36C25519R0007-0001000.docx
DOCX document 42 KB Posted
- Attached to
- Replace Mechanical Systems in B2 657-17-184JB Federal contract opportunity
- Solicitation number
- 36C25519R0007
About this file
36C25519R0007 0001 36C25519R0007 0001.docx
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 36C25519R0007-0001001.pdf | ||
| 36C25519R0007.docx | DOCX document | |
| Drawings_657-17-184JB_1of5_-_1_page.pdf | ||
| Drawings_657-17-184JB_4of5_-_11_pages.pdf | ||
| Drawings_657-17-184JB_3of5_-_13_pages.pdf | ||
| Drawings_657-17-184JB_5of5_-_10_pages.pdf | ||
| 2018-10-17_Bid_Specifications.pdf | ||
| Drawings_657-17-184JB_2of5_-_13_pages.pdf | ||
| 36C25519R0007-002.docx | DOCX document | |
| 36C25519R0007-001.docx | DOCX document | |
| 36C25519R0007-000.docx | DOCX document |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE
7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office.
is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER
16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer) 02-08-2019
657-17-184JB
36C255 Department of Veterans Affairs Network Contracting Office (NCO) 15 3450 S 4th Street Leavenworth
KS
66048 36C255 Department of Veterans Affairs Network Contracting Office (NCO) 15 3450 S 4th Street Leavenworth
KS
66048 To all Offerors/Bidders
36C25519R0007 01-09-2019
X X X ** HOUR & DATE for Receipt of Offers is EXTENDED to:
19 FEB 2019 3:00 pm CST X Request for Proposal for project 657-17-184JB Replace Mechanical Systems in Building 2, Jefferson Barracks, St. Louis Missouri.
The above cited solicitation is hereby amended as shown below:
A. The due date for proposals is extended to 19 FEB 2019 at 3:00 pm CST.
B. Answers to questions and other information from the site visit are provided in this amendment.
C. All other terms and conditions of the solicitation remain unchanged.
David P. Holden Questions and Answers for solicitation 36C25519R0007 Project 657-17-184JB STL VAHCS
Set #1 General Requirement Questions:
1. Do we have to have all dumpsters picked up daily? No, this is at your discretion, your means and methods are yours.
2. How many copies from all subs do we have to provide for the “Maintenance Manuals and Red Line Drawings?
· From specifications, section 01 00 00 paragraph 1.3 J. Submit O&M manuals under the applicable specification section, rather than under this section. Submit O&M data to the Resident Engineer aka COR. Unless indicated otherwise, submit three (3) copies of O&M manuals.
And
· Para 1.14 AS-BUILT DRAWINGS
· A. The contractor shall maintain two full size sets of as-built drawings which will be kept current during construction of the project, to include all contract changes, modifications and clarifications.
· B. All variations shall be shown in the same general detail as used in the contract drawings. To insure compliance, as-built drawings shall be made available for the COR review, as often as requested.
· C. Contractor shall deliver two approved completed sets of as-built drawings in the electronic version (scanned PDF) to the COR within 15 calendar days after each completed phase and after the acceptance of the project by the COR.
· D. Paragraphs A, B, & C shall also apply to all shop drawings.
3. Can work be performed after normal work hours? Yes, after coordination with the COR.
Electrical Questions:
1. Question……….. will the entire ceiling grid be removed / re-installed in the work area? Will all light fixtures and ceiling devices be removed and re-installed after grid / ceiling pads are re-installed?
· The existing ceilings are to be removed and replaced. Contractor is to carry 20% of the ceiling tile area with new tiles due to damage during removal and installation. See sheet M-001 Note 14. ESTABLISH PASSAGE CLEARANCES REQUIRED TO DELIVER, INSTALL AND ERECT ALL REQUIRED EQUIPMENT. IF STRUCTURES, EQUIPMENT AND SYSTEMS MUST BE ALTERED TO PROVIDE PASSAGE OF EQUIPMENT, THE CONTRACTOR SHALL RESTORE STRUCTURES, EQUIPMENT AND SYSTEMS TO THEIR ORIGINAL CONDITION AT TIHE CONTRACTOR'S EXPENSE; INCLUDING REMOVING AND REPLACEMENT OF ALL CEILING AS REQUIRED TO COMPLETE THE WORK.
2. Question……….. should electrical contractor include any labor/material to repair / re-lamp existing light fixtures that removed and re-installed in ceiling as part of the project?
· Yes, as needed. Light fixtures were recently installed.
