S05 - Pre-Bid RFIs Log with Answers 550-20-121- 11-10-2026.xlsx

XLSX spreadsheet 72 KB Posted

Attached to
Z1DA--550-20-121 Demo Old Boiler Plant B100 (CON)
Solicitation number
36C25227B0002
Issued by

About this file

This is a Pre-Bid Requests for Information (RFI) Log with Answers for the demolition of Building 100 (Old Boiler Plant) at VA Illiana Healthcare in Danville, Illinois, under Solicitation 36C25227B0002. The document contains 154 RFIs submitted by potential bidders between October 16 and October 27, 2026, with responses from VA contracting and technical personnel. Key project details include: a November 18, 2026 bid deadline at 1:00 PM CST with bids accepted only as sealed, in-person hard copy or mailed submissions; a 180-calendar-day completion requirement; and a single pre-bid site visit conducted October 20, 2026 at 11:00 AM with no additional site visits planned. The project involves complete demolition of the boiler plant building including removal of asbestos-containing materials (ACM), lead-based paint (LBP), an underground storage tank (UST), contaminated soil, mechanical systems, electrical systems, the 111-foot brick chimney stack, cooling tower, and steam tunnels, with estimated base quantities of 100 cubic yards of contaminated soil removal and six soil testing locations; additional quantities beyond these estimates will be compensated through contract modification. Scope includes hazardous materials abatement per Sections 02 82 11 (ACM) and 02 83 33.13 (LBP), with a regulated building materials survey by Mabbett & Associates dated February 8, 2021 referenced for material locations and quantities.

Staffing requirements specify a full-time Superintendent employed directly by the prime contractor; an on-site Site Safety and Health Officer (SSHO), who may be a subcontractor; a Contractor Quality Control (CQC) System Manager; with one qualified individual permitted to serve concurrently in multiple roles (Superintendent/SSHO/QCM) provided qualifications are met. Normal working hours are Monday-Friday, 7:30 AM to 4:00 PM, though extended or Saturday hours may be approved by the Contracting Officer's Representative at contractor expense. The contractor staging/laydown area is located on the south side of campus on the north/south maintenance road by the south water tower; dumpsters, porta-johns, and temporary 6-foot construction fencing are permitted near Building 100; and parking is available north and west of the building. The contractor must obtain all required federal, state, and local permits and licenses, including asbestos abatement notifications, NPDES/stormwater permits, and UST closure documentation; the VA will follow up on NPDES permit requirements. The project is tax-exempt, with anticipated award within two weeks of bid opening and no impact from winter weather on the Notice to Proceed (NTP) date. As-built drawings, hazmat survey reports, and specification sections 01 45 29 and 01 57 19 will be provided by amendment; the contract includes federal prevailing wage rates, including truck driver classification at $47.71/hour base plus $25.72 fringes per wage determination TEAM0050-002 effective May 1, 2025.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Pre-Bid RFIs 550-20-121 Demo Old Boiler Plant B100 (CON) Pre-Bid RFIs

No.Date SubmittedReferenceSUBJECT/COMMENTResponderResponseIncluded in Amendment #
110/16/26Would the VA consider approving a second site visit at some point prior to the November 18, 2026 bid deadline? Alternatively, would it be possible to arrange individual site visits for subcontractors who are unable to attend on October 20?JCGNo, there are no plans for a second site visit for this project besides the Site visit conducted on October 20, 2026 at 11am.0001
210/16/26We are unable to attend the pre-bid meeting and site visit scheduled for Tuesday, October 20th at 11AM. Would it be possible to schedule a second meeting/visit for the following week? Possibly on the 27th or 28th?JCGNo, there are no plans for a second site visit for this project besides the Site visit conducted on October 20, 2026 at 11am.0001
310/21/26Please confirm that bid opening stands at 18 November 2026 at 1:00 PM Central, and that no amendment is pending that would move it.JCGYes, the bid due date is November 18, 2026, at 1pm CST. We are posting amendment 1 today, October 21, 2026 and there are no changes to the bid due date.0001
410/21/26The presolicitation notice of 22 September stated that a pre-bid conference would be held and that details would be included in the solicitation package. Please confirm the date, time and location, and how to register. If those details are already in the posted package, point me to the file and page and I will take it from there.JCGThe Site visit was listed on SF 1442 Page 1 and page 4. Site visit was conducted on October 20, 2026 at 11am. There are no plans for a second site visit for this project.0001
510/21/26Please confirm the address and method for bid submission, and whether bids are accepted electronically.JCGPer solicitation instructions (See page 4 and 5), No email bid submissions will be considered, only in person hard copy and mailed bid submissions will be accepted. All submissions must be received no later than the required bid due date and time. All submissions must be received in a sealed envelope and addressed to the following:

