This document contains responses to questions from potential offerors regarding a solicitation for developing private and semi-private bed spaces at a Veterans Affairs medical center. The solicitation will be issued as a 100% set-aside for Service-Disabled Veteran-Owned Small Businesses to renovate pods 4B and 4C at the John L. McClellan Veterans Memorial Hospital in Little Rock, Arkansas. The construction cost is estimated between $5-10 million. The performance period is 485 days from the notice to proceed. Proposals are due around September 1, 2021 in response to a request for proposals expected to be issued on August 1, 2021. The contract award is anticipated within 30 days after receipt of proposals. The document provides clarification to questions on medical gas and alarm systems, fire protection, telecommunications, and other technical aspects of the work.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFI 79 DRAWING 4.pdf | ||
| PRE-BID RFIS COMPLETE.docx | DOCX document | |
| RFI 79 DRAWING 3.pdf | ||
| RFI 79 DRAWING 1.pdf | ||
| nLight IECC 2018 Applications Guide.pdf | ||
| RFI 79 DRAWING 2.pdf | ||
| AMENDMENT 36C25621R0145 0002.docx | DOCX document | |
| SITE VISIT SIGN IN SHEET.pdf | ||
| AMENDMENT 36C25621R0145 0001.docx | DOCX document | |
| P07 WAGE DETERMINATION AR20210032 04-02-2021.pdf | ||
| 59818103 Specifications.pdf | ||
| EXHIBIT C CONTRACTOR EVALUATION FORM CONSTRUCTION SAFETY v2.docx | DOCX document | |
| SOW - revised.docx | DOCX document | |
| EXHIBIT A PERFORMANCE RELEVANCY SURVEY v2.docx | DOCX document | |
| 598918103 Drawings 2 of 2.pdf | ||
| 36C25621R0145.docx | DOCX document | |
| 59818103 BOD.pdf | ||
| 598918103 Drawings 1 of 2.pdf | ||
| EXHIBIT B Past and Present Performance Questionnaire.docx | DOCX document |
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
| PROJECT # | 598-18-103 | |
| Develop Private/Semi-Private Bed Spaces | ||
| Little Rock, AR |
DATE: August 10, 2021
ITEM 1 – Bidding Requests For Information
| # |
| Reference |
| Question |
| Answer |
1.
| Is the commissioning to be done by the contractor or the VA? |
| See Specification Section 01 91 00 Part 1.8, B.,1. |
2.
| There is a specification for temporary signage but no specification for final signage. |
| Final Signage by the VA Media Department. |
VA Medical Media department to remove existing, and reinstall upon project completion.
3.
| Are all patient lifts to be removed and thrown away or is the VA requiring to save and store? |
| See note 9 on ACD104-1, ACD104-2. To be turned over to the VA. |
4.
On Beta.Sam.Gov in the description of the project it states the anticipated contract award date will be approximately 30 calendar days after receipt of proposals. Can you verify this will happen. The VA is notoriously slow about releasing the results making it difficult to bid other projects because you have used up all bonding waiting on a answer.
Award will be made once evaluations and reviews are completed. We do anticipate award to be made approximately 30 days after the closing date of the solicitation.
| 5. |
| finish legend on I603 |
| The finish legend on I603, designates P-4 as Stonhard Stonglaze VSR. The properties and |
characteristics of the VSR are the same as the characteristics of the Sherwin Williams water based catalyzed epoxy paint in P-1,2,3, & 5. The charts below identify the VSR characteristics and the Pro Industrial characteristics. High gloss is the VSR finish and that will not match with the eggshell finish of the Sherwin Williams catalyzed epoxy when installed on adjacent walls.
Furthermore, adding the P-4 VSR complicates the project because ordinary painters do not have access to this type of product. Additionally, VSR only comes in 6 standard color options. The odds are low that they will be a close match to the adjacent Sherwin Williams paint color. For bidding purposes, will the VA please standardize the epoxy wall paint by converting the P-4 walls to P-3?