3. Question……..Should electrical contractor include any labor/material to provide temporary lighting in the work area? Existing light fixtures will be removed as part of demolition.
· Yes, as needed.
4. Question……… Will mechanical contractor be required to provide temporary heat / cooling in the office areas during construction?
· Yes, when needed.
5. Question……… Does electrical contractor need to include labor/material to provide power and connection to any temporary heat/cooling?
· Yes.
Set #2
1. Looking at the insulation table on 23 07 11 – 18 I do not find the pipe sizes for the various systems to be insulated. Past experience would indicate that the first column is for 1” and smaller, the second column is for 1” thru 1-1/4”, the third column is for 1-1/2” thru 3”, and the fourth column is for 4” and larger. Please confirm.
· Yes first column is for piping under 1”, second column pipe between 1” and 1-1/4”, third column is for pipes 1-1/2” and 3” and the fourth column is for all piping 4” and above.
2. The table specifies that GH and GHR gets insulated outside. What about inside?
· Contractor to insulate GH and GHR inside with Mineral Fiber to the thickness’s identified for HWH and HWHR.
3. Do you intend the refrigeration piping to get insulated? There is no spec.
· YES, Contractor to insulate refrigerant piping with 1.5” flexible elastomeric foam insulation in non-plenum areas. Refrigerant piping routed in return plenums to be insulated with 1.5” Mineral Fiber similar to LPR.
4. Do you intend the condensate drains off the cooling coils to get insulated? There is no spec.
· Yes, contractor to insulate all interior cooling coil condensate drains with 1.5” Mineral Fiber similar to LPR. Exterior cooling coil condensate drains, routed to grade do not require insulation.
5. Do you intend the Heat Exchangers to get insulated? There is no spec.
· Heat exchanger to be insulated with 1-1/2” mineral wool with ASJ as called out in specification 23 07 11, para. 3.2.A.5
6. For the Four floor mounted FCUs on the 1st floor per drawing M-111 (2-FCU-124/1, 2-FCU-124/2, 2-FCU-124/3, 2-FCU-124/4) is the cooling coil condensate drain supposed to drain to the basement below, or be provided with a condensate pump to run along the ceiling?
· All FCU’s to be equipped with a condensate pump and piped to the vertical condensate riser in the ceiling. If the FCU condensate can be gravity drained contractor to follow notes on contract drawings.
Set #3
1. In looking over the phasing plan, we are relocating one half of the floor to another floor during our work. Is the second side of the space empty as well? Are we going to be able to have full access the entire floor at a time?
· No, at this time you have access to half a floor at a time.
2. Are we to figure replacing, “In Kind” the finishes that will be removed for access to ceilings (and walls / floors) during mechanical re work?
· Contractor to match all existing finishes of patches or new work required due to mechanical access and installation requirements.
Set #4 1 – Are the existing lighting fixtures and fire alarm devices to be replaced with new. (Plan Symbol ME- NEW)
- If so what type of LED Lighting Fixtures do they want
· Building 2 has existing new light-fixtures.
2 – The mechanical schedules shows (3) Fans that do not appear on the Electrical Drawings. Are these being installed if so where. Is the mechanical furnishing disconnects or electrical.
· The three fans in question are provided as part of unit 2-DOAS-1. Unit 2-DOAS-1 is included in the electrical connections schedule.
3 – Is any power required for the Clean Stream Generator. There is nothing on the electrical drawings for this.
· Clean steam generator CSG-1 is a steam powered unit. Basis of design did not identify any electrical service. Contractor to provide a dedicated 20 amp circuit for miscilaneous electrical requirements for CSG-1.
Set #5
1. To truly bid this project - we need Seismic Design Criteria Provided to us by the EOR.
They point to the HA-18-8 standard for VA and in a chart it lists St Louis JB.
But they do not provide the Importance Factor nor Soil Site Class ( A, B, C, or D or greater ) - these are needed to determine the seismic criteria and they, the design team needs to provide that to us.
We do not want to guess.
Typically a Geotech will provide the Site Class, the Design EOR will provide the Importance Factor.
After that the data is simply computed and I would rather they determined it as they are the responsible party for the design.
If Site Class C, Ip = 1.0, the resulting data would be SDC C, Ip = 1.0 and everything is exempt.
If Site Class C, Ip = 1.5, the result is SDC D, Ip = 1.5 and everything / pipe over 1" needs bracing If Site Class D, Ip = 1.0, the result is SDC D, Ip = 1.0 and and everything needs bracing except pipe 3" and smaller.
