This document provides specifications for a painting project. The Southeast Louisiana Veterans Health Care System is soliciting proposals for Project No. 629-18-107 to construct a surface level parking lot in New Orleans, Louisiana. The project specifications include preparation and application requirements for various paint products on surfaces such as steel, ferrous metal, and zinc-coated metal. Proposals are due around October 26, 2021 with contract award anticipated within 30 days thereafter. The performance period is 180 calendar days from notice to proceed. The estimated construction cost range is between $1,000,000 and $2,000,000. The solicitation is set aside as 100% for Service-Disabled Veteran-Owned Small Businesses.
View the file
Other files
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Southeast Louisiana Veterans Health Care System, New Orleans, LA Project No. 629-18-107 Construct Surface Level Parking Lot LACHIN Architects, apc
PAINTING 09 91 00 - 1
SECTION 09 91 00
PAINTING
PART 1 - GENERAL
DESCRIPTION
A. Work of this Section includes all labor, materials, equipment, and services necessary to complete the painting and finishing as shown on the construction documents and/or specified herein, including, but not limited to, the following:
1. Prime coats which may be applied in shop under other sections.
2. Prime painting unprimed surfaces to be painted under this Section.
3. Painting items furnished with a prime coat of paint, including touching up of or repairing of abraded, damaged or rusted prime coats applied by others.
4. Painting ferrous metal (except stainless steel) exposed to view.
5. Painting galvanized ferrous metals exposed to view steel bollards.
6. Painting pipes, pipe coverings, conduit, ducts, insulation, hangers, supports and other mechanical and electrical items and equipment exposed to view.
7. Incidental painting and touching up as required to produce proper finish for painted surfaces, including touching up of factory finished items.
8. Painting of any surface not specifically mentioned to be painted herein or on construction documents, but for which painting is obviously necessary to complete the job, or work which comes within the intent of these specifications, is to be included as though specified.
RELATED WORK
A. Section 01 35 26, SAFETY REQUIREMENTS: Activity Hazard Analysis.
B. Division 05 METALS: Shop prime painting of steel and ferrous metals.
C. Division 32 EXTERIOR IMPROVEMENTS: Shop prime painting of steel and ferrous metals.
D. Section 32 17 23, PAVEMENT MARKINGS: Asphalt and concrete pavement marking.
SUBMITTALS
A. Submit in accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.
B. Painter qualifications.
C. Manufacturer's Literature and Data:
PAINTING 09 91 00 - 2
1. Before work is started, or sample panels are prepared, submit manufacturer's literature and technical data, the current Master
Painters Institute (MPI) "Approved Product List" indicating brand label, product name and product code as of the date of contract award, will be used to determine compliance with the submittal requirements of this specification. The Contractor may choose to use subsequent MPI
"Approved Product List", however, only one (1) list may be used for the entire contract and each coating system is to be from a single manufacturer. All coats on a particular substrate must be from a single manufacturer. No variation from the MPI "Approved Product List" where applicable is acceptable.
D. Sample Panels:
1. After painters' materials have been approved and before work is started, submit sample panels showing each type of finish and color specified.
2. Strips showing not less than 50 mm (2 inch) wide strips of undercoats and 100 mm (4 inch) wide strip of finish coat.
E. Sample of identity markers if used.
F. Manufacturers' Certificates indicating compliance with specified requirements:
1. Manufacturer's paint substituted for Federal Specification paints meets or exceeds performance of paint specified.
DELIVERY AND STORAGE
A. Deliver materials to site in manufacturer's sealed container marked to show following:
1. Name of manufacturer.
2. Product type.
3. Batch number.
4. Instructions for use.
5. Safety precautions.
B. In addition to manufacturer's label, provide a label legibly printed as following:
1. Federal Specification Number, where applicable, and name of material.
2. Surface upon which material is to be applied.
3. Specify Coat Types: Prime; body; finish; etc.
PAINTING 09 91 00 - 3
C. Maintain space for storage, and handling of painting materials and equipment in a ventilated, neat and orderly condition to prevent spontaneous combustion from occurring or igniting adjacent items.