Bid as drawn/specified.
| 6. |
| Sheets H104-1 & H104-2 |
| Sheets H104-1 & H104-2 are listed on the table of contents (G002) but are not in the set. Please confirm that they were intentionally omitted or mistakenly left out of the project? |
| Drawings are to be removed from Sheet Index. |
| 7. |
| Spec section 22 63 00-7 para 2.3C |
| At the prebid walkthrough, it was observed that existing med gas zone valves do not have gauges and therefore are not in compliance with NFPA code 5.1.4.6.4 subpara 1311.6.3 Indicators. The code states that medgas zone valves w/ gauges shall be provided on station outlet/inlet side of each zone valve. When we corrected OR 2F’s medgas deficiencies we installed zone valves with gauges. Spec section 22 63 00-7 para 2.3C states to provide 1/8" NPT gauge port for a 2" diameter monitoring gauge downstream of the shutoff valve. The drawings do not identify gauges downstream from the shutoff valves. Will we be required to bring existing conditions up to code by installing gauges downstream of the valves? |
| Per NFPA 99 Section 5.1.4.6.4, the existing zone valves will need to be replaced with one with gauges on downstream (medical gas and oxygen) and upstream (vacuum). |
| 8. |
| Spec section 22 63 00-8 para 2.4.c |
| Spec section 22 63 00-8 para 2.4.c states that each valve shall have a gauge upstream of the valve inside the valve box. The current zone valve boxes appear to not have a gauge upstream or downstream. Does the VA want the contractor to install a gauge upstream (on the patient side) per this specification and also per NFPA 5.1.4.6.4 subparagraph 1311.6.3? |
| Per NFPA 99 Section 5.1.4.6.4, the existing zone valves will need to be replaced with one with gauges on downstream (medical gas and oxygen) and upstream (vacuum). |
9.
| There are two area alarm panels in each pod (or at least the pod we visited during the site visit). The existing panels and sensors have been upgraded about ten years ago. The alarms and their associated sensors will be obsolete in the next five years or sooner. Does the VA want to replace this system now while the project is under construction? |
| Bid per construction documents. Alarm panel replacement not part of this project. |
| 10. |
| glazing spec section 1.4 paragraph D |
| The glazing spec section 1.4 paragraph D calls for windborne requirements. The storefront system is not impact resistant and the insulated glass make up is not for windborne requirements. Spec Section 08 43 13-6 para 2.1b.3. calls for large missile test windborne rating glass however 2.3A calls for Kawneer Trifab VG 451T which is not missile rated nor windborne debris rated glass. Please clarify if windborne requirements are to be included or if the contractors should use the Kawneer Trifab VG 451T as their basis of design for all glass in the project. |
| Window/glazing product provided by VA. |
Bid as drawn/specified.
| 11. |
| specifications page 09 67 23.20 |
| The EPY-1 system in the product properties column of the finish legend calls for a three component troweled system. The style and color column call for a chip broadcast system. Trowel and broadcast are two different application methods. The specifications page 09 67 23.20 call for a four component epoxy system which differs from the finish legend's three component system. Neither of these systems call for a chemically resistant urethane nor polyaspartic top coat and both systems are a single flake broadcast system. Both systems differ from the VA standard double flake broadcast system which includes a chemically resistant top coat. A single flake system will not hold up to the traffic and wear that this shower floor will experience. Will the VA please clarify the use and need of the double flake broadcast system with chemically resistant topcoat in lieu of the three component system as specified in the drawings and four component system as specified in the specs? |
12.
The shower floors should really be a troweled quartz system. A troweled quartz system will provide the best durability and the best moisture resistance of the epoxy options. Will the VA consider changing to a RES-3 and pursuing the troweled quartz option?
| 13. |
| Note "B" on sheet ETD104-1 and 2 |
| In regards to Note "B" on sheet ETD104-1 and 2. Triple S is a local certified installer of this system. Is it acceptable to contract with Triple S to perform this work, in lieu of the out of state contractor (Liberty IT Systems) listed in the notes? |
| R.S.: Triple S is the point of contact to perform this work. (NOT Liberty IT Systems) |
14.
| What fire stopping product does the VA prefer the contractor to use for penetrations? |
| Products cannot be sole sourced. If they are, they must allow for an equal that is approved by the VA. |
The VA prefers color red on all firestopping products.