Can you let me know what I need to know to complete the bid?
· Design criteria is listed on Drawing S-001.
Set #6
1. Immediately prior to A.5 PROPOSAL SUBMITTAL INSTRUCTIONS on page 8 of 79, there is a section labeled SAFETY OR ENVIRONMENTAL VIOLATIONS AND EXPERIENCE MODIFICATION RATE. This information is not included in the A.5 submittal instructions. Do we include it as part of Factor 4, or as an attachment to the proposal, or do we not have to include it with the proposal?
· Section A7 titled Contractor Certification Regarding Safety and Environmental should be included as an attachment and will be considered in the evaluation for Factor 4. Additional information may be provided to address Factor 4 if desired.
1. Reference solicitation page 9 of 79: This states how we are to provide our proposal.
1. It says to submit as a single package. Does this mean we include Part 1 and Part 2 together as one document in our hard copy?
· This means we should only receive one parcel that includes everything for the proposal. Parts 1 and 2 should be readily distinguished but may be provided in a single binder. Parts 1 and 2 should be separate files in the electronic copy.
1. Do you want the hard copy for Parts 1 & 2 bound in some particular fashion, e.g., paper clips, clam clips, three-ring binders, etc.?
· In a binder is preferred but not required.
1. Reference solicitation page 15 of 79, paragraph d., Price Proposal. This paragraph states, in part: “offerors shall include a breakdown of material and labor costs, by specification division for each bid item. Overhead, profit and bond costs shall be added after a subtotal of materials and labor costs has been calculated.” Do you want this accomplished thru use of A.6 CALCULATION WORKSHEET FOR SELF-PERFORMED AND SUBCONTRACTED WORK?
· This should be a separate spreadsheet for each Bid Item which breaks down the costs within each Division, see Section A6.
1. Reference solicitation page 15 of 79, paragraph d., Price Proposal. It says we are to provide the pricing from page 5, but does not mention including the SF 1442, Bid Bond, or any other requirements. Can you please clarify what you want included in the Price Proposal and in what order?
· A copy of the signed SF1442, the original Bid Bond (with raised seal), and the completed Bid Items pages are required. Anything that has a price should be in this section. No pricing of any kind that pertains to this project should appear in Part 1 (i.e. the value of previous projects may appear in Part 1 for Past Performance evaluation).
1. Reference solicitation page 15 of 79: At the bottom of this page, it says “END OF PROPOSAL SUBMITTAL INSTRUCTIONS”, but there are several items that follow that are typically provided in a proposal, including:
A.6 CALCULATION WORKSHEET FOR SELF-PERFORMED AND SUBCONTRACTED WORK
A.7 CONTRACTOR CERTIFICATION REGARDING SAFETY AND ENVIRONMENTAL
52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS
52.209-7 INFORMATION REGARDING RESPONSIBILITY MATTERS
· These are addenda to the Instructions and must be completed and included in the proposal package. Furthermore, all sections of the solicitation that provide for offeror input should be completed and included in the package.
Set #7
1) Would integration of the new BACnet equipment controllers to another local VA BAS server be acceptable as an alternate?”
· Contractor to bid the building Automation system as per the contract documents, unless otherwise directed by the VA COR.
2) During the walk through we observed that there is between 4 to 10 inches of clear room above the ceiling space. In multiple rooms it is called out for there to be a fan coil unit placed above the ceiling. On the drawings it is noted that the contractor is to review for constructability of the project. In the majority of locations there is not room to put a fan coil unit above ceiling as well as duct work. We believe that this part of the solicitation is defective and unable to be accomplished. We request that the fan coil units be hung below ceiling with return and supply grills directly off of the units.
Since this design is pumping outside air above the ceiling and then using it as a plenum, I am concerned that there are non-plenum rated items in the ceiling such as wood. How will this be address as it is not noted on the drawings?
· The intent of the construction documents is to place the fan coils in the same location of the existing units, route the ductwork to shown location of the supply diffuser, and ensure proper drainage for gravity drains. If gravity drains are not feasible contractor must install a pump drain to facilitate drainage. During construction if a fan coil is identified not to be able to be installed due to existing height restrictions, the Contractor may extend below the ceiling plane with return and supply grills directly off the units, similar to existing system. Proper submittal including diagrams, ways, and means will be required prior to installation. Any adjustment to ceiling will be included in the bid.
· Due to the available above ceiling space, the supply air system is being installed similar to the existing distribution. Contractor is to price the removal of the above ceiling items as identified in the contract documents, including but not limited to lead paint abatement, mechanical systems and the other items necessary for the installation of the project.
