(PN589A5-18-135)Renovate 2nd Floor for VCL, TOP
Solicitation number
36C25518R0528
Issued by

About this file

36C25518R0528 P09 Supplement B - Renovate 2nd Floor of Bldg 3 for VCL 589A5-18-135 Version 5.3.doc

View the file

Other files

File Type Posted
36C25518R0528-0003000.docx DOCX document
36C25518R0528-0002000.docx DOCX document
36C25518R0528-0001001.pdf PDF
36C25518R0528-0001000.docx DOCX document
36C25518R0528-010.pdf PDF
36C25518R0528-004.pdf PDF
36C25518R0528-003.docx DOCX document
36C25518R0528-011.pdf PDF
36C25518R0528-009.pdf PDF
36C25518R0528-007.pdf PDF
36C25518R0528-008.pdf PDF
36C25518R0528-012.pdf PDF
36C25518R0528-006.pdf PDF
36C25518R0528-002.docx DOCX document
Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project 589A5-18-135 Renovate 2nd Floor of Building 3 for VCL

SUPPLEMENT B

1. SCOPE OF WORK:

Design Build services are required for the design and construction of project 589A5-18-135, Renovate 2nd Floor of Building 3 for VCL. During the design phase, the Design/Build team will provide the renovation design, schematics, construction documents and cost estimates for the project. During the construction phase, the Design/Build team will construct the project and maintain all required construction documentation. This delivery order shall cover the following tasks.

General Statement The Design Build team shall take the VA’s 35% design documents and complete the plans and specifications, detailed cost estimates, schedules, including project phasing, and then complete the construction to accomplish the following scope of work. This scope of work will include the renovation and reconfiguration of existing 2nd floor space in the Topeka VHA building 3 to correct functional layout issues and expand a Veteran Crisis Line Call Center. The design shall include the expansion and bituminous surfacing of parking lot 14 to achieve 200 parking spaces, security parking lights, a dedicated uninterruptable power supply, emergency power generator and ATS/building. The facility shall be designed to have zone controlled climate control for both heating and cooling.

The designer shall produce a 3D walk through presentation in REVIT of the floor plan for the VA Staff to visualize the space being renovated. These design reviews will be face to face at the Topeka VAMC and will occur when the designs are 60% and 90% complete. The meetings will have a virtual call in option for stakeholders that cannot attend.

2. DESIGN DEVELOPMENT/CONSTRUCTION:

The Design/Build team shall:

a. Meet onsite with Topeka Facilities staff to coordinate information and discuss the overall concept. Afterward, meet with Facility staff and Integrated Projects Team and key stakeholders at least twice prior to start of design to validate 35% design documents, and determine space requirements and adjacencies of work involved. The DB firm shall provide environmental and industrial hygienist reviews, a geo-technical survey, and testing of all affected areas as part of their investigative studies.

b. Work from existing building and site drawings furnished by the VA to develop project design updates. The AE firm shall validate and confirm the existing conditions through investigative studies, produce accurate drawings and develop a situational awareness of the current conditions prior to 60% of design. (The VA 35% design documents are to be used as a starting point. The design completed by the DB team will require further levels of design development and will need to be validated.)

c. Perform all necessary on-site field investigations. These investigations include, but are not limited to: measurements of existing conditions, civil grading, drainage, and utility locations. The purpose of these investigations is to verify the design documentation provided by the VA.

d. Prepare conceptual drawings and present onsite 2D and 3D concepts to Topeka Facilities and stakeholder staff (Integrated projects team) via visual presentation aid.

e. Follow VA Program Guide PG-08-15 Volume C, and other applicable guidelines to design the project.

f. DB/AE shall work with a 3rd party commissioning agent to provide detailed commissioning of all specified systems.

3. INDUSTRIAL HYGIENE SERVICES:

Design Build Architect/Engineer

Determine if asbestos, lead based paint and/or mold is present. If found, design a method for abating all asbestos, lead based paint and/or mold within the construction limits of this project.

a. Determine locations of asbestos and/or lead contamination, and water and moisture damage, working with the Industrial Hygienist (I.H.) to uncover and assess hidden areas. Design a way to rectify.

b. For mold, determine entry point of water infiltration. Design a correction.

c. For asbestos and/or lead contamination, determine the extent of abatement required within the construction limits of the project.

d. Provide 3rd Party Air Monitoring Services during construction.

e. Review the I.H. report.

f. Produce a written report compiling all necessary information.

g. Demolition and Removal:

1) Remove only the part of the structure required to abate asbestos, remove lead contamination, or area damaged by mold (unless required to be removed by the larger design concept.)

2) Have all asbestos, lead based paint and/or mold within the construction limits of this project removed from the existing walls, above ceilings or in floor coverings as needed before installing the new work specified for the project area of the building.

The DB A/E shall retain a qualified Industrial Hygienist to perform the following work:

Industrial Hygienist

a. Conduct a site visit and perform viable and non-viable air sampling for asbestos, lead based paint and/or mold spore concentrations. Collect samples throughout the existing area within the construction limits of this project under the direction of the Project Engineer. Sampling activities will be performed by trained personnel under the direction of a licensed Industrial Hygienist and/or Board Certified Microbial Consultant.

b. Perform a limited assessment of the existing area within the construction limits of this project with the goal to identify contaminated areas of asbestos and/or lead paint, and moisture sources and proliferation of mold growth. Field work will be performed by trained personnel under the direction of a licensed Industrial Hygienist and/or Board Certified Microbial Consultant.

c. Prepare a written report detailing sample locations, laboratory analysis and professional recommendations.