ATTN: Juan C. Gaytan Solicitation: 36C25227B0002 Great Lakes Acquisition Center (GLAC) 115 S. 84th Street, Suite 101

Milwaukee, WI 53214-14760001
610/27/2602 41 00 1.9.D; HA101/102 note 6Please provide the Mabbett & Associates Regulated Building Materials Survey dated February 8, 2021 referenced on HA101/HA102 Note 6 and stated as 'on file for review'. In particular, please confirm whether the roofing membrane, boiler/incinerator refractory and firebrick, the 111-ft brick chimney liner and mortar, and the steam tunnel insulation were sampled and their results.TJFThis will be provided. See attachment: Demolish Boiler Plant V1 - Final Hazmat Report with attachments0002
710/27/26CD101 KN19; 02 82 11 1.1.2CD101 Keynote 19 states steam tunnels are anticipated to include asbestos-containing material, but Section 02 82 11 1.1.2 lists no tunnel quantities. Please provide the estimated linear feet and pipe sizes of ACM in the tunnel segments to be removed, or confirm that tunnel ACM will be handled at the unit prices for newly discovered ACM.TJFNo additional information for steam asbestos is available. Plan for bid based on amount of steam tunnel to be removed and standard quantities of ACM to be removed accordingly.0002
810/27/2602 82 11 1.2; 02 65 00 1.3; Bid ScheduleSections 02 82 11 1.2 and 02 65 00 1.3 require unit prices for newly discovered ACM and for additional contaminated soil, but the Bid Schedule contains a single lump-sum CLIN. Please advise whether a unit-price schedule will be added by amendment, or whether these unit prices will be negotiated after award under FAR 52.243-4 / 52.236-2.JCGEstimated quantities are provided in solicitation. Any additional quantities beyond estimate may require an amendment and we may negotiate those additional quantities based on pricing submitted with bid for estimated amount.0002
910/27/2602 83 33.13 1.1Section 02 83 33.13 describes 'potential' removal of lead-based paint. Please provide any XRF/paint-chip data. Please confirm that painted components may be demolished intact and disposed as C&D debris where TCLP results are non-hazardous, with LBP removal limited to OSHA 29 CFR 1926.62 compliance at hot-work/cutting locations.TJFSee regulated building materials survey report by Mabbett & Associates, Inc. in 2021. This will be provided. See attachment: Demolish Boiler Plant V1 - Final Hazmat Report with attachments0002
1010/27/26HA101/HA102 note 9Note 9 makes the Contractor responsible for characterization of ash waste. Please provide any existing sampling data or estimated quantities of ash/residue in the incinerator, scrubber, breeching and ash/cart/truck enclosure (Rm 110). If residues are found to be RCRA-hazardous, please confirm this will be treated as a differing site condition.TJFRefer to regulated building mat. Report for sampling data. Site condition would be same since on the drawing.0002
