This document is a Request for Information (RFI) Register containing questions and answers related to Solicitation Number 36C25624R0109 for Project #667-25-125 to Upgrade Isolation Wards Room Exhaust System.

The key details include:

  • Commissioning and ICRA barriers/containment will be required for work inside the hospital
  • The SSHO and site superintendent can be the same person, but the QC Manager must be separate
  • Roofing system details including existing TPO roofing and maintaining the manufacturer's warranty during construction
  • The Period of Performance is 180 days, but an administrative NTP extension to 240 days may be considered
  • The laydown area location will be discussed after award
  • The solicitation is being issued by the Department of Veterans Affairs, Veterans Health Administration, Veterans Integrated Service Network 16.

View the file

Other files

File Type Posted
36C25624R0109 0005.docx DOCX document
36C25624R0109 0004.docx DOCX document
Final RFI Register V2 667-25-125.docx DOCX document
Commissioning Spec 01 91 00 v2.pdf PDF
36C25624R0109 0003.docx DOCX document
36C25624R0109_Drawing_Service Elevator.pdf PDF
36C25624R0109_SOW_Update Revised 08-15-2024.doc DOC document
36C25624R0109_G2024-0002275-005-001_Diamond Pledge NDL Roof Guarantee .pdf PDF
36C25624R0109_SPECS_26 41 00 - FACILITY LIGHTNING PROTECTION.docx DOCX document
RFP 36C25624R0109 Site Visit Sign in Sheet.pdf PDF
36C25624R0109 0002.docx DOCX document
36C25624R0109 0001.docx DOCX document
36C25624R0109 EXHIBIT C.docx DOCX document
36C25624R0109 EXHIBIT B.docx DOCX document
36C25624R0109 - Drawing_Project 667-25-125 .pdf PDF
36C25624R0109 EXHIBIT D.docx DOCX document
36C25624R0109 EXHIBIT A.docx DOCX document
36C25624R0109 - Final SOW_Project 667-25-125 .doc DOC document
36C25624R0109 - WD LA20240031 Mod1 dtd 01052024 .pdf PDF
36C25624R0109.docx DOCX document
36C25624R0109 - ICRA - Inpatient Wards isolation Rooms Exhaust System ICRA FINAL .pdf PDF
36C25624R0109 EXHIBIT F.docx DOCX document
36C25624R0109 - Specs Combined_Project 667-25-125 .pdf PDF
36C25624R0109 - ICRA - Inpatient Wards Isolation Rooms Exhaust System Class I Precautions .docx DOCX document
36C25624R0109 EXHIBIT E.docx DOCX document
Show all 25

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project #667-25-125 RFI Register

Questions
Answers

1. Will commissioning be required on this project?

Yes, refer to section 01 91 00 General Commissioning Requirements.

2. Will any work inside of the hospital require ICRA barriers/containment?

Yes, refer to 01 35 26 Infection Control. ICRA was included in solicitation package. Request from contracting if not found.

3. Will the SSHO be able to have multiple roles?

Yes, the SSHO and the site superintendent can be the same person.

4. What are the dimensions of the elevator we will be permitted to use?
Please see attachment for Service Elevator.

5. Does the VA believe there to be any asbestos work on this project?

No, we do not believe there is asbestos within the area of construction.

6. Can the VFD’s #1&2 be mounted to brick wall?
The VA will allow this if the brick can handle the weight of the equipment being mounted.
7. If VFD’s are to be mounted to roof deck, Can we receive a curb detail?
See response #6
8. The horsepower and electrical requirements are not listed on the plans, Can we get the motor information?
Contractor to coordinate sizing of equipment per information sheet M-103
9. Does the lighting protection need to be UL listed?
Please Refer to attached project specs for Facility Lighting Protection.

10. Is the Lighting protection required to be copper?

Please Refer to attached project specs for Facility Lighting Protection. Note: This section has been omitted from the Specification.

11. the plans provided for this project have no stamp. Are there other drawings that we will be receiving that are stamped?
All Construction drawings are included in this solicitation package. There are no other available drawings.
12. Due to the size of this project, will the VA allow the site superintendent to also hold the roles of SSHO & Quality Control Manager?
Quality Control Manger (QC) will need to be a separate person.
13. The Statement of Work (SOW) mentions that the contractor needs to "maintain existing manufacturer roof warranty during construction work and keep roofing system watertight." Could the government please provide information on the current manufacturer's roof that has been installed and the company holding the warranty?
Please see attachment for existing manufacture roof warranty.
14. The specifications in the Table of Contents list an Ethylene Interpolymer (KEE) roofing system. However, Section 075423 includes Thermoplastic Polyolefin (TPO) Roofing. Will the government please clarify which of the two systems is currently installed on the roof?
Thermoplastic Polyolefin (TPO) Roofing is what is currently installed.
15. POP is shown as 180 days. After discussions with the mechanical contractors, meeting this deadline with the current lead times will be very challenging. Will the VA consider extending the POP to 240 days?
AN administrative NTP can be discussed at award. Revised SOW is attached.

16. Will the government clarify where the laydown area is located?

This will also be discussed after award.