3) It is noted for existing steam convectors on the wall to removed. I see no note about repairing damaged carpet or walls behind or under them. Is this not part of the SOW? Also, I seen nothing that says how the holes in the floor where the piping comes up will be patched. How is this to be patched?
Contractor is to repair the architectural systems damaged during construction. Contractor is to document existing condition prior to demolition. The current SOW does not address repair of existing architectural conditions. The floor penetrations are to be repaired with a 2 hour UL fire rated system.
4) Can Veiga Propress fittings be used on copper lines 2" and down?
· Piping connections allowed on this project are identified in specification section 23 21 13. The above identified fittings are not allowed on this project.
5) What is the exact hot work procedure for this building as in what exactly do you require for hot work?
· Unlike utility outages, which requires 3 weeks’ notice to the VA, hot work notification can be accomplished within 48 hours. “The Hot Work” process begins with the filled-out Permit (see attachment a), emailed to the Contracting Officer Representative. Within 48 hours the COR will process the “Hot Work Permit” and return to the contractor. The COR will coordinate with the electrical shop for any required fire-alarm outage in conjunction with the hot-work. Contractor to refer to Specification 01 35 26 Safety requirements.
6) Are the existing ceilings to be removed and replaced?
· The existing ceilings are to be removed and replaced. Contractor is to carry 20% of the ceiling tile area with new tiles due to damage during removal and installation. See sheet M-001 Note 14. ESTABLISH PASSAGE CLEARANCES REQUIRED TO DELIVER, INSTALL AND ERECT ALL REQUIRED EQUIPMENT. IF STRUCTURES, EQUIPMENT AND SYSTEMS MUST BE ALTERED TO PROVIDE PASSAGE OF EQUIPMENT, THE CONTRACTOR SHALL RESTORE STRUCTURES, EQUIPMENT AND SYSTEMS TO THEIR ORIGINAL CONDITION AT TIHE CONTRACTOR'S EXPENSE; INCLUDING REMOVING AND REPLACEMENT OF ALL CEILING AS REQUIRED TO COMPLETE THE WORK.
7) It is noted that the contractor is to relocate items in the way of the install of the new pipe, equipment and duct. This is not quantifiable. How are we supposed to know exactly what is to be relocated until we get into the construction phase of this project? We need the relocation of items quantified. Please quantify these.
There appears to be no room for the new duct in the ceiling, is the height of the existing ceiling to be lowered?
· Items to be relocated will not be quantified. Any removal or replacement of items is considered incidental to the scope of the project and should be covered in the offerors proposal. Contractor is to coordinate the installation and routing of the new piping, fan coils and other associated appurtenances with the existing conditions. The intent is for the existing above ceiling spaces to be fully demolished of MEP systems, and the installation of the new in the existing location, so that coordination of the existing with the routing of the new is possible.
· Contractor is to install the ceiling at the existing height upon completion of construction. The intent is place the fan coils in the similar location of the existing and coordinate the routing of the supply ductwork.
8) Who is the existing fire alarm vendor at this location?
· Siemens
9) Will a location for multiple connex boxes and two office trailers be provided?
· South soft gravel parking lot is where contractors will stage and park.
10) Where can contractors park?
· Multiple connex boxes will be allowed at the south gravel over flow parking lot located south of building 18. There is room for only 1 job trailers to be in the parking spaces east of building 2. Location for the contractor’s trailers and connex boxes will be identified by the VA COR upon award.
11) Can an entire floor be given to the contractor at a time or just the phased area?
At this time, NO.
| 33. | Does the cooling condensate piping require insulation? Yes |
| 34. | Does the indoor GHWS & R piping require insulation? Yes |
| 35. | Does the refrigerant piping require insulation? Yes |
| 36. | Is all the indoor supply ductwork on the basement plan exposed? Yes |
Set #8
12) On Drawing Sheet M-002, under Phase 3, second bullet point, it states to “Remove & replace all AHU’s and fan coil units on 2nd floor”. Should that refer to 3rd floor instead?
· Phase three is replacing the FCU’s on the 1st floor, not the 2nd floor noted.
13) Are there any as-built drawings we can receive which show the existing piping & duct layout above the ceiling?
· Possibly, Drawings exist, however verification must be done.
14) If no as-builts are available, what should be estimated for the removal of existing piping and ductwork?
· VA to provide existing drawings, however verification must be done.
15) Will a finish schedule be provided for interior finishes?