1110/27/26GI002; AD102 n.7; AD201 n.10For the 111-ft brick chimney and the steel exhaust stack: (a) has the chimney liner/mortar been tested for asbestos; (b) are there known structural deficiencies; (c) may mechanical top-down demolition with an exclusion zone that temporarily closes adjacent drives be used (explosives are prohibited)? (d) inform the average inner diameter of chimney; (e) inform dimensions of chimney foundations and footings; (f) are there any underground tie beams existing; (g) required removal depth of chimney foundations; (e) chimney liner material and its thickness; (h) chimney liner anchorage details.TJFa- refer to building mat report, b-no known def., c-yes, explosives are prohibited, d-h-See asbuilts. File name: B100 asbuilts reduced.0002
1210/27/2602 41 00 3.5.B vs 3.6.E; 31 20 00May clean, non-ACM, TCLP-compliant concrete and masonry from the demolition be processed on site (crushed to a specified gradation) and used as basement/void backfill below the top 24 inches, subject to testing and COR approval? 3.5.B requires daily off-site removal while 3.6.E allows recycled pulverized concrete fill.TJFThe site is limited on size, process off site.0002
1310/27/26ES102 KN6For the fire-alarm fiber backbone work: (a) please confirm the Contractor is to procure JCI services and materials for the new 6-strand fiber and terminations, (b) who performs panel reprogramming and acceptance testing, and (c) what Interim Life Safety Measures / fire watch are required during the loop interruption and whether the cutover must be off-hours.TJFYes JCI services. Coordinate with JCI Services to reroute affected buildings before demolition.0002
1410/27/2601 35 26 1.7; 01 45 0001 45 00 3.4 requires a CQC System Manager on site at all times and a Safety and Health Manager independent of the CQC System Manager. May the Superintendent also serve as the CQC System Manager (meeting 01 45 00 3.4.B qualifications), with a separate full-time SSHO? May the SSHO be the designated alternate CQC System Manager?TJFYes, as long as they qualify for each.0002
1510/27/26HA102 KN7Please confirm whether boiler/incinerator refractory, firebrick and castable linings are non-ACM, or include them in the ACM scope with quantities.TJFSee regulated building materials survey report by Mabbett & Associates, Inc. in 2021. This will be provided.See attachment: Demolish Boiler Plant V1 - Final Hazmat Report with attachments0002
1610/27/26GI004 Rms 103/104; ES101Please inform if supplying 5 kV cables are oil-filled, also please identify any oil-filled transformers or capacitors in the Transformer Room (103), Generator Room (104) and Electrical Room, including PCB status, and confirm that the generator, 5kV switchgear, 5kV cables and transformers are NOT reserved Government property.TJFWe suspect that there are no "oil-filled" electric equipment on VA grounds and none have incurred in the past.0002
1710/27/2601 00 00 1.9; 02 41 00 3.6.C

