Questions and Answers I 062022.docx

DOCX document 16 KB Posted

Attached to
J061--36C25622Q0985 - Transformer Testing and Maintenance Federal contract opportunity
Solicitation number
36C25622Q0985
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 16

About this file

This document outlines a request for quotation for transformer testing and maintenance services at the Southeast Louisiana Veterans Healthcare System facility. The contractor will perform testing, inspection and maintenance on over 200 transformers for a base period and three option years. Quotes are due by June 22, 2022 at 1:00 PM Central Time and must be submitted electronically to David.Bourgeois1@va.gov. A site visit is scheduled for June 10, 2022 at 9:30 AM Central Time. This is a 100% set-aside for service-disabled veteran owned small businesses under NAICS code 238210 with a size standard of $16.5 million. The Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 16 is the contracting agency.

View the file

Other files for this federal contract opportunity

Other files attached to J061--36C25622Q0985 - Transformer Testing and Maintenance, newest first.
File Type Posted
36C25622Q0985 0002_1.docx DOCX document
36C25622Q0985 0001.docx DOCX document
Multiple Drawings.pdf PDF
418-8ES601.pdf PDF
01477-1ES602.pdf PDF
36C25622Q0985.docx DOCX document
WD 2015-5189 Revision 22.pdf PDF
5 - Site Visit 052722.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Q1. Provide copies of last arc flash study with hazard diagrams.

A1. Will provide information on-site hard copy access & electronically file access to the awardee. Information spread over multiple volumes and the electronic file is too large to transmit.

Q2. Provide riser diagrams showing all transformers.

A2. Forwarded separately Q3. Provide a copy of last switchgear testing.

A3. Will provide awardee access to Coordination Study Q4. Is the Certified Electrical Test Technologist required to be on site at all times while work is being performed?

A4. Certified Electrical Test Technologist required during testing.

Q5. The report requires photos, but we were told during pre-bid they are not allowed. Please clarify.

A5. Photos can be taken of transformers and related equipment in non-patient areas. Pictures shall not depict patients, staff personnel or other people. General approach was taken to avoid competitors taken pictures of competition or others without their knowledge.

Q6. Please clarify the statement: Testing must be performed over a time frame that cannot exceed a three-week period.

A6. Minimizing shutdown activities Q7. SOW states a max of 225 transformers, how many breakers?

A7. Riser diagrams will aid with determination. Panel/distribution schedules will be available for awardee.

Q8. Can the VA provide a copy of the one line and riser diagrams and arc flash studies for the facility?

A8. See A1. A2 Q9. What will be required for contractor access? Badges, uniform, etc.

A9. Contractors shall use USA access for badging. 1st step will be to forward basic information of personnel to VA to set-up fingerprinting – full name, birthplace (city, state), and Full SSN Q10. Will the VA allow laydown areas, for storage of parts/equipment, if coordinated and contract provides secure storage?

A10. VA will allow laydown area. Amount of area must be approved. Contractor is responsible for their parts/equipment.

Q11. What is the location for authorized deliveries?

A11. Central Energy Plant dock is the area for deliveries. Contractor must be present to accept deliveries and notify Police Services prior to deliveries.

Q12. Which facilities have ½ floors?

A12. Research, Central Plant and Pan Am (Admin) have ½ floors Q13. What are vaccination requirements for contractors?

A13. Refer to FAR Provision 52.223-99 in the original RFQ.

Q14. Do any areas require testing prior to entry and if so, what is the process?

A14. Transitional Living requires swab testing twice a week. Contractors will forward contact information to VA COR, who forwards the information to Occupational Health for on-site testing at Emergency.

Q15. What are the advance requirements to schedule shutdown of equipment?

A15. What, Where, When, How long? 2-week advance notice to allow communication with areas that are impacted.