Red Intumescent fire caulk with a 3-hour rating is required
15.
| What is the realistic period of time that the VA anticipates turnover between final certification of the first pod in phase one and mobilization of the second phase in the next pod? |
| Recent ward relocations have taken 2 weeks with adequate planning. Contractor should estimate 30 days. |
16.
| The solicitation PoP is 485 days. If the contractor schedules 400 days of construction and budgets for general conditions for 400 days, and the construction runs longer then 400 days due to delays borne from the VA, contract or design modifications, will the VA issue a contract modification to provide the GC more general conditions for the extra period of time that the contractor was onsite even though that extension may still be within the 485 day period of performance? |
| Regardless of the Contractor’s estimated schedule the contract will have a POP of 485 days. |
17.
| Is the VA responsible for the storage of the existing RTLS system during construction? |
| Yes. Contractor will turn equipment into VA for storage. |
18.
| Is the VA responsible for contracting with the RTLS contractor under the sustainment contract or is the Prime Contractor responsible for the RTLS subcontractor? |
| GC will remove all devices and turn into the VA for storage. VA will coordinate a remapping of all devices for the new layout. GC will then be responsible for reinstallation of devices at all new location. – Please note many devices will not be reinstalled as patient room count is decreasing. |
| 19. |
| ET104-2 general note 1 |
| ET104-2 general note 1 states that the Prime Contractor shall subcontract with MST Group or equal. Allegedly, MST Group may be out of business. If this is the case, who is the subcontractor that they used to install the system wide nurse call? |
| MST group is now dissolved. GC to contact Triple S to coordinate removal and reinstallation of devices. |
| 20. |
| EFD104-2, note B |
| Refer to EFD104-2, note B. If the fire alarm system is down overnight will the contractor be required to post a continuous fire watch guard during nighttime hours? |
| Yes. |
21.
| Will the VA allow the site superintendent to carry one of the additional duties, either SSHO or Quality Control Manager? |
| Superintendent can fill the role of the SSHO. The QAQC role must the individuals’ sole position. |
22.
| Does the VA want a single individual to fill the roles of SSHO, QC, and Site Superintendent? |
| Superintendent can fill the role of the SSHO. The QAQC role must the individuals’ sole position. |
| 23. |
| sheet EL104-1.1 |
| Please refer to sheet EL104-1.1. in the nurse alcove 4B119A there is a light fixture labeled F10. F10 is not identified anywhere in the lighting fixture schedule on E600. Will the VA please clarify what type of light F10 is suppose to be? |
| 24. |
| ET104 1.1 general note D.a |
| Refer to ET104 1.1 general note D.a. It states television sets are to be procured from VA approved single source..... Please confirm that the VA is to purchase these televisions per the furniture and accessory finish schedule? |
| GC to provide and install. |
25.
Which contractor, if other than Guldmann (name and POC please) has the current maintenance contract on the existing patient lift systems on campus?
BAE: Basis-of-Design is Guldmann. Request for substitution must be made and must be approved by the VA COR.
Review requirements for request for substitutions and deviations from Basis-of-Design.
26.
| If the contractor has to turn off medgas upstream of the current valves to replace the 4b and 4c valves with new valves and gauges can they do so without shutting down the medgas to the entire campus? |
| BAE: Based on existing drawings and field survey, it appears that there are no isolation valves upstream of the valve box. The area that the medical gas system serves will need to be temporarily shut down. The contractor will need to install new locking type isolation valves near the risers. |
27.
| Is there a medgas isolation valve that services the entire pod or 4th floor upstream of the 4b and 4c isolation valves? |
| BAE: Based on existing drawings and field survey, it appears that there are no isolation valves upstream of the valve boxes on 4b and 4c. |
28.
| Does the VA want the ASSE 6030 verifier to be a third party person separate from the company that installed the medgas piping? |
| BAE: Yes, per spec 22 63 00 section 1.5.D, testing shall be performed by a party other than the installing contractor. |
29.