· No. all finishes are to match existing.
16) Please confirm that all interior walls are drywall and go to the underside of the deck. Due to the numerous duct & piping penetrations that the new work entails, multiple areas of reframing/patching will be required if the existing walls do go to deck.
· Contractor to assume that all walls goes to the underside of deck for bidding purposes, however they do not constitute either a smoke or fire rated assembly. Stairwells, electrical, and mechanical rooms are the exception.
17) How long after the required 7-day notice should we anticipate it will take to move VA personnel to their designated location per the phasing plan?
· Approximately 3 days after notice.
18) On the mechanical drawing sheets, under sheet notes, there is a requirement to provide temporary heating and cooling. Will there be a temporary heating and cooling plan provided that details these requirements?
· Contractor to provide temporary heating and cooling to maintain the space temperature requirements. No plan will be provided. Temperature requirements are heating (68-72 degrees) & cooling (70-75 degree)
19) Due to the difficulties in predicting future weather conditions, can an allowance amount be given to all bidders to address temporary heating and cooling? This will allow all bidders to be on a level playing field in regard to this issue, and will insure the government only pays what is actually needed?
· The cooling and heating system should be out of service during the heat/cool seasons, per the contract documents, and that is when to provide temporary heating and/or cooling is to be provided in the occupied spaces. Contractor to determine the length of these outages per their schedule and provide the quantity and size of units based on square footage served.
20) If an allowance amount for the temporary heating & cooling cannot be given, then can an average indoor temperature based historical temperature averages be issued so all bidders are working with the same criteria for estimating the cost of it?
· Contractor to provide temporary heating and cooling to maintain the space temperature requirements. Temperature requirements are heating (68-72 degrees) & cooling (70-75 degree). Temporary heating and cooling units to be sized based on area served.
21) Required temperature ranges are listed for the heating (68-72 degrees) & cooling (70-75 degree) seasons. We are assuming this would only apply to occupied areas, and not the floor upon which contractors are working?
· Yes. Construction area temperatures are not required to meet the above temperatures. Contractor to ensure that construction areas are above freezing (32˚F) at all times.
22) On the mechanical drawing sheet notes, it mentions that the work should occur “during shoulder seasons”. Can this be assumed to be the following months for non-heating (April, May, June) and for non-cooling (September, October, December)? If this is done, can the denoted duration in calendar days be adjusted in order to accommodate this, as it would lead to gaps between the phases?
The non-heating season shall be June, July, August and the non-cooling season shall be November, December, January. Typically, the VA runs the chiller well into October and heat into May due to the rainy season.
23) On the new work mechanical drawing sheets under “new work keynotes”, there is a keynote referencing two different conditions to bid. These conditions are based on field verification of the routings onsite to see if the FCU’s can be gravity drained or not to determine if a condensate pump can be utilized. For competitive bidding purposes, can contracting designate which condition should be accounted for to assure all contractors are bidding the same scope?
· The note details all FCU’s to be equipped with a condensate pump routed to the vertical condensate riser. If a FCU condensate can be routed via gravity to an indirect drain or condensate riser, the contractor is to provide a credit or condensate pump to the VA. For bidding purposes contractor to provide a condensate pump for every FCU.
24) Can we assume that the 2% requirement minimum slope for condensate drain lines will not interfere with crossing of various ductwork? The concern is that there appears only to be a 24” or less interstitial space above the ceiling at floors 1 thru 3.
· There is room in the ceiling plenum to route the condensate piping. Contractor to provide coordination drawings, with all disciplines including but not limited to piping, ductwork, cable tray, and lights, showing the coordinated routing of the condensate drain lines with or without sloping.
25) To confirm, for any penetrations through existing windows with mechanical ductwork and/or piping, we can remove the entire window and frame.
· Yes it is acceptable to remove the entire window and frame provided at completion of the project that area is weather tight. Contractor to provide weather proofing during construction to minimize weather damage to the building during construction.
26) Project requirements call for “1” insulated plate”. Can more information be given on this material? Is it an FRP panel face, metal panel face, etc…? Is there a certain R-Value minimum required?
· Contractor to provide a minimum of R-5 with paintable metal panel faces.
27) Please confirm if the VA is responsible for all costs associated with the 3rd party commissioning agent?
· The Contractor is responsible for all cost associated with the 3rd party commissioning agent.
28) To confirm, environmental abatement costs should be included in contractors bid?
· Yes.
29) In terms of site staging, can a permitted trailer location, as well as worker parking area be given so we can determine if any added costs are needed to shuttle workers in?