GI003 KN1

GI004 KN102 41 00 3.6.C states that items to be salvaged are indicated on the drawings; none are indicated, while also it is mentioned in GI003 & GI004 Note 1 that VA grounds equipment will be removed by VA. (a) Please confirm that there are no reserved/salvage items and that all equipment and materials become Contractor property. Otherwise send the list of such equipment / items and advise which require only storage and which need to be reinstalled. (b) Contractor will remove and store / reinstall such equipment/ items only within the perimeter of VA Illiana Healthcare. At the place of reinstallation, it is expected that existing system is fit for relocated equipment/ items i.e. no additional work is envisaged on such existing systems. Re-commissioning of relocated equipment is also not included.TJFThe grounds equipment will be vacated before NTP. Everything else in B100 will be treated as vacated.0002
1810/27/26MS101 photo M1 vs. plan note; CD101 KN10MS101 Photo M1 is labelled 'Cooling Tower by Others', while the MS101 plan note and CD101 Keynote 10 require the demolition contractor to remove the abandoned cooling tower. Please confirm the removal of cooling tower and its piers are in the Contractor's scope.TJFYes, refer to Note 10 on drawing CD101 and Note 1 on MS101 for mechanical demolition.0002
1910/27/2602 41 00 3.7; CG101; 31 20 0002 41 00 3.7.A requires below-grade areas rough-graded 'ready for further excavation or new construction'. Please confirm the compaction requirement for basement backfill (e.g., 90% vs 95% ASTM D1557) and whether the area is intended for future structures.TJFRefer to spec 31 20 00.0002
2010/27/26ES101 KN2 & KN4; ES102 KN4(a) Has the new Power Center (480V panel, transformer, 120/208V panel) near the storage/maintenance canopies been already designed and installed? If not, when is it expected date and will it be procured separately? (b) Please confirm the locations of the Power Center and of the new handholes which is understood to be required regardless if Power Center is ready or not. (c) If existing raceways require extension to Power center, please confirm the shortest route below the permanent seeding area to be considered. (d) Same is presumed also for existing raceways described in ES101 Note 4, if extension is required it would follow the shortest route. Please confirm.TJFa-Yes b-The power center is located west of the temporary building shown on the drawing, across the road, and directly between the two temporary buildings in close proximity. It is a very small building. c-N/A d- Yes, if raceway is required, directly west is the shortest anticipated path.0002
2110/27/26ES101 KN1; 01 00 00 1.10

