598-22-102 - PRE-BID RFIs COMPLETE.docx

DOCX document 36 KB Posted

Attached to
Y1NZ--598-22-102 | Fisher House Utilities Site Prep - JLM
Solicitation number
36C25624R0045
Issued by

About this file

This document is a set of pre-bid Requests for Information (RFIs) related to Solicitation No. 36C25624R0045 for the Fisher House Utilities Site Prep (Project No. 598-22-102) at the Department of Veterans Affairs (VA) facility.

The key details include:

  • The project requires site preparation work to support the construction of a Fisher House, including removal of existing solar panels, installation of new utility infrastructure (gas, electrical, water), and demolition of existing underground structures.
  • The VA is responding to 30 RFIs from contractors on various aspects of the project, including utility coordination, site access, fencing requirements, schedule accommodations for long-lead items, and infectious control measures.
  • The contractor will be responsible for coordinating with utility providers (Summit Utilities, Entergy) and including their costs in their proposal. The VA is not providing a "plug number" for these services.
  • The project has a period of performance of 260 days after notice to proceed, with potential extension for the diesel generator procurement if required.
  • The VA has specified certain preferences for the sequencing and timing of the utility installation work.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation No. 36C25624R0045 Project No. 598-22-102 Prebid Requests For Information

FISHER HOUSE UTILITIES SITE PREP

JLM

ITEM #

QUESTIONS

VA RESPONSES

Will VA provide contact information for Summit Utility providers for the person in charge of this project with VA so that we can get an exact SOW from what will be required?
Summit Contact is on sheet CU100 under Gas

Summit Utilities 501-772-2134 Contact Joni Bates

Will Entergy be supplying the Vaults Required in the drawings for Contractor to set under Entergy supervision as they currently do on other projects?
Contractor shall purchase and install Vaults.

During the site visit it was noted by the VA that the GC would have to include a monetary value in the contract to be paid to Summit Utilities for the gas line installation, to be installed by Summit Utilities and their chosen subcontractors in coordination with GC.

What is this monetary value or “plug” number for this requirement?

All offerors are encouraged to contact Summit for estimate. (See contact information in RFI 1)

4
Will the Electrical Service to be installed in conjunction with Entergy be handled in the same manner as the Gas Service by setting aside a set monetary value aside for Entergy? If so, what is the monetary value or “plug” number?
Contractor to install the conduits and manhole/handholes. Entergy will be paid by the contractor to pull the cable. All offerors are encouraged to contact Entergy for estimate. - See CU100 POCs for Entergy are Brad Vance and Jay Hartman.
5
What allowance will be given if ( solid rock ) is encountered during the bore for the electrical service being performed as specified per the drawings? This can add considerable costs and is stated or listed in most HDD/Boring projects.
Solid Rock is not anticipated in this area since the other areas and geotechnical reports do not report solid rock. If solid rock is encountered, this would be considered a differing site condition and a contract modification can be considered at that time.
6
Is this a tax-exempt project?

No, this is not a tax-exempt project.

7
If tax-exempt, will the government be providing a tax-exempt certificate to the Prime Contractor for use by subcontractors and vendors?
No, the VA Federal Tax-Exempt number does not flow down to contractors per FAR 29.303
8
Can the Superintendent be shared across multiple projects, or should they be dedicated full-time to this project and this project only?
No, the Site Superintendent must be dedicated to this project. See FAR 52.236-6.
9
Can the Superintendent fulfill multiple roles?

If so, can they also fulfill the Quality Control role? Can they also fulfill the SSHO role?

Yes, superintendent can serve multiple roles as long as they have experience required per specifications and proper documentation is provided for each role. The superintendent must satisfactorily maintain the roles assigned throughout the project.

10
Does the VA anticipate this project will require off-hours (Overtime) work? If so, what trades or scopes will be required to perform off-hour(Overtime) work?
All work to be performed during normal business hours unless contractor requests otherwise. COR must approve prior to doing work outside of normal business hours and will be at no additional cost to the Government.
11
Will the VA provide a copy of the Site Visit Attendance Sheet?
The site visit attendance sheet will be provided via amendment to the solicitation.
12
Is temp power available for contractors to connect to? If yes, what are the locations where it is available? If available, will contractors need to set a meter to monitor usage?
There is no temp power within site area. Contractor will not have sufficient space for trailer in area. Contractor can use maintenance building for small items as needed and in coordination with COR.
13
Is space available for an 8’ x 40’ temp office/ storage ground-level office that is near the temp power source?
There is no temp power; Contractor can have maximum 8’x20’ temp office on the far northwest side of parking lot or at Maintenance building, if office or storage is necessary.
14
Will the VA consider waiving the AISC (American Institute of Steel Construction) requirement for structural steel fabrication and/or erection for this project? This requirement makes steel procurement on the project exponentially more difficult to obtain.
No new structural steel required, just removal of existing steel.
15
Are any AISC substitute certifications acceptable in lieu of AISC certification?
See Response to RFI 14
16
Can contractors work a four (4) tens schedule?