· South soft gravel parking lot is where contractors will stage and park.
30) To confirm, in addition to the temp heating & cooling, will contractors be required to provide temporary lighting in the occupied areas?
· Temporary heat and cooling requirements are intended to be provided when the central heating and cooling systems are being replaced during the non-heating/cooling months. Lights should be provided to assist construction. If lights are removed in occupied offices contractor to provide temporary lighting providing 30 fc.
31) If temporary lighting is required, Is there a specific minimum foot-candle requirement?
· 5 fc in construction areas.
32) Please provide the line sizes for the new split system in the basement.
· Refrigerant line sizes are to be per the manufacturers requirement due to coordination drawings routed lengths.
33) Please confirm what type of lines are being run for the split system (i.e. refrigerant? )
· The split system is a refrigerant system.
34) Please provide the sizes for the glycol and steam lines in the basement.
· Contractor to refer to M-101 basement plan and M-601 and M-602 for basement piping sizes.
35) The phasing plan does not appear to describe at what point the existing risers will be demolished or at what point shutdown should occur for swap to new systems. Please advise.
· In phase 1, the vertical risers will be installed. The systems (chilled water, hot water, etc) being connected to at each floor during that phase will affect the entire system and will require that system to be down during that time. Contractor to refer to his proposed schedule to determine that down time for each phase. These activities will be coordinated with the VA during the construction period.
36) M001 General notes detail excavation. Will contracting clarify what aspect of work this pertains to?
· This note reference is general in nature and covers any excavation that is needed by the contractor to facilitate the installation of the MEP systems.
37) Please define what “normal work hours” are.
· Normal work hours are 7 to 4:30 typically. However individual employee work hours range from 6 am to 5pm.
38) Please confirm if both CQC System Manager and Alternate CQC System Manager are required to have completed the Construction Quality Management (CQM) for Construction Course.
· Yes, both are required.
39) Please confirm if LEED specialist is required as noted in 01 45 00 -7.
· Not required.
40) Please confirm if Design Quality Manager is required as noted in 01 45 00 -6 - YES
41) Please confirm the CQC Systems Manager may dual role as the Site Superintendent - NO
42) Please confirm if the Prime Contractor must provide a full time Site Safety and Health Manager that may not be the site Superintendent or the CQC Systems Manager. Correct
43) Specification 07 84 00 FIRESTOPPING does not appear to have been included. Please provide specification for Firestopping work.
· Specification 07 84 00 Firestopping is part of submitted bid package.
44) Please provide the requirements/parameters for the duct air leak test.
· Duct leakage testing requirements are per section 23 31 00 paragraph 3.2.
45) If CQC can dual role as Site Superintendent, are we required to submit two separate resumes in Technical Proposal Factor 3 ? Not a dual role.
Set #9 (Response to questions pertaining to acceptability, location and selection of control items are part of the submittal review process).
1) "Please clarify that VA shall provide for use by BAS Network Panel, a Data Port and coordinated static IP address on Campus Ethernet in Basement Heating Plant Room G-07 near column A,2" Yes. COR will coordinate with the AC shop and provide IP address
2) Please clarify there is currently no Emergency Generator and no Emergency Power in the facility (This would negate the noted requirement for Controls to have power from emergency source per General Note-7 on M-801)
· There is campus wide backup generator power.
3) "Please clarify locations for VFDs serving DOAS-1 (SF1, EF1 & Energy Wheel) This is required for accurate pricing."
· The Basis of design for DOAS-1 has the VFD being factory mounted and provided with the unit. Contractor shall coordinate location of VFD with approved shop drawing.
4) Please clarify that Fan 2-SF-2 shall be furnished with ECM motor and terminals for remote input for ON/OFF and Speed Control (instead of Control of VFD per M-804)
· Contractor to provide the VFD and control DOAS-2 as identified on M-804.
5) Please clarify that 2-DOAS-2 shall not require an additional Air Flow Measuring Station in the OA Duct (indicated on M-804) since it is 100% OA Unit with Airflow Measured at Supply Fan.
· Contractor to provide an Air Flow measuring station as identified on Drawing M-804.