D. Store materials at site at least 24 hours before using, at a temperature between 7 and 30 degrees C (45 and 85 degrees F).
QUALITY ASSURANCE
A. Qualification of Painters: Use only qualified journeyman painters for the mixing and application of paint on exposed surfaces. Submit evidence that key personnel have successfully performed surface preparation and application of coating on a minimum of three (3) similar projects within the past three (3) years.
B. Paint Coordination: Provide finish coats which are compatible with the prime paints used. Review other Sections of these specifications in which prime paints are to be provided to ensure compatibility of the total coatings system for the various substrates. Upon request from other subcontractors, furnish information on the characteristics of the finish materials proposed to be used, to ensure that compatible prime coats are used. Provide barrier coats over incompatible primers or remove and re-prime as required. Notify the Contracting Officer Representative (COR) in writing of any anticipated problems using the coating systems as specified with substrates primed by others.
REGULATORY REQUIREMENTS
A. Paint materials are to conform to the restrictions of the local Environmental and Toxic Control jurisdiction.
1. Volatile Organic Compounds (VOC) Emissions Requirements: Field-applied paints and coatings that are inside the waterproofing system to not exceed limits of authorities having jurisdiction.
2. Lead-Base Paint:
a. Comply with Section 410 of the Lead-Based Paint Poisoning Prevention
Act, as amended, and with implementing regulations promulgated by
Secretary of Housing and Urban Development.
b. Regulations concerning prohibition against use of lead-based paint in federal and federally assisted construction, or rehabilitation of residential structures are set forth in Subpart F, Title 24, Code of
Federal Regulations, Department of Housing and Urban Development.
c. Do not use coatings having a lead content over 0.06 percent by weight of non-volatile content.
PAINTING 09 91 00 - 4
d. For lead-paint removal, see Section 02 83 33.13, LEAD-BASED PAINT
REMOVAL AND DISPOSAL.
3. Asbestos: Provide materials that do not contain asbestos.
4. Chromate, Cadmium, Mercury, and Silica: Provide materials that do not contain zinc-chromate, strontium-chromate, Cadmium, mercury or mercury compounds or free crystalline silica.
5. Human Carcinogens: Provide materials that do not contain any of the
ACGIH-BKLT and ACGHI-DOC confirmed or suspected human carcinogens.
6. Use high performance acrylic paints in place of alkyd paints.
SAFETY AND HEALTH
A. Apply paint materials using safety methods and equipment in accordance with the following:
1. Comply with applicable Federal, State, and local laws and regulations, and with the ACCIDENT PREVENTION PLAN, including the Activity Hazard
Analysis (AHA) as specified in Section 01 35 26, SAFETY REQUIREMENTS.
The AHA is to include analyses of the potential impact of painting operations on painting personnel and on others involved in and adjacent to the work zone.
B. Safety Methods Used During Paint Application: Comply with the requirements of SSPC PA Guide 10.
C. Toxic Materials: To protect personnel from overexposure to toxic materials, conform to the most stringent guidance of:
1. The applicable manufacturer’s Material Safety Data Sheets (MSDS) or local regulation.
2. 29 CFR 1910.1000.
3. ACHIH-BKLT and ACGHI-DOC, threshold limit values.
APPLICABLE PUBLICATIONS
A. Publications listed below form a part of this specification to the extent referenced. Publications are referenced in the text by basic designation only.
