdown/startup.
• Installation of electrical devices or new flooring that produces minimal dust and debris.
• The removal of drywall where minimal dust and debris is created.
• Controlled sanding activities (e.g., wet or dry sanding) that produce minimal dust and debris.
Type C
Large-scale, long duration activities; moderate amount of dust and debris. Includes but not limited to:
• Removal of preexisting floor covering, walls, casework, or other building components.
• New drywall placement.
• Renovation work in a single room.
• Non-existing cable pathway or invasive electrical work above ceilings.
• The removal of drywall where a moderate amount of dust and debris is created.
• Dry sanding where a moderate amount of dust and debris is created.
• Work creating significant vibration and/or noise.
• Any activity that cannot be completed in a single work shift.
Type D
Major demolition and construction activities. Includes but is not limited to:
• Removal or replacement of building system component(s).
• Removal/installation of drywall partitions.
• Invasive large-scale new building construction.
• Renovation work in two or more rooms.
Step Two: Circle the Risk Group(s) affected. Select the higher group, when more than one group will be affected.
Low Risk* Medium Risk High Risk Highest Risk
*Not in patient care areas
• Public hallways & gathering areas
• Office areas
• Breakrooms
• Bathrooms or locker rooms
• Mechanical rooms
• EMS closets
• Waiting areas
• Clinical engineering
• Materials management.
• SPS Decon area
• Kitchen, cafeteria, gift shop, coffee shop, food kiosks.
• Patient care rooms/clinics
• All acute inpatient units
• Emergency department
• Occupation Health
• Pharmacy general areas
• Medication, clean utility & sterile supply rooms
• Imaging/diagnostic suites
• Laboratory.
• All transplant & ICUs
• All oncology units.
• OR suites & restricted areas.
• Procedural suites.
• Pharmacy compounding areas
• SPS: Prep and HLD areas
• Transfusion services.
• Dedicated isolation wards/units.
• Invasive imaging suites:
Step Three: Using the IC Matrix CIRCLE the Class of Precautions as determined by Construction Type and Patient Risk.
Construction Project Type
Patient Risk Group Type A Type B Type C Type D
IC
M a tr ix LOW Risk Group1 I II II III
MEDIUM Risk Group1 I II III2 IV2
HIGH Risk Group1 I III IV2 V2
HIGHEST Risk Group1 III IV2 V2 V2
1. Amend as follows for environmental conditions that could affect human health (i.e., sewage, mold, asbestos, gray water, and black water). Class IV Precautions for LOW and MEDIUM Risk Groups and Class V Precautions for HIGH and HIGHEST Risk Groups.
2. Infection Control documents required for Class III Precautions in Type C projects and all Class IV & V Precautions.
Carol Phillips, RN, CIC
MDRO Prevention Coordinator
Preliminary ICRA: ________________
DATE
Final ICRA: _
DATE