Questions 6 thru 17 on set #9 are not applicable to be answered at this time. These items will be responded to during the shop drawing review of the controls. Contractor to follow the contract documents for device type, pipe size and coordinate with approved equipment selections and coordination drawings on location of sensors.
| 6) | "Please clarify that Air flow Measuring Device (AFMD) are to be Thermal Dispersion type, furnished under SECTION 23 09 23 - DIRECT-DIGITAL CONTROL SYSTEM FOR HVAC for installation by Ventilation Contractor in the following locations:" | |
| a. | 2-DOAS-1 Supply Fan Inlet | |
| b. | 2-DOAS-1 Exhaust Fan Inlet | |
| c. | 2-DOAS-2 Supply Fan Inlet | |
| 7) | Please clarify the following for Steam Flow Meter Selection | |
| a. | Pipe diameter (inches) of HPS line inside BLDG-2 | |
| b. | HPS Steam Quality (Saturated or Super-heat Temperature) | |
| c. | HPS line pressure (psig) | |
| d. | HPS Flow range (0-2200 LBS/HR) | |
| 8) | "Please clarify that the standard JCI products used, provided, and installed on campus for recent similar projects (Bldg-55, 56 & 57) will be acceptable for the following (see attached catalog data):" | |
| a. | Heating & Cooling Water Flow Meters - Onicon F-3500 Insertion Electro-Magnetic Flow Meter (BTU Meter) | |
| b. | Steam Flow Meter - Onicon F-2600 Series Inline Vortex Meter | |
| c. | Standard RTD (Nickel or Platinum) without transmitters - JCI TE-6300 Series | |
| d. | Fan Inlet Thermal Dispersion Air Flow Measuring Devices (AFMD) - JCI RA-1250 Series | |
| e. | Ball valves (or butterfly for large 2-position) for hydronic & globe for proportional steam (vs globe valves for all applications) -JCI VG1000 Series |
9) Please clarify that HWUH (Hot Water Unit Heater) and Air Curtain shall be controlled for ON/OFF Fan and OPEN/CLOSE heating valve by DDC (similar to other projects on campus vs standalone package controls by EQT MFR)
10) Please clarify that all automatic control valves for modulating control shall be equipped with proportional actuators (instead of incremental/floating point)
11) Please confirm the automatic control valves for Fan Coil Units (FCU) shall be fail in place (not spring fail-safe)
12) Please clarify that FCU Fan Speed may be selectable at the unit but will not require a remote/wall mounted 3-speed switch with additional aux contacts for Off/On monitoring (as noted in 238200.2.1.E.2)
| 13) | "Please clarify that cooling coils located above ceilings in occupied areas (FCUs and DOAS-2) shall have ""hardwired"" (not monitored by DDC) Float Switch for high water level safety in drip pan (similar to other projects on campus):" |
| FLOAT SWITCH LOCATED AT HIGH POINT OF FAN COIL?S CONDENSATE DRAIN PAN SHALL DE-ENERGIZE SUPPLY FAN IN THE EVENT A HIGH WATER LEVEL CONDITION OCCURS. |
14) Please clarify that DDC is to monitor and alarm temperature in each room served by AC-G01 and AC-GC04 (No Spec Section and Scheduled to be Stand-Alone w/ OEM Controls)
| 15) | Please clarify overall Period of Performance dates (start & completion) and key dates associated with: | ||
| Phase-1 | (remove existing & install new Chiller & associated pumps during non-cooling season when this project will likely be awarded in the at the start of the cooling season - is temporary cooling required to be provided under this contract?) |
| 16) | "Please confirm that the additional work for Section 230923 (above that indicated on M-805) is required for each FCU by ""Trending and Alarms"" table in SECTION 01 91 00 - GENERAL COMMISSIONING REQUIREMENTS" | ||||
| Furnish and install the additional Input Points to DDC & BAS | |||||
| Type | Name | Description | Signal | FIELD DEVICE | |
| AI | FILT-DP | PreFilter Differential Pressure | 4-20mA | By 230923 | |
| BI | WTR-S | Water Switch (Float) | Dry Contact Maintained | By 230923 |
| 17) | "Please confirm that the additional work for Section 230923 (above that indicated on MEP Plans) is required for various systems or equipment by ""Trending and Alarms"" table in SECTION 01 91 00 - GENERAL COMMISSIONING REQUIREMENTS" | ||||
| Furnish and install the additional Input Points to DDC & BAS | |||||
| DOAS-1 | |||||