B. American Conference of Governmental Industrial Hygienists (ACGIH):
ACGIH TLV-BKLT-2012.....Threshold Limit Values (TLV) for Chemical
Substances and Physical Agents and Biological
Exposure Indices (BEIs)
ACGIH TLV-DOC-2012......Documentation of Threshold Limit Values and
Biological Exposure Indices, (Seventh Edition)
C. ASME International (ASME):
PAINTING 09 91 00 - 5
A13.1-07(R2013).........Scheme for the Identification of Piping Systems
D. Code of Federal Regulation (CFR):
40 CFR 59...............Determination of Volatile Matter Content, Water
Content, Density Volume Solids, and Weight Solids of Surface Coating
E. Commercial Item Description (CID):
A-A-1272A...............Plaster Gypsum (Spackling Compound)
F. Federal Specifications (Fed Spec):
TT-P-1411A..............Paint, Copolymer-Resin, Cementitious (For
Waterproofing Concrete and Masonry Walls) (CEP)
G. Master Painters Institute (MPI):
1.......................Aluminum Paint
3.......................Primer, Alkali Resistant, Water Based
4.......................Interior/ Exterior Latex Block Filler
5.......................Exterior Alkyd Wood Primer
6.......................Exterior, Latex for Exterior Wood Primer
7.......................Exterior Oil Wood Primer
8.......................Exterior Alkyd, Flat MPI Gloss Level 1
9.......................Exterior Alkyd Enamel MPI Gloss Level 6
10......................Exterior Latex, Flat
11......................Exterior Latex, Semi-Gloss
15......................Exterior Latex, Low Sheen (MPI Gloss Level 3-4)
17......................Primer, Bonding, Waterbased
18......................Organic Zinc Rich Primer
22......................Aluminum Paint, High Heat (up to 590% - 1100F)
23......................Primer, Metal, Surface Tolerant
27......................Exterior / Interior Alkyd Floor Enamel, Gloss
31......................Polyurethane, Moisture Cured, Clear Gloss
36......................Knot Sealer
39......................Primer, Latex, for Interior Wood
40......................Exterior, Latex High Build
42......................Textured Coating, Latex, Flat
43......................Interior Satin Latex, MPI Gloss Level 4
44......................Interior Low Sheen Latex, MPI Gloss Level 2
45......................Interior Primer Sealer
46......................Interior Enamel Undercoat
PAINTING 09 91 00 - 6
47......................Interior Alkyd, Semi-Gloss, MPI Gloss Level 5
48......................Interior Alkyd, Gloss, MPI Gloss Level 6
50......................Interior Latex Primer Sealer
51......................Interior Alkyd, Eggshell, MPI Gloss Level 3
52......................Interior Latex, MPI Gloss Level 3
53......................Interior Latex, Flat, MPI Gloss Level 1
54......................Interior Latex, Semi-Gloss, MPI Gloss Level 5
59......................Interior/Exterior Alkyd Porch & Floor Enamel, Low
Gloss
60......................Interior/Exterior Latex Porch & Floor Paint, Low
Gloss
66......................Interior Alkyd Fire Retardant, Clear Top-Coat (ULC
Approved)
67......................Interior Latex Fire Retardant, Top-Coat (ULC
Approved)
68......................Interior/ Exterior Latex Porch & Floor Paint, Gloss
71......................Polyurethane, Moisture Cured, Clear, Flat
77......................Epoxy Cold Cured, Gloss
79......................Marine Alkyd Metal Primer
90......................Interior Wood Stain, Semi-Transparent
91......................Wood Filler Paste
94......................Exterior Alkyd, Semi-Gloss
95......................Fast Drying Metal Primer
98......................High Build Epoxy Coating
99......................Sealer, Water-based, for Concrete Floors
101.....................Epoxy Anti-Corrosive Metal Primer
107.....................Primer, Rust-Inhibitive, Water-based
108.....................High Build Epoxy Coating, Low Gloss
113.....................Elastomeric, Pigmented, Exterior, Water-based, Flat
