This document is a set of Class I Precautions for infection control procedures required for a project to upgrade the inpatient isolation room exhaust system at the Overton Brooks VA Medical Center. The key details are:

The project requires noninvasive work activities to be performed on the roof, coordinated with nursing staff to minimize disruption to patient care. Workers must adhere to strict PPE requirements and ensure there is no dust generation or interruption to the HVAC system. After completion, the work areas must be thoroughly cleaned, and the HVAC system verified to meet original airflow and air exchange specifications. This document outlines the minimum required infection control precautions for this project.

View the file

Other files

File Type Posted
36C25624R0109 0005.docx DOCX document
36C25624R0109 0004.docx DOCX document
Final RFI Register V2 667-25-125.docx DOCX document
Commissioning Spec 01 91 00 v2.pdf PDF
36C25624R0109 0003.docx DOCX document
36C25624R0109_Drawing_Service Elevator.pdf PDF
36C25624R0109_SOW_Update Revised 08-15-2024.doc DOC document
36C25624R0109_G2024-0002275-005-001_Diamond Pledge NDL Roof Guarantee .pdf PDF
36C25624R0109_Final RFI Register 667-25-125.docx DOCX document
36C25624R0109_SPECS_26 41 00 - FACILITY LIGHTNING PROTECTION.docx DOCX document
RFP 36C25624R0109 Site Visit Sign in Sheet.pdf PDF
36C25624R0109 0002.docx DOCX document
36C25624R0109 0001.docx DOCX document
36C25624R0109 EXHIBIT C.docx DOCX document
36C25624R0109 EXHIBIT B.docx DOCX document
36C25624R0109 - Drawing_Project 667-25-125 .pdf PDF
36C25624R0109 EXHIBIT D.docx DOCX document
36C25624R0109 EXHIBIT A.docx DOCX document
36C25624R0109 - Final SOW_Project 667-25-125 .doc DOC document
36C25624R0109 - WD LA20240031 Mod1 dtd 01052024 .pdf PDF
36C25624R0109.docx DOCX document
36C25624R0109 - ICRA - Inpatient Wards isolation Rooms Exhaust System ICRA FINAL .pdf PDF
36C25624R0109 EXHIBIT F.docx DOCX document
36C25624R0109 - Specs Combined_Project 667-25-125 .pdf PDF
36C25624R0109 EXHIBIT E.docx DOCX document
Show all 25

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Overton Brooks VA Medical Center Infection Prevention & Control Class I Precautions

Minimum Required Infection Control Precautions Required for

Project: Upgrade Inpatient Isolation Rooms Exhaust System Date: 5/29/24

CLASS I PRECAUTIONS
Before and During Work
Upon Completion

1. All work is to be conducted on the roof.

2. All work will be coordinated with Nursing Service for room shut down.

3. Perform noninvasive work activity as to not block or interrupt patient care.

4. Perform noninvasive work activities in areas that are not directly occupied with patients.

5. Perform noninvasive work activity in a manner that does not create dust.

6. Immediately replace any displaced ceiling tile before leaving the area and/or at end of noninvasive work activity.

7. Strict adherence to PPE while working in the exhaust system.

Cleaning:

1. Clean work areas including all environmental surfaces, high horizontal surfaces, and flooring materials.

2. Check all supply and return air registers for dust accumulation on upper surfaces as well as air diffuser surfaces.

HVAC Systems:

1. Remove isolation of HVAC system in areas where work is being performed. Verify that HVAC systems are clean and operational.

2. Verify the HVAC systems meet original airflow and air exchange design specifications.

Rev May 2022