GI002 KN1

MS101 KN1 and KN2

E002, demolition note 2Boiler plant is described as in “Abandoned state”, also in MS101 it is mentioned that Gas service is disconnected, Water discontinued and Steam abandoned. On the other hand, MS101 KN2 states that coordination is required for Gas work with the facility provider. Also in E-002, demolition note 2 states that plant is operational. (a) Please confirm that Steam and Water utilities are abandoned. (b) Please clarify status of gas connection and what coordination is required with gas provider. (c) Please confirm our understanding that electricity and telecommunications are still in service in the plant. (d) For removal of 5 kV feeders (ckts #3 and #4): will VA's authorized person perform switching, isolation, earthing and padlocking at Main substation SW-MH28A/B and at the B100 switchgear, and what outage windows are available?TJFa- Water and steam is abandoned. b- Gas is in use for heat in south side of building, coordinate removal with ameren. c- yes. d- Yes, VA electrical personnel will oversee and perform the tasks need for disconnection at MH28s and main power switch station(B99). Shutdown for B58 is likely and will need coordinated. The VA would prefer daytime/morning outage so electrical personnel will be available for oversight.0002
2210/27/2601 00 00 1.6; 02 41 00 3.5.FPlease confirm the location and size of the contractor staging/ laydown area (to be 'determined at the pre-bid meeting') and whether the road segment between the cemetery intersection and the main substation entrance may be closed to non-project traffic during demolition.TJFThere is a location for contractors to stage and work from outside the site located on south side of campus on the north/south maintenance road by the south water tower.0002
2310/27/2601 00 00 1.9.A.3; GI004 note 1; SOW records clausePlease confirm that VA will remove all grounds equipment, portable equipment, spare parts, chemicals and any records/documents from B100 before NTP, so that the Contractor does not handle Federal records.TJFYes, the VA grounds crew will vacate and remove all grounds equipment before NTP.0002
2410/27/2632 90 00 1.10; Bid Schedule 180 cdIf the 180-day completion falls outside the seeding season, will VA accept dormant seeding / erosion-control blanket with turf establishment (95% stand) completed under the warranty period?TJFThe current schedule for NTP should allow for the seeding to fall in line in the 180 day completion window.0002
2510/27/26CD101 'utility connection unverified'CD101 notes an unverified utility connection near the west side. Please provide any additional record drawings for utilities entering B100, including the abandoned steam tunnel / force main records dated 7-22-92.TJFSee asbuilts. File name: B100 asbuilts reduced.0002
2610/27/26Hazardous waste manifestsPlease confirm that VA (VA Illiana EPA ID number) will sign as generator on any hazardous waste manifests, with the Contractor acting as the generator's agent.TJFRefer to specifications. The contractor shall apply for and have all required permits and licenses as required by Federal, State, and
Local regulations.0002
2710/27/26Sol. pre-bid / site visitPlease provide the October 20, 2026 site visit minutes, sign-in sheet and any questions and answers from the visit.JCGSee amendment 00010002
2810/27/26ES102 KN2Keynote 2 requires extending circuit #10 from the handhole at pole base to the 'existing manhole shown at street'. Please confirm which manhole is intended (MH 27A or MH 27B) and the approximate route length.ELECThis is a typo on the drawing, use "HANDHOLE" located between 100-8 and 100-9. The route is described with a dark horizontal black line.0002
2910/27/26GI002 general note 1GI002 Note 1 requires professional animal removal services. Please advise whether any animal activity (e.g., bats or protected species) is known, and whether removal of protected species would be treated as a change.TJFWe have on-site pest control and can use this service for standard pest removal.0002
3010/27/2601 00 00 1.4Are extended hours or Saturday work permitted for demolition and abatement (at Contractor's cost) with COR approval?TJFyes0002
3110/27/26WD IL20260002The wage determination (Building) has no truck driver classification. Please confirm whether a conformance request (SF-1444) is required for on-site truck drivers, or whether haul drivers are not covered.JCGSee TEAM0050-002 05/01/2025- Rate $47.71 Fringes $25.720002
3210/27/26Solicitation Item 12a
Special Instruction Cl. 4.15As the progress payments will be processed only on the basis of completed work certified by VA and against the approved Schedule of Cost, it is not clear why additional retention is envisaged in the Contract, noting that the Performance and Payment Bonds are also included in the Contract. Please inform (a) why additional retention is required, (b) methodology for deciding retention value by Contracting officer, and (c) % value of Performance and Payments bonds.JCGRead VAAR 852.232-70. CO may retain but there are no plans for retaininage unless is needed per VAAR clause.0002
3310/27/2601 00 00 1.27If any archeological/ cultural/ historical resources are found in/ below the site, please advise if cost of required works to handle the same would be treated as a change.TJFThat will be determined at time of discovery.0002
3410/27/2602 41 00 1.1Description stipulates demolition of shown utilities/ buildings/ debris /structures. If any unshown or undocumented utilities/ hazardous materials/ debris /structures are found during the execution of works, please advise if removal of the same would be treated as a change (compensation mechanism to be mutually agreed with the Client).TJFIf the described not shown is not on drawings,specs,materials report, rfi answers, or asbuilts it will be treated as additional work and a modification will be used for compensation.0002
3510/27/26CD101 KN6Existing utilities running through/ below the plant (e.g. steam tunnel, drain/ water / gas pipes, storm/ sanitary sewer, unneeded raceways etc.) will be demolished only between points marked with no.6 and capped with concrete in accordance with Note 6. Please confirm.TJFFollow design drawings.0002
3610/27/26CD101 KN19