114.....................Interior Latex, Gloss
115.....................Epoxy-Modified Latex, Interior Gloss (MPI gloss level 6)
118.....................Dry Fall, Latex Flat
119.....................Exterior Latex, High Gloss (acrylic)
PAINTING 09 91 00 - 7
134.....................Galvanized Water Based Primer
135.....................Non-Cementitious Galvanized Primer
138.....................Interior High Performance Latex, MPI Gloss Level 2
139.....................Interior High Performance Latex, MPI Gloss Level 3
140.....................Interior High Performance Latex, MPI Gloss Level 4
141.....................Interior High Performance Latex (SG) MPI Gloss
Level 5
144.....................Latex, Interior, Institutional Low Odor / VOC, (MPI Gloss Level 2)
145.....................Latex, Interior, Institutional Low Odor / VOC, (MPI Gloss Level 3)
146.....................Latex, Interior, Institutional Low Odor / VOC, (MPI Gloss Level 4)
151.....................Light Industrial Coating, Interior, Water-based, (MPI Gloss Level 3)
153.....................Light Industrial Coating, Interior, Water-based, (MPI Gloss Level 4)
163.....................Exterior Water Based Semi-Gloss Light Industrial
Coating, MPI Gloss Level 5
164.....................Exterior, Water Based, Gloss, Light Industrial
Coating, MPI Gloss Level 6
H. Society for Protective Coatings (SSPC):
SSPC SP 1-82(R2004).....Solvent Cleaning
SSPC SP 2-82(R2004).....Hand Tool Cleaning
SSPC SP 3-28(R2004).....Power Tool Cleaning
SSPC SP 10/NACE No.2....Near-White Blast Cleaning
SSPC PA Guide 10........Guide to Safety and Health Requirements
I. U.S. National Archives and Records Administration (NARA):
29 CFR 1910.1000........Air Contaminants
J. Underwriter’s Laboratory (UL)
PART 2 - PRODUCTS
MATERIALS:
A. Conform to the coating specifications and standards referenced in PART 3.
Submit manufacturer’s technical data sheets for specified coatings and solvents.
PAINTING 09 91 00 - 8
PAINT PROPERTIES:
A. Use ready-mixed (including colors), except two component epoxies, polyurethanes, polyesters, paints having metallic powders packaged separately and paints requiring specified additives.
B. Where no requirements are given in the referenced specifications for primers, use primers with pigment and vehicle, compatible with substrate and finish coats specified.
C. Provide undercoat paint produced by the same manufacturer as the finish coats. Use only thinners approved by the paint manufacturer and use only to recommended limits.
D. VOC test method for paints and coatings is to be in accordance with
40 CFR 59 (EPA Method 24). Part 60, Appendix A with the exempt compounds’ content determined by Method 303 (Determination of Exempt Compounds) in the South Coast Air Quality Management District’s (SCAQMD) “Laboratory
Methods of Analysis for Enforcement Samples” manual.
PART 3 - EXECUTION
JOB CONDITIONS:
A. Safety: Observe required safety regulations and manufacturer's warning and instructions for storage, handling and application of painting materials.
1. Take necessary precautions to protect personnel and property from hazards due to falls, injuries, toxic fumes, fire, explosion, or other harm.
2. Deposit soiled cleaning rags and waste materials in metal containers approved for that purpose. Dispose of such items off the site at end of each day’s work.
B. Atmospheric and Surface Conditions:
1. Do not apply coating when air or substrate conditions are:
a. Less than 3 degrees C (5 degrees F) above dew point.
b. Below 10 degrees C (50 degrees F) or over 35 degrees C
(95 degrees F), unless specifically pre-approved by the COR and the product manufacturer. Under no circumstances are application conditions to exceed manufacturer recommendations.
c. When the relative humidity exceeds 85 percent; or to damp or wet surfaces; unless otherwise permitted by the paint manufacturer’s printed instructions.