| Does the VA want the contractor to provide engineer stamped drawings with calculations for the new fire sprinkler layout? |
| BAE: Yes, per spec 21 13 13 section 1.3.A.1, the contractor shall perform hydraulic calculations in accordance with NFPA 13 |
| 30. |
| Page I104-6, finish general note 3 & 4 |
| Page I104-6, finish general note 3 & 4 appears to be exclusive note 2. Is this the case? |
| 1) General Note E. applies to floors to be removed and replaced with new. |
2)Key note 2 applies to rooms where there will be NO changes to existing flooring. Applies to I104-5 and I104-6.
| 31. |
| Page I406-6 note E1 |
| Page I406-6 note E1 refers to mastic abatement. H104-1 and H104-2 were excluded from the drawings. Is there any abatement in this project? |
| Per environmental testing report, no ACM was discovered. No mastic abatement. |
32.
| If there is abatement, will the VA please post the appropriate documents for bidding purposes. |
| Per environmental testing report, no ACM was discovered. Sheets were eliminated from set. |
| 33. |
| Note C on I406 |
| Note C on I406 states floor leveling as necessary based on sub-floor condition. A104-1.1 – Gen note F – “all” sub-floors requiring new finishes shall be entirely skim coated to a smooth and level finish. A104-2.1 same note adds that skim should be ¼” thickness. |
The condition of the subfloor was not visible during the walk through. The only accurate way to account for floor leveling is to add unit pricing as a CLIN item. This prevents the VA from paying for leveling compound and shonox that was not applied. Accounting for 20K square feet of 1/4" leveling will cost the VA over $100K and is wasteful and unnecessary. Will the VA please provide a line item in the bid sheet summary that allows for unit pricing of floor patch and leveling by the square foot?
No CLIN will be added for floor leveling. Offerors will include floor leveling in the base bid pricing.
34.
| Contracting officers from other agencies have told us they don't have time to fill out CAVHS's repetitive past performance paperwork. Their sentiment is that they are at the end of the fiscal year, they're overworked and understaffed. Will CAVHS contracting staff hold this against the contractor if they don't fill out the paperwork? |
| In the event no PPQs are received for any offeror, Exhibit A, CPARS and other knowledge of past performance will be evaluated as indicated in the solicitation. |
35.
| Can the contractor resubmit a past performance review from another contracting officer that was recently submitted within the last few months on a different project? |
| PPQs should come directly from the reviewer and not from the offeror. |
36.
| The contractor has no way of knowing if the agency contracting officer or private industry customer actually submits the PPQ on their behalf. Will CAVHS accept a CPARS in the proposal packet in lieu of the PPQ if the contracting officer refuses to fill out the paperwork? |
| CPARS will be evaluated as indicated in the solicitation. |
37.
| The solicitation instructs the contractor to not include copies of the letters or questionnaires in the proposal. Does this include the exhibit A? Should exhibit A be included in the contractor's factor 2 portion of the proposal? |
| Exhibit A is not considered a letter or questionnaire. Exhibit A shall be included in Past Performance. |
| 38. |
| EL104-1.1 & 1.2 and 2.1 |
| The drawings and details issued for the lighting control devices shown on EL104-1.1 & 1.2 and 2.1 are unclear. Will the VA provide more details on the lighting control devices? |
| 39. |
| Sheet A412 detail 3 |
| Sheet A412 detail 3 calls out "Curved 3-Form Acrylic Panel (ACR-2). This call-out is not defined on the room finish legend (I603) nor is it identified in the 10 26 00 specification. All other acrylic paneling listed in the finish schedule is by Lumicor. Will the VA please clarify ACR-2 and provide a specification and basis of design for it? |
| 1/2” thick Acrylic panels are AC-1 (Lumicor). Clarifications to drawings: |
1. Elevation 3/A412: curved panel should read LUMICOR (not “3-Form”), and AC-1 (not ACR-2).
2. Elevation 1/A412A: Note “temporary acrylic screen by “Corona Group, Inc., or VA approved equal” should be pointing to the elevations of the screens (where chairs indicated), not to the section it is currently pointing to.