COR approval can be requested after award. See response to RFI 10

17
In the event of a schedule slip, will weekend work be allowed?
See Response to RFI 10.
18
1.04 DESCRIPTION OF WORK, A. 3. states that existing VA furnishings and equipment will be stored on site. How far from the project location will the storage location be, and is this in reference specifically to the solar canopies and supports column materials or are there other furnishings and equipment as well?
Just to the solar canopies to be palleted and moved to the staff parking garage on the east side of the hospital. See attached Site Map for Garage PV Pallets.

Any cameras removed not needing reinstall to be turned over to the VA.

No other furnishings

19
Drawing Number CD101 Demolition Note 15 states that the construction fence should be 7 feet minimum height around the construction area indicated on sheet G-101. Sheet G-101 is not included in the drawings file. Will sheet G-101 be included in an amendment and will 7 feet minimum height be required for construction fencing? Or will the 6 feet minimum height for construction fencing per Drawing Number CD100 Demolition Note 15 be required?
Minimum of 7 feet to be followed. G-101 should be CD100 and CD101
21
POP is 260 days after NTP. The current lead times on diesel generators (150kva required for

this project) may be up to 360 days for procurement once approved. Will there be an extension of the POP to allow for this long lead item.

Yes, but the POP will only be extended if documentation is provided indicating generator lead time will extend beyond the project POP of 260 days. Only the generator can extend beyond work. All other work to be performed within the 260 days. Generator submittal to be provided to VA and AE for review within 30 days of NTP and then ordered within 15 days of approval.

22
01 00 00- H.1 (Operations and storage areas) – connection fees to a public utility provider

shall be responsibility of the Government – will the GC have any monetary responsibility The contractor will be responsible for providing and installing the Meter; account set ups and other utility fees after set-up are VA responsibility.

23
CD100 – As builts for the existing canopies and piers – the existing piers are from 11’-8”-14’-2” in depth – will piers need to be removed in their entirety or is there a depth below grade that will suffice to meet the intent of this task
Remove up to 5’ depth
24
CU100 – notes that Proposed gas Line & Meter are to be installed by Summit Utilities, also design and install new gas line by Summit – is contractor to contact Summit for pricing

during proposal and include in overall costs or are costs available from GOV.

See Above response to RFI 1

25
CD100 General note #15 denotes a chain link fence around construction area at minimum

height of 6’0”, CD101 General note #15 denotes a height of 7’0” – Is this fence required for the entirety of the construction site and what is preferred height of construction fence.

7’ minimum see above response

26
ED-001 Key Note #3 – Entergy will provide labor materials for dip pole and conduit –

Contractor to carry $10,000 in aid to construction costs to Entergy – Will this $10,000 cover all costs involved for this task.

Contractor is responsible for boring and all other work as well as coordination with Entergy for associated work; the $10,000 in aid is only for the dip pole and conduit material from Entergy

27
As discussed at site visit the existing solar panels to be removed are to be salvaged and

turned over to facility - will contractor leave on site or is there a proposed area for these panels to be stored.

Panels to be palleted and moved to the facility parking garage storage on east side of facility.

28
A-501 – Denotes the coring of the existing exterior wall at the electrical shop GD114F – it

appears there is no other work withing the facility – please concur or provide information.

Correct, contractor to make sure penetration has the appropriate box inside the facility ceiling and no water is penetrating facility at location. Once wire is pulled no other work inside the facility

29
01 00 00-1.12 – Infectious Control – Requires Tuberculosis Screening for contractor

employees within 90 days of site work – with the vast majority of work exterior to the facility can this requirement be deleted.

Contractor employees performing work inside a hospital building are required to have the Tuberculosis Screening.

30
Does the VA have a preference or order of priority for installation of various utilities to coordinate with the Fisher House construction?
Yes, The Facility priority of utilities is removal of solar panels to be complete or near complete by June 17th. The electrical boring/conduits to be installed and near complete within 60 days of NTP. Then the duct bank to follow electrical work.

Gas to be ordered with Summit utilities within 10 days of NTP. Water to be constructed at any point in the project but shortly after the duct bank or concurrent with duct bank work is preferred Generator submittal to be provided to VA and AE for review within 30 days of NTP and then ordered within 15 days of approval.