2. Maintain interior temperatures until paint dries hard.
3. Do no exterior painting when it is windy and dusty.
PAINTING 09 91 00 - 9
4. Do not paint in direct sunlight or on surfaces that the sun will warm.
5. Apply only on clean, dry and frost-free surfaces except as follows:
a. Apply water thinned acrylic and cementitious paints to damp (not wet) surfaces only when allowed by manufacturer's printed instructions.
b. Concrete and masonry when permitted by manufacturer’s recommendations, dampen surfaces to which water thinned acrylic and cementitious paints are applied with a fine mist of water on hot dry days to prevent excessive suction and to cool surface.
INSPECTION:
A. Examine the areas and conditions where painting and finishing are to be applied and correct any conditions detrimental to the proper and timely completion of the work. Do not proceed with the work until unsatisfactory conditions are corrected to permit proper installation of the work.
GENERAL WORKMANSHIP REQUIREMENTS:
A. Application shall be by brush. Spray application only upon acceptance from the COR in writing.
B. Protect work at all times. Protect all adjacent work and materials by suitable covering or other method during progress of work. Upon completion of the work, remove all paint and varnish spots from floors, glass and other surfaces. Remove from the premises all rubbish and accumulated materials of whatever nature not caused by others and leave work in a clean condition.
C. Remove and protect hardware, accessories, device plates, lighting fixtures, and factory finished work, and similar items, or provide in place protection. Upon completion of each space, carefully replace all removed items by workmen skilled in the trades involved.
D. When indicated to be painted, remove electrical panel box covers and doors before painting walls. Paint separately and re-install after all paint is dry.
E. Materials are to be applied under adequate illumination, evenly spread and flowed on smoothly to avoid runs, sags, holidays, brush marks, air bubbles and excessive stipple.
F. Apply materials with a coverage to hide substrate completely. When color, stain, dirt or undercoats show through final coat of paint, the surface is to be covered by additional coats until the paint film is of uniform
PAINTING 09 91 00 - 10
finish, color, appearance and coverage, at no additional cost to the
Government.
G. All coats are to be dry to manufacturer’s recommendations before applying succeeding coats.
SURFACE PREPARATION:
A. General:
1. The Contractor shall be held wholly responsible for the finished appearance and satisfactory completion of painting work. Properly prepare all surfaces to receive paint, which includes cleaning, sanding, and touching-up of all prime coats applied under other
Sections of the work. Broom clean all spaces before painting is started. All surfaces to be painted or finished are to be completely dry, clean and smooth.
2. See other sections of specifications for specified surface conditions and prime coat.
3. Perform preparation and cleaning procedures in strict accordance with the paint manufacturer’s instructions and as herein specified, for each particular substrate condition.
4. Clean surfaces before applying paint or surface treatments with materials and methods compatible with substrate and specified finish.
Remove any residue remaining from cleaning agents used. Do not use solvents, acid, or steam on concrete and masonry. Schedule the cleaning and painting so that dust and other contaminants from the cleaning process will not fall in wet, newly painted surfaces.
B. Zinc-Coated (Galvanized) Metal, Surfaces Specified Painted:
1. Clean surfaces to remove grease, oil and other deterrents to paint adhesion in accordance with SSPC-SP 1 (Solvent Cleaning).
2. Spot coat abraded and damaged areas of zinc-coating which expose base metal on hot-dip zinc-coated items with MPI 18 (Organic Zinc Rich
Coating). Prime or spot prime with MPI 134 (Waterborne Galvanized
Primer) or MPI 135 (Non-Cementitious Galvanized Primer) depending on finish coat compatibility.
PAINT PREPARATION:
A. Thoroughly mix painting materials to ensure uniformity of color, complete dispersion of pigment and uniform composition.
PAINTING 09 91 00 - 11
B. Do not thin unless necessary for application and when finish paint is used for body and prime coats. Use materials and quantities for thinning as specified in manufacturer's printed instructions.
C. Remove paint skins, then strain paint through commercial paint strainer to remove lumps and other particles.
D. Mix two (2) component and two (2) part paint and those requiring additives in such a manner as to uniformly blend as specified in manufacturer's printed instructions unless specified otherwise.
