This document outlines a federal contract opportunity for construction renovation services. The Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 16 is soliciting proposals to conduct demolition and anti-ligature construction work in Building 9, 3rd Floor at an unspecified medical center. The project scope involves remodeling areas to reduce ligature risks and will take an estimated 300 days to complete. All contractors must be trained on mental health safety protocols and comply with infection control and Environment of Care requirements. Noise, vibrations, air quality issues and other potential impacts are assessed, along with safety precautions for electrical work, fall protection, fire plans, and other construction activities.

View the file

Other files

File Type Posted
36C25622R0073 AL 9500.pdf PDF
36C25622R0073 Updated RFI Register 14 July 2022.docx DOCX document
36C25622R0073 0005.docx DOCX document
Updated RFI Register 12 July 2022.docx DOCX document
P-101 v2.pdf PDF
36C25622R0073 0004.docx DOCX document
36C25622R0073 0003.docx DOCX document
RFI Register 28 June 2022 v2.docx DOCX document
36C25622R0073 0002.docx DOCX document
Site Visit Sign in Sheet.pdf PDF
36C25622R0073 0001.docx DOCX document
36C25622R0073 EXHIBIT C.docx DOCX document
36C25622R0073 EXHIBIT E.docx DOCX document
36C25622R0073 EXHIBIT A.docx DOCX document
36C25622R0073 Brand Name JA 502-20-113_Redacted v2.pdf PDF
36C25622R0073 RFP.docx DOCX document
36C25622R0073 Drawings Volume 1 .pdf PDF
36C25622R0073 WD LA 20220051 Mod 2 02252022 .docx DOCX document
36C25622R0073 Drawings Volume 2 .pdf PDF
36C25622R0073 Specifications Rev 2 .pdf PDF
36C25622R0073 Revised SOW 04012022 .docx DOCX document
36C25622R0073 EXHIBIT F.docx DOCX document
36C25622R0073 EXHIBIT D.docx DOCX document
36C25622R0073 EXHIBIT B.docx DOCX document
36C25622R0073 COVID-19 Safety Protocols for Federal Contractors rev2.docx DOCX document
Show all 25

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Pro·ect Risk & Im act Assessment Date of Print Review: Demolition Start Date: TBD

Estimated Project Length: 300 Days

1--------------------------------1

Scope of Project: Bldg. 9 3rd Floor Anti-Ligature

Areas Effected by the Project:

Bldg. 9

Required OSHA Training: (10hr, 30hr)

Services Render Inoperative: None Overall EOC Effect to Which Areas: Locked MH Unit

X

X

X

X

Hi h Interest Assessment Items Construction Specific

Noise Type: □ Drilling □ Blasting I Pounding □ Heavy Equipment □ Motors □ Other: ______ _ Severity: □ Low I Mild □ Moderate □ High □ Severe Duration: □ Short □ Brief I Intermittent □ Frequent □ Prolon ed □ Continuous

Vibration Type: □ Primary I Secondary □ Other: ___ _ Severity: I Low □ Mild □ Moderate □ High ·o Severe Duration: □ Short I Brief □ Intermittent □ Frequent □ Prolon ed □ Continuous

ILSM

Air Quality Issues Type: I Fumes □ Dust □ Mold □ Smoke □ Chemicals Severity: I Low □ Mild □ Moderate □ High □ Severe Duration: □ Short I Brief □ Intermittent □ Frequent □ Prolon ed □ Continuous Utility Issues Type: I HVAC □ Med Gas □ Power □ Water □ Suction Impact: I Modified Operational □ Shut Down Duration: □ Short I Brief □ Intermittent □ Frequent □ Prolon ed □ Continuous

Operational Impact

Asbestos

X Access and Waiting Areas

X Infection Control Hazards Security Systems Impaired

O vercrowding/Patient Flow

Impaired Access to Facility Patient Care Effected Trench ing/Shoring/Holes X Heat or Flames

Team Involvement

X High

-Medium

Low

Comments

X E lectrical Work Limit Access to Care All employee 1---X--+-O- v_e_rh_ e_a_d _H_ a_z _a -rd_s _/C_ r_a -in- O-pe- r -at-io_n_(_S_e_e_N_o_te_B_) ---+----+-C- 1 -in -ic_a _l A-la _rm_ s -lm_p_a-irm_e _n _t --+-----< notification on

X Hot Work Permits Generator Power ISLM issued during 1---X--+-F- i -re _ P_ l -an _R_e -qu- i -re_d _ ____ ___________ E_q_u-ip_m_ e_ n_t _M_o_d _ifi-c-at-io_n _s_--+-----< the construction of

X Fall Protection Air/Oxygen/Suction (AOV) this project Lighting X Smoke Producing

0 erations Portable Heaters X Weekly Inspections required Access to IT closets Access to IT data systems

X Fire Wall Penetrations VISN Notifications Other Special Needs or Considerations Recommendations: Must comply to all infection control permit requiremenU Reminder even though there is no Asbestos noted for the building please be aware that anyth ing that should look like asbestos should be tested. Must comply with Mental Health environment of Care and all Contractors work ing the building must be trained on Mental health safe rior to workin in the buildin