3. There is no ACR-2 (only ACR-1).
4. Sections 2 & 3/A513: 1/2” acrylic panel is LUMICOR (not 3-FORM).
5. Specifications and installation instruction can be obtained through Lumicor.
40.
| Currently there are no details describing the mounting of ACR-1. Will the VA please provide a section showing the mounting details above the headwall buildouts for ACR-1? |
| Elevation 3/A412A: Acrylic privacy screen should be ACR-1 in lieu of AC-1. Mounting of back panel is the same as reception desk (section detail 2/A513 and 4/A513). |
Detail for Privacy Screens at reception desk are on detail 3/A513. Follow manufacturers installation instructions.
41.
| A previous project at the VA has revealed a major discrepancy between the manufacturer’s reps, the A&E, and the installers as to the best method of bonding the ACR panels to each other. Does the VA want the seams between the ACR panels to be mechanically seamed, epoxied, or caulked? |
| 1. Solid Surface installations (vertical & horizontal) to have invisible seams. |
2. ACR-1 (above headwalls) do not require seaming- standard sheet size is 4’x 8’. Panels above headwalls are approx.. 3’-4” x 5’-9”.
3. AC-1 (nurse station) do not require seaming- standard sheet size is 4’ x 8’. None of the sheets detailed are larger than this.
42.
| On A412 et al, how does the contractor identify which of the elevated acrylic screens (hatched with the plus pattern) are intended to be permanent and which are intended to be temporary “Acrylic Screen by Corona Group”? |
| West side reception counter (Elevation 3/A412) has the temporary acrylic screens by “Corona Group”. All other acrylic screens are permanent. |
| 43. |
| Sheet A412 detail 3 |
| Sheet A412 detail 3 calls out "Temporary Acrylic Screen by Corona Group Inc". Neither the temp screen nor the permanent screen are identified on the furniture legend. Is the temp screen and permanent screen in the contractor's scope of work or is the VA providing this? |
| The GC is responsible for providing and installing the temporary screens. |
Temporary Screens AND Permanent Screen panels are shown on Room Finish Legend and Elevations.
44.
| Will the VA please provide a specification for the acrylic screens? |
| AC-1 (1/2” thick acrylic panels): Basis-of-Design is “Lumicor”. Information is on the Room Finish Legend. |
ACR-1 (wall protection above patient bed headwalls): Basis of Design is “Lumicor”. Information is on the Room Finish Legend.
Contact Lumicor rep for specifications and installation instructions.
| 45. |
| A412 detail 3 |
| The temp screen is identified on A412 detail 3. Detail 3 has a callout to look at A513 detail 4. Detail 4 does not show the temp screen as indicated in detail 3. How is the temp screen mounted to the transaction counter? |
| Temporary screens on this transaction counter are clamped to the transaction counter. Install per “Corona Group” instructions. |
46.
| If the bids are to be emailed directly to Felicia Lovelady and the hard copies delivered to Bradley Martin, must the hard copies arrive before the due date and time or can they arrive within a certain time after the due date so long as the bid bond arrives before the due date and time? |
| Hard copies and electronic copies must arrive before the due date and time. |
47.
Although we know that Bradley Martin’s address is not at JLM, can the government confirm that hard copy proposals and bid bonds should be mailed to the following JLM address:
Department of Veterans Affairs Central Arkansas Veterans Healthcare System Network Contracting Office 16 Attn: Bradley Martin, Contracting Officer 4300 W 7th St Little Rock, AR 72205 Hard Copies of proposals and bid bonds must be received by closing date and time of the solicitation at:
Department of Veterans Affairs Central Arkansas Veterans Healthcare System Network Contracting Office 16 Attn: Bradley Martin, Contracting Officer Building 41, Room 209 North Little Rock, AR 72114
48.
| Does the government permit the use of past performance from the offerors SBA Mentor-Protégé mentor company and/ or an official teaming partner? |
| Yes as long as documentation confirming a teaming agreement or mentor protégé arrangement is included in the package. |
49.
| Does the government require a copy of the offerors current VETS-4212 to be submitted within the response package? If so, which section should the VETS-4212 be placed? |
| Please include in Volume I, it will not count against the page limit. |
50.
| Will the government permit utilizing “a competent 30 hour OSHA certified superintendent” from the offerors SBA Mentor-Protégé mentor company and/ or an official teaming partner? |
| Yes. As long as they are the full-time superintendent |
51.