| Type | Name | Description | Signal | FIELD DEVICE & TRADE COORDINATION | |
| BI | LT2-A | Low Temperature Alarm 2 | Dry Contact Maintained | Temperature Switch By 230923 | |
| BI | LT3-A | Low Temperature Alarm 3 | Dry Contact Maintained | Temperature Switch By 230923 | |
| BI | OA-ALM | Outdoor Temperature Switch | Dry Contact Maintained | Temperature Switch By 230923 | |
| BI | PWR-FAIL | Power Failure | Dry Contact Maintained | Contact at MDP in RM G-09 by DIV-26 |
| Steam and Condensate Pumps | ||||
| Type | Name | Description | Signal | FIELD DEVICE & TRADE COORDINATION |
| BI | CP-S | Condensate Pump Run Time | Dry Contact Maintained | By 230923 |
| AI | WM-F | Water Meter (GPM) | 4-20mA | "DIV-22 to furnish & install Meter with transmitter mounted inside BLDG-2 RM G-07 columns C,1" |
| AI | ELEC-PWR | Electric Meter (KW/H) | 4-20mA | Transmitter at MDP in RM G-09 by DIV-26 |
| AI | IRWM-F | Irrigation Water Flow (GPM) | 4-20mA | "DIV-22 to furnish & install Meter with transmitter mounted inside BLDG-2 RM G-07 columns C,1" |
| AI | COND-F | Condensate Flow (GPM) | 4-20mA | DIV-23 to furnish & install Meter with transmitter mounted inside BLDG-2 RM G-08 |
| BI | HILVL-ALM | High Water Level Alarm | Dry Contact Maintained | DIV-23 to furnish & install Float Switch with AUX/Dry contacts inside BLDG-2 RM G-08 |
| BO | CP-C | Condensate Pump Command | 24VAC Maintained | Relay By 230923 |
| Domestic Hot Water | ||||
| Type | Name | Description | Signal | FIELD DEVICE & TRADE COORDINATION |
| AI | DWH1-SET | Dom HW Setpoint DWH-1 | 0-10VDC | DIV-22 to replace existing as required to receive remote setpoint from BAS |
| AI | DWH2-SET | Dom HW Setpoint DWH-2 | 0-10VDC | DIV-22 to replace existing as required to receive remote setpoint from BAS |
| AI | DWH1-T | Domestic Water Heater-1 Temperature | Platinum 1K RTD | Temperature Sensor with thermowell By 230923; Well installed in Pipe by DIV-22 |
| AI | DWH2-T | Domestic Water Heater-2 Temperature | Platinum 1K RTD | Temperature Sensor with thermowell By 230923; Well installed in Pipe by DIV-22 |
| BI | DCP1-S | Primary HW Pump 1 Status | Dry Contact Maintained | Current Sensing Relay By 230923 |
| BI | DCP2-S | Primary HW Pump 2 Status | Dry Contact Maintained | Current Sensing Relay By 230923 |
| BO | DCP1-C | Primary HW Pump 1 Command | 24VAC Maintained | Relay By 230923 |
| BO | DCP2-C | Primary HW Pump 2 Command | 24VAC Maintained | Relay By 230923 |
| BO | DWH1-ENA | Dom HW DWH-1 Enable | 24VAC Maintained | Relay By 230923 |
| BO | DWH1-ENA | Dom HW DWH-1 Enable | 24VAC Maintained | Relay By 230923 |
| 18) | Please clarify that no additional MISC monitoring by DDC and/or BAS are required for the following |
| CO2 Sensors | |
| Elevator Sump level alarm | |
| Electric or Power Distribution | |
| Condensate Pumps | |
| RO Water Systems | |
| Domestic Hot Water Systems | |
| Plumbing Systems | |
| Other |
· The identified systems above, other than the condensate pump is not part of the project scope. Controls contractor to leave spare points in the BAS panels for future equipment connections.
19) I noticed that 2-DOAS-1 had mention of a Humidifier (H1) but there is not a Humidifier schedule for that humidifier. Do you have a schedule? Also, will steam be provided from the building, or do we need to generate our own steam?
· A clean steam generator is being installed as part of this project (CSG-1) which is piped to each of the duct mounted humidifiers located on each floor. There are no humidifiers located in either DOAS unit.
For the questions 1 – 4 below, Source Selection data applicable to this project will not be released at this time.
1. What was the budgeted overall value of this project when it first bid last year?
2. Who were the GC’s that bid this project last time?
3. How much over budget last bid?
4. What was the value of the mechanical bid from the previous bid?
5. For Deduct Alternate #1 (to reuse existing mains), if the response to this request is “No Bid”, does that mean that the entire bid will be thrown out?
· Paragraph d. on page 15 states that offerors “must” submit prices for each bid item. If pricing is not provided for an alternate bid item, the offer would be deemed non-responsive and thrown out.