36C25227Q0051_ 0002_Vendor Questions Updated_28Oct2026.docx
DOCX document 402 KB Posted
- Solicitation number
- 36C25227Q0051
About this file
This is a Vendor Questions and Answers amendment document that provides Government clarifications to potential offerors regarding a condenser coils replacement solicitation for the VA Illiana Health Care System (VAIHCS) in Danville, Illinois.
The amendment addresses 14 vendor inquiries covering submission procedures, equipment specifications, labor requirements, and contractual obligations. Quotes must be submitted by email to eric.king2@va.gov as a single PDF document with no special subject line required. The equipment to be replaced is a CGAM060F2A chiller with serial number U10A13482, located at grade level at Building 14. The Period of Performance is 30 days from award date. Key clarifications include: certified payroll submissions are not required; R-410A refrigerant will be Government-furnished for any pre-existing shortage; repair must be completed within the performance period with material sourcing issues addressed on a case-by-case basis; and no dedicated Key Personnel are required, including no mandatory Project or Site Supervisor, Site Safety and Health Officer (SSHO), or Quality Control Manager. Regarding the Service-Disabled Veteran-Owned Small Business (SDVOSB) subcontracting requirement under VAAR 852.219-75, the correct limitation is the 50% services threshold (not the 75% special trade construction threshold), meaning the contractor cannot pay more than 50% of Government payments to non-certified SDVOSB/VOSB firms. The contractor may directly purchase OEM replacement coils with local subcontractors performing installation labor only, consistent with the services limitation calculation.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C25227Q0051_0002.docx | DOCX document | |
| 36C25227Q0051 0001.docx | DOCX document | |
| S02_Attach1_Department of Labor Wage Determination_Vermilion County Illinois_0215-5021_22Aug202.pdf | ||
| 36C25227Q0051_Condenser Coils Replacement_Solicitation_15Oct2026_Final.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Vendor Questions
This amendment incorporates the Government’s responses to questions submitted by potential offerors. These questions and corresponding answers are provided for clarification purposes only and do not revise or otherwise change the requirements unless explicitly stated within this amendment.
1. Q: Please confirm how quotes are to be submitted: by email to eric.king2@va.gov, or to the Great Lakes Acquisition Center address in SF 1449 block 9 and advise any required subject line or file format.
A: eric.king2@va.gov A: Return file as one document with any attachments included (PDF Preferred).
A: No special subject line necessary.
2. Q: Please provide the serial number from the CGAM060F2A nameplate, needed to order the OEM coils.
A: The serial number is U10A13482
3. Q; Is the chiller at Building 14 installed at grade or on a roof?
A: The chiller is installed at grade.
4. Q: Please confirm whether certified payroll submissions are required for the condenser-coil replacement work and identify the applicable clause and reporting instructions.
A: Not Required
5. Q: Clarification regarding refrigerant quantities, existing piping leaks, coil procurement lead times and the period of performance, and key personnel requirements.
A: Period of Performance is date of award plus 30 days, per the solicitation schedule of items (B.2). This answers the “coil procurement” lead times.
A: No Key Personnel requirements.
6. Q: The VAAR 852.219-75 certification in the package appears with both the services limitation (50%) and the special trade construction limitation (75%, cost of materials excluded) presented. Which limitation governs this requirement?
A: The correct block is Services not Special Trade Construction. So, disregard the Special Trade Construction block, as it is not applicable to this RFQ.
i) [X] Services. In the case of a contract for services (except construction), the contractor will not pay more than 50% of the amount paid by the government to it to firms that are not certified SDVOSBs listed in the SBA certification database as set forth in 852.219–73 or certified VOSBs listed in the SBA certification database as set forth in 852.219–74. Any work that a similarly situated certified SDVOSB/VOSB subcontractor further subcontracts will count towards the 50% subcontract amount that cannot be exceeded. Other direct costs may be excluded to the extent they are not the principal purpose of the acquisition and small business concerns do not provide the service as set forth in 13 CFR 125.6.
7. Q: If MK2E purchases the OEM replacement coils directly and a local subcontractor performs installation labor only, please confirm that structure is consistent with the governing limitation's calculation (materials excluded under the special trade construction prong.
A: That block was incorrectly checked. See question five (5) answer.
8. PWS 2.1 Task 4 (B)-(C) Additional Refrigerant:
Q: Please confirm whether R-410A needed to replace a pre-existing shortage or loss from the existing system will be Government-furnished or separately compensated through a contract modification.
A: Additional R-410A will be government furnished.
9. PWS 2.1 Tasks 4 (A) and (B) Refrigerant Leaks Q: Existing Refrigerant Piping Leaks
A. If additional leaks are detected outside of the condenser coils, this must be immediately brought up to the COR and CO to determine next steps
10. Q: Coil Lead Times:
A: The repair must be conducted within the time frame of the period of performance. Any issues with sourcing materials will be addressed on a case-by-case basis.
11. PWS 9.1; Project or Site Supervisor:
Q: Please confirm whether a dedicated Superintendent or Site Supervisor is required, the minimum qualifications, and whether continuous onsite presence is required whenever work is performed. Must this individual be a direct W-2 employee of the prime contractor, or may a qualified subcontractor employee serve under the prime contractor’s direction and authority?
A. A Project or Site Supervisor is not Required.
12. PWS 9.1(d); applicable safety requirements
Q: Please confirm whether a designated SSHO is required and identify the minimum training, certifications, experience, and onsite attendance requirements. Must the SSHO be a direct W-2 employee of the prime contractor, or may a qualified subcontractor employee serve in this role?
A. A designated SSHO is not required.
13. PWS 8.3 Quality Control Manager
Q: The PWS requires a Quality Control Plan. Please confirm whether a dedicated QCM is also required, and identify minimum qualifications, certifications, and onsite attendance requirements. Must the QCM be a direct W-2 employee of the prime contractor, or may a qualified subcontractor employee serve under the prime contractor’s QCP?
A. A dedicated Quality Control Manager is not required.
14. PWS 8.3 and 9.1 Combined Key Personnel Roles:
Q: Please confirm whether one qualified individual may serve concurrently as Superintendent/Site Supervisor, SSHO, and QCM, or in any combination of these roles. If separate personnel are required, please identify the roles that must be separated and whether each must remain onsite whenever work is performed.
A. Not required.
All other terms and conditions remain unchanged. The RFQ response date remains unchanged.