Will the VA please Verify cable count for Data/Voice Outlet Locations. It is Assumed to be 2D/2V per previous VA standards. Will the VA please clarify?
| 52. |
| Sheet E401 – General Note H |
| Sheet E401 – General Note H: “Refer to Project 598-19-114, MTS Group Submittal for all Nurse Call Electronics and Low Voltage Terminations, Cat6 POE Cabling Required.” Verify need for Cat6 Data provisions to Patient Camera locations in this proposal or is this to be covered by the Nurse Call Installer? |
| 53. |
| Basis of Design – Page 37 |
| Basis of Design – Page 37: “Four Data and voice ports will be installed in headwalls and at locations per Patient Room Design Standards.” Will the VA please Verify need for Cat6 Data/Voice provisions to Patient Headwall Locations in this proposal. |
| 54. |
| Basis of Design – Page 37 |
| Basis of Design – Page 37: “Wiring will originate from the Patient Headwalls and be routed into Telephone Closets and Coiled. Terminations and additional equipment in Telephone Closets is not included in contract |
55.
Please clarify expectations for Telephone Closet Terminations. Will all new Cat6 cables for VoIP system be terminated on Patch Panels or left coiled above ceiling?
56.
It was stated in the walkthrough that this project is to be broken up into multiple phases. Please clarify the cabling expectations and timeline of these phases. Should the construction team assume the patient rooms are to be turn-key for all LV/Systems work per each phase?
57.
| This wing was Identified as a COVID wing during the Site walkthrough. Will this area be open to the patients for the full duration of the project? |
| The COVID wing is only open to COVID patients. At the time we are ready to start construction on this wing patient will be relocated to a swing ward and this ward will receive a terminal clean prior to contractor access. |
58.
| Will the VA please Clarify ICRA level inside the pods? |
| On drawings. Coordinate with VA COR. |
59.
| Will an Above-Ceiling permit be required for this project and issued by the VA or covered by the GC? |
| None of the VA required permits have an associated cost for the contractor. |
60.
| Will existing Data Racks be utilized in the COMMS Closets or will New Racks need to be provided in this proposal? |
| Existing data racks will be utilized. |
| 61. |
| Sheet ET104-1.3 – Key Note #2 |
| Sheet ET104-1.3 – Key Note #2: “New (48) Cisco VLAN Switch” |
62.
Please clarify requirements for new Network Switch. Will Redundant power supply be necessary for this model?
63.
Are there any Fiber Optic or backbone cabling runs associated with this project? If so, please specify approximate length, Cable Type and Connector Style?
| 64. |
| Specifications 27 15 00-5 |
| Specifications 27 15 00-5: “Provide wall outlet with a stainless-steel face plate and sufficient ports…” Please verify that all faceplates will be stainless steel? |
| 65. |
| 01 00 00, 1.2.D – Page 25 |
| 01 00 00, 1.2.D – Page 25 - Before placement and installation of work subject to tests by testing laboratory retained by Department of Veterans Affairs, the Contractor shall notify the COR in sufficient time to enable testing laboratory personnel to be present at the site in time for proper taking and testing of specimens and field inspection. Such prior notice shall be not less than three work days unless otherwise designated by the COR. What testing will be VA testing lab be responsible for? |
| 66. |
| 01 00 00, 1.3.A Item V.A Page 26 |
| 01 00 00, 1.3.A Item V.A Page 26 - PIPE TESTING: Perform a pipe wall thickness test to identify any weaknesses or leaks in the existing sprinkler piping system within the project area. Follow the procedures and calculations for the minimum required wall thickness as defined by ASME and Industry standards. Use internal design pressure of 200 psi as indicated in the hydrostatic test section in NFPA 25. Provide written reports and documentation illustrating all finding to the VA/COR. This appears to be a new requirement at the VA as we have not seen it before. Does the VA want this as specified or should the contractor disregard it? |
| BAE: Contractor to follow the construction specification and perform a wall thickness test to meet scope of work. Provide VA/COR all needed documentations. |
67.
| Should the contractor submit as-builts red-lined on drawings, in autocad, or both? |
| BAE: Autocad, marked up PDF’s for reference. |
68.
