Questions and Answers - 36C25621Q1402.docx
DOCX document 20 KB Posted
- Attached to
- 6625-- Centrak Environmental Monitoring system
- Solicitation number
- 36C25621Q1402
About this file
This document contains questions and answers related to solicitation number 36C25621Q1402 issued by the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 16. The solicitation seeks proposals for a Centrak compatible environmental monitoring system to be installed at the Michael E. DeBakey Veteran Affairs Medical Center. Acceptable alternative equivalent products to Centrak will be considered so long as all technical specifications are met. The period of performance is 240 days with activities required to begin within 5 business days of award.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Questions and Answers - 36C25621Q1402 v2.docx | DOCX document | |
| Updated RFQ - 36C25621Q1402.docx | DOCX document | |
| 36C25621Q1402.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
36C25618Q0549
MEDVAMC Centrak Compatible Environmental Monitoring System Questions and Answers
1. The Michael E. DeBakey Veteran Affairs Medical Center (MEDVAMC) Network Contracting Office (NCO) 16 received 2 questions in response to Request for Quotation (RFQ) 36C25621Q1402, Centrak Compatible Environmental Monitoring System.
2. Please see below detailed Vendor questions and NCO 16’s respective answers accordingly.
Question #1: Will you accept bids for alternative but equivalent products to Centrak?
The proposed equipment must meet all technical specifications outlined in the statement of objectives.
Question #2: 1. Section 4 states a 240 day Period of Performance, but Section B.3 states that delivery and installation is required within 60 days after award. Can the Government please clarify what the Period of Performance should be?
The SOO states 240 days for overall performance. Section B.3 was an error and has been updated. Activities must begin within 5 business days of award.
The deadline for questions was 15 July 2021 at 12:00pm CST. No other questions will be accepted.