All work shall comply with all applicable laws, regulations and procedures published or issued by federal, state and local regulatory agencies for the abatement and control of hazardous materials.

4. DESIGN DELIVERABLES:

Design Development (DD) 60% and 90% Submission:

Phasing plan and schedule
Narratives, Analyses, Studies, HVAC Load & Other Calculations, Data, BIM Models and Drawings, Specifications
VA Master

and A/E produced

Specifications

Upload to FTP site and provide hard copy and disc to VA COR
(1) Full size complete print set, CD-ROM of PDF’s, and all BIM models in Revit 2015

(2) Upload all files to FTP site Upload to FTP site and provide hard copy and disc to VA COR

Construction Documents (CD) 100% Submission:

Phasing plan and schedule
Narratives (scope of work), Analyses, Studies, Calculations, Data, BIM models and Drawings
VA Master

And A/E produced

Specifications

(2) complete sets
(1) Full size and (2) half size prints, CD-ROM of all PDFs, and all BIM models in Revit 2015

(2) Upload all files to FTP site

(2) complete bound sets and also uploaded to FTP site

As-Built BIM Models, 3D Doc Files & Drawings (As-Built) Project Close Out Submission:

Narratives, Analyses, Studies, Calculations, Data, and Drawings

(1) Full size Set, CD-ROM computer disks with all drawings listed in current version of AutoCAD in use by the VAMC, PDF’s, all BIM models in Revit 2015 and all 3D documentation files of completed project in Recap 2015

(2) Upload all files to FTP site

5. DESIGN REVIEW AND COMPLETION SCHEDULE:

a. The A/E shall perform the work required by this contract within the limits of the following schedule. The A/E shall provide Professional Architects and Engineers as directed by the Contracting Officer who are familiar with the work to attend the Design Reviews on the dates described below.

Make all investigative studies and site work to:

Deliver Design Development (DD 60%) material to Contracting Officer Rep _45__ days after Notice to proceed

Review Design Development (DD 60%) material with IPT and VA facilities/COR in person _3_ days after delivery of material. (DB/AE shall coordinate face to face design review for the third day)

Deliver Design Development (DD 90%) material to Contracting Officer Rep and CO _45__ days after acceptance of 60%.

Review Design Development (DD 90%) material with IPT and VA facilities/COR in person _3_ days after delivery of material. (AE shall coordinate face to face design review for the third day)

Deliver Final Construction Documents (CD 100%) material to the Contracting Officer and COR _15_ days after Notice to Proceed. .

Review Construction Documents (CD 100%) material with the Contracting Officer and COR _3__ days after delivery of material. (AE shall coordinate face to face design review for the third day)

Deliver Final material incorporating comments from 100% review to Contracting Officer _7_ days after review.

Total of 121 days from contract Notice to Proceed to complete the design.

Request a NTP for Construction after design has been approved.

b. The Contracting Officer (CO) may schedule an additional Design Review(s) as necessary when it is determined by the CO that such review(s) is/are required for satisfactory completion of design contract requirements. The DB/A/E will be reimbursed for all additional review meetings, unless it is determined by the CO that such additional reviews were requested by the A/E, or were required due to the A/E’s failure to meet contract requirements.

c. A/E firm shall provide to the COR three full size and two half-size drawings of the 100% package, digital on FTP and on disc. A/E shall also provide two bound sets of 100% specifications to the COR for use during bidding and construction, all documentation shall be included digitally on a disc at that time.

6. CONSTRUCTION:

a. The Design build team shall perform all work, equipment, and materials to renovate the 2nd floor of building 3 to expand a new suicide crisis line call center. The facility shall have dedicated breakrooms, lactation rooms, restrooms, private offices, open office call center space, meditation, conference rooms, supply storage rooms, swing space, secure access, zoned HVAC to be able to provide heating and cooling at the same time, noise control, high performance LED lighting and plumbing fixtures, and upgraded elevators.

b. The design build team shall perform and provide all labor work, equipment, and materials to surface and expand parking lot 14 to a 200-parking stall lot with adequate security lighting (meeting or exceeding VA standards), pavement marking, curbing, sidewalks, site security panic devices, and handicap access requirements. All on-grade concrete will be designed to meet KCMMB specifications.

c. The Design build team shall perform and provide all work, equipment, and materials to construct a dedicated emergency backup generator for the call center, integrated uninterruptable power supply UPS, and automatic transfer switch ATS system. The general construction contractor shall have 240 days to complete the construction. The DB team shall provide detailed scheduling and phasing plan.

7. MISCELLANEOUS:

a. In accordance with 52.236-22, Design within Funding Limitation (APR 1984), the estimated construction contract price for this project is $8,613,500, not including any contingency.

b. The A/E firm shall establish a means for submitting and exchanging information, drawings, RFI’s, etc. between the A/E firm and CO such as Submittal Exchange or equivalent type of website service provider designed for transmitting information between all construction team members.

-END-