| Will Bancroft require the use of P6 for submittal exchange? |
| Submittal Exchange will be contracted through the A/E. Contractor will use SE as required. |
69.
| Will the contractor and construction team have access to facility restrooms inside the work site or in an adjacent hallway? |
| Contractor will be able to designate one restroom inside the construction area for contractor use. |
70.
| Will the VA provide the construction team with an office space inside the construction site or close by inside the facility to avoid funding an exterior worksite trailer? |
| Contractor should be able to use space inside the construction area for an onsite office. 4B101 and 4C162 are conference rooms inside the construction area that are not receiving any level of construction. |
| 71. |
| 01 00 00, 1.22 Page 41 |
| 01 00 00, 1.22 Page 41 - The contractor shall coordinate with the work of installation of telephone equipment by others. This work shall be completed before the building is turned over to VA. Will the VA please clarify what telephone work they are referring to and what is the construction team’s extent of involvement with this work? |
| 72. |
| 01 00 00, 1.25 G Page 44 |
| 01 00 00, 1.25 G Page 44 – Gov furnished property - Furnish supervision of installation of equipment at construction site by qualified factory trained technicians regularly employed by the equipment manufacturer. Is the contractor responsible for monitoring the assembly of government furnished equipment if the furniture legend states VV? |
| NO, if by VV (VA provided, VA installed). |
Contractor not responsible for monitoring the assembly of government furnished and installed equipment.
| 73. |
| 01 35 26,1.9.B Page 84 |
| 01 35 26,1.9.B Page 84 - A Certified Safety Professional (CSP) with specialized knowledge in construction safety or a certified Construction Safety and Health Technician (CSHT) shall randomly conduct a monthly site safety inspection. The CSP or CSHT can be a corporate safety professional or independently contracted. The CSP or CSHT will provide their certificate number on the required report for verification as necessary. This appears to be a new requirement or an excerpt from the USACE specs. Does the VA want the contractor to provide this person in their budget or can the onsite SSHO suffice for this position? |
| Onsite SSHO suffice for this position |
| 74. |
| 01 45 00, 3.4.C Page 121 |
| 01 45 00, 3.4.C Page 121 states - These individuals or specified technical companies are directly employed by the General Contractor and cannot be employed by a supplier or subcontractor on this project are employees of the prime or subcontractor; be responsible to the CQC System Manager; be physically present at the construction site during work on the specialized personnel’s areas of responsibility; have the necessary education or experience in accordance with the Experience Matrix listed herein. The requirement to have these individuals on the GC’s payroll staff is excessive and unwarranted. Can the QC personnel for the trades be employed by the subcontractors for these trades? |
| GC can use their own QAQC personnel to meet this requirement. However, this must be their only job responsibility. |
| 75. |
| 09 91 00 – 3.14 Page 448 |
| 09 91 00 – 3.14 Page 448 – Identity Painting - Can sticker labels be used in lieu of painting the labels on the items? |
| Labels will vary by what is being identified – i.e. Fire walls need to be stenciled on the wall above ceiling |
| 76. |
| 11 73 00 – 1.3.C Page 485 |
| 11 73 00 – 1.3.C Page 485 – After installation, an inspector of record must inspect the system to ensure compliance with VA Specs and inspector must be a registered structural engineer in the state of Arkansas. Does the VA want this inspector to be a third party inspector or can it be an inspector that works for the patient lift system company or manufacturer? |
| Third Party inspector required. |
| 77. |
| SF104-1 – Gen note B |
| SF104-1 – Gen note B – contractor to xray slab prior to core drilling any penetrations. Note D – infill all abandoned pipe openings with like existing materials. Does the VA know if there are post tension cables in the slab of the 4th floor pods B & C? |
| The original structural design drawings indicate a composite slab on metal deck with welded wire reinforcing. Post tension cables are not indicated on the original drawings. |
78.
| What if any, will be the VA’s intention if an x-ray identifies an obstacle in the path of a core drill? |
| Notify COR of obstacle. Architect will provide direction upon notification of any obstacles. |
79.
| If there are post tension cables, will the VA please provide the structural as-built drawings that identify the location of the cables in an amendment? |
| VA to provide as built drawings. |