AD102 KN10 & KN11

MS101 KN1(a) Please clarify the dimension of the steam tunnel running through/ below the plant basement, especially its depth for demolition.
(b) In MS101, note 1, it is stated to coordinate with General Contractor for the length of steam pipe to be removed, please clarify this note.TJFa-See asbuilts. b-See AD102 for steam cap detail/location.0002
3710/27/26CD101Storm sewer manholes around and within the plant will not be demolished as same are not marked for removal in sheet CD101. Only the castings of 2Nos. Storm sewer manholes marked in sheet CS101 will be replaced in line with Notes #3 & #4. Please confirm understanding.TJFFollow design drawings.0002
3810/27/26AD102 KN1, KN2 & KN4Foundation walls (interior and exterior) are stipulated for complete removal. (a) Please clarify if walls are supported on strip footings, piles/ pile caps or raft, and if these shall be demolished (fully or partially). (b) Please inform thickness of basement slab and if it shall be fully removed. (c) If full basement slab removal is required, please inform removal size for filling below the slab. (d) KN4 states that complete equipment curb/ pad shall be removed, please inform the thickness of major equipment curbs/ pads (Incinerator area).TJFRefer to drawings and asbuilts provided.0002
3910/27/26CS101. Restoration KN1Please clarify if it is in Contractor’s Scope to supply and plant the permanent seeding in area marked as per the restoration note #1. Also, please inform the quantity of structural fill required.TJFYes, per note 1 on CS101 permanant seeding is required. Backfill quantity unknown.0002
4010/27/26ES101, Partial site plan #2Works in Illiana Main substation is limited to removal of cables ckts. #4 & #5 and replacement of tags as spares. No other works in Main substation is envisaged (e.g. modification of SLDs and Layout drawings, modifications in Protection and SCADA systems etc.). Please confirm our understanding.TJFCorrect.0002
4110/27/26ES102 KN5 & KN6For the new FO handhole and extension of existing raceways, please confirm the shortest route below the permanent seeding area to be considered.TJFThe known utilities drawing for VA Danville Site will be provided for planning the shortest/easiest route for B69/22 to B68. The shortest route seems to be from B68 along the cemetary road north of B19 and south of B100 to B69/22.0002
4210/27/26Please also confirm that Amendment 0001 (posted October 21, 2026) is the only amendment issued to date.JCGWe are posting amendment 0002 today, November 05, 2026 and there are only two amendments including 0002 as of November 05,2026.0002
4310/27/26The specifications identify approximate asbestos-containing material quantities and require the contractor to verify actual quantities. For bidding purposes, please confirm that bidders may use the quantities identified in Section 02 82 11 and Drawings HA101 and HA102 as the basis for their proposals, and that additional quantities discovered during construction beyond the specified allowances will be addressed through a contract modification.TJFYes, the information in the specifications should be used for bidding purposes. The unknown additoinal quantities will be addressed through contract modification.0002
4410/27/26Please provide any available information regarding the existing underground storage tank, including tank capacity, construction, last known contents, current condition, and any previous environmental testing or remediation. If this information is unavailable, please clarify the assumptions bidders should utilize when pricing tank cleaning, removal, and disposal.TJFRefer to specifications.0002
4510/27/26Specification Section 02 41 00, Paragraph 3.3; Drawings MS101, ES101, and ES102
Please identify which existing utility services associated with Building 100 must remain operational to serve adjacent facilities during demolition. Additionally, please confirm whether temporary utility bypasses are required as part of the base bid and, if so, identify the services and anticipated duration of temporary service.TJFGas shutoff is located on drawing and B100 is isolated from shutoff. Coordinate with Ameren with work to be completed for bid. Electrical can be coordinated with facility electric shop. Fire Alarm, coordinate with JCI Services. Street lights should remain working during dark times of day, possible shutdown on bright daytimes can be approved.0002
4610/27/26Please clarify whether independent third-party asbestos air monitoring, final clearance testing, and associated environmental oversight will be provided by the Government or are required to be included in the contractor's base bid.TJFTo be included in the contractor's base bid.0002
4710/27/26Section 02 65 00 identifies a base-price threshold of 100 cubic yards of soil removal and six testing locations, with additional work subject to unit pricing. Please confirm that bidders are to include no more than 100 cubic yards of contaminated soil removal and six testing locations in their base bid, and that quantities exceeding these thresholds will be measured and compensated using the applicable unit prices as directed by the Contracting Officer's Representative.TJFYes, bid per the section 02 65 00 measurements.0002
4810/27/26Please confirm whether one qualified individual may serve concurrently as the Project Superintendent, Site Safety and Health Officer (SSHO), and Contractor Quality Control (CQC) System Manager, provided the individual meets all applicable qualifications and can fulfill the responsibilities of each position.TJFYes, one individual that is qualified can serve multiple positions as Superintendant, SSHO, and CQC. Refer to specifications for qualification of each position.0002