E. For tinting required to produce exact shades specified, use color pigment recommended by the paint manufacturer.
APPLICATION:
A. Start of surface preparation or painting will be construed as acceptance of the surface as satisfactory for the application of materials.
B. Unless otherwise specified, apply paint in three (3) coats; prime, body, and finish. When two (2) coats applied to prime coat are the same, first coat applied over primer is body coat and second coat is finish coat.
C. Apply each coat evenly and cover substrate completely.
D. Allow not less than 48 hours between application of succeeding coats, except as allowed by manufacturer's printed instructions, and approved by
COR.
E. Apply by brush. Spray application for new or existing occupied spaces only upon approval by acceptance from COR in writing.
1. Apply painting materials specifically required by manufacturer to be applied by spraying.
2. In new construction and in existing occupied spaces, where paint is applied by spray, mask or enclose with polyethylene, or similar air tight material with edges and seams continuously sealed including items specified in “Building and Structural Work Field Painting”; “Work not
Painted”; motors, controls, telephone, and electrical equipment, fronts of sterilizes and other recessed equipment and similar prefinished items.
F. Do not paint in closed position operable items such as access doors and panels, window sashes, overhead doors, and similar items except overhead roll-up doors and shutters.
PRIME PAINTING:
A. After surface preparation, prime surfaces before application of body and finish coats, except as otherwise specified.
PAINTING 09 91 00 - 12
B. Spot prime and apply body coat to damaged and abraded painted surfaces before applying succeeding coats.
C. Additional field applied prime coats over shop or factory applied prime coats are not required except for exterior exposed steel apply an additional prime coat.
D. Metals except boilers, incinerator stacks, and engine exhaust pipes:
1. Zinc-coated steel and iron: MPI 135 (Non-Cementitious Galvanized
Primer).
EXTERIOR FINISHES:
A. Steel and Ferrous Metal (Bollards):
1. Two (2) coats of MPI 94 (Exterior Alkyd, Semi-Gloss) // on exposed surfaces, except on surfaces over 94 degrees C (201 degrees F).
PAINT COLOR:
A. Color and gloss of finish coats is to match existing.
B. Coat Colors:
1. Color of priming coat: Lighter than body coat.
2. Color of body coat: Lighter than finish coat.
3. Color prime and body coats to not show through the finish coat and to mask surface imperfections or contrasts.
PROTECTION CLEAN UP, AND TOUCH-UP:
A. Protect work from paint droppings and spattering by use of masking, drop cloths, removal of items or by other approved methods.
B. Upon completion, clean paint from other surfaces and items not required to be painted of paint drops or smears.
C. Before final inspection, touch-up or refinished in a manner to produce solid even color and finish texture, free from defects in work which was damaged or discolored.
- - - E N D - - -
| SECTION 09 91 00 PAINTING |
| PART 1 - GENERAL |
| 1.1 DESCRIPTION |
| 1.2 RELATED WORK |
| 1.3 SUBMITTALS |
| 1.4 DELIVERY AND STORAGE |
| 1.5 QUALITY ASSURANCE |
| 1.6 REGULATORY REQUIREMENTS |
| 1.7 safety and health |
| 1.8 APPLICABLE PUBLICATIONS |
| PART 2 - PRODUCTS |
| 2.1 MATERIALS: |
| 2.2 PAINT PROPERTIES: |
| PART 3 - EXECUTION |
| 3.1 JOB CONDITIONS: |
| 3.2 inspection: |
| 3.3 general workmanship requirements: |
| 3.4 SURFACE PREPARATION: |
| 3.5 PAINT PREPARATION: |
| 3.6 APPLICATION: |
| 3.7 PRIME PAINTING: |
| 3.8 EXTERIOR FINISHES: |
| 3.9 PAINT COLOR: |
| 3.10 PROTECTION CLEAN UP, AND TOUCH-UP: |