4910/27/26Please confirm whether a building demolition permit from the City of Danville or other local authority is required for demolition of Building 100 on federal property. If required, please clarify whether the contractor is responsible for obtaining and paying for the permit or whether the VA will provide the necessary approvals.TJFNo permit is needed with the city of Danville or local authority for this project.0002
5010/27/26Please confirm whether the contractor is responsible for obtaining any environmental permits or regulatory approvals beyond those specifically identified in the contract documents, including any required IEPA stormwater/NPDES permits, SWPPP approvals, and environmental permits associated with building demolition and underground storage tank removal. Additionally, please clarify whether the VA will provide any existing environmental permits, investigations, or regulatory approvals applicable to the project.TJFNo additional requirements required outside of specifications/drawings. The VA to follow up on NPDES permit.0002
5110/27/26Does the Superintendent need to be directly employed by the Prime Contractor?TJFYes0002
5210/27/26Must the Superintendent be on site at all times while work is commencing?TJFYes0002
5310/27/26Does the SSHO (Site Safety Health Officer) need to be directly employed by the Prime Contractor?TJFNo0002
5410/27/26Must the SSHO be on site at all times while work is commencing?TJFRefer to spec 01 35 26 1.7.C0002
5510/27/26Can the Superintendent & SSHO be a dual-hatted individual assuming that individual is qualified for both roles?TJFRefer to RFI #480002
5610/27/26Are there any other mandatory on-site supervisory roles required in this contract?TJFNone outside of scope of the specifications.0002
5710/27/26When does the gov expect the project to be awarded following the bid opening?JCGWithin 2 weeks after bid opening.0002
5810/27/26Does the VA anticipate this project starting on-site during winter or waiting until Spring 2027?TJFWinter will not have impact on NTP date.0002
5910/27/26Are there any ICRA requirements for this project?TJFThere is no current ICRA requirements planned for B100 demo project.0002
6010/27/26Is this contract Tax Exempt?JCGYes, See solicitation page 6.0002
6110/27/26Drawing HA 102, Note 6 states to refer to Mabbett & Associates 2021 Survey Report, however this is not provided on SAM. Please provide if possible.TJFThis will be provided.0002
6210/27/26What will waste reporting requirements look like?TJFRefer to specifications.0002
6310/27/26RFI – Asbestos abatement – Drawing HA102 – Please clarify Keynote 8? “remove and dispose of asbestos containing damp proofing” What / where / depth of damp proofing?TJFThis is identified as "black damp proofing" in the building materials survey report. This will be provided for location, quantity, etc.0002
6410/27/26Are there as-built drawings available?TJFSome as-builts from original construction project will be provided.0002
6510/27/26The abatement drawings do not provide clear quantities of how much is located in many of the areas (asbestos, lead, etc). Without quantifiable data, it's hard to estimate. Please provide clearer quantities of hazardous materials for all bidders, as these amounts will sway pricing drastically.TJFThe estimated quantities are in the building materials survey report. This will be provided.0002
6610/27/26Is there a Lead paint survey to show locations of lead paint if any?TJFYes, a lead containing paint survey was part of a regulated building materials survey report by Mabbett & Associates, Inc. in 2021. This will be provided.0002
6710/27/26Are there tunnels associated with abatement work?TJFAll known abatement work for bid purposes have been identified. Any additional work found during project will be addressed through a contract modification.0002
6810/27/26Is there asbestos (amosite) and where is it located?TJFYes, the asbestos was part of a regulated building materials survey report by Mabbett & Associates, Inc. in 2021. This will be provided.0002
6910/27/26What are the details of VA privacy training, where, how long, and is there a cost?TJFThere is a record management powerpoint training for contracts provided by the privacy officer here at the VA. We will provide the powerpoint and require signature to confirm training from contractor.0002
7010/27/26Is there a list for confined space locations?TJFNo.0002
7110/27/26How will furniture, fixtures, equipment, tools, trash, etc. that is left behind be treated as contaminated or not contaminated?TJFNot contaminated.0002
7210/27/26Ref: 01 45 00, Quality Control ManagerWill an onsite QC manager with 20 years supervision experience be acceptable in lieu of a graduate engineer, graduate architect, or graduate of construction management QC Manager?TJFEach case will be evaluated on a case by case basis in leu of the graduate degree requirement.0002
7310/27/26Ref: 01 45 00, Quality Control ManagerPlease confirm that the CQC manager is a separate individual from the prime superintendent/SSHO.TJFRefer to RFI #480002
7410/27/26Please confirm that this will be a triple hat project with one site manager servising as Super/QCM/SSHO.TJFRefer to RFI #480002
7510/27/26Where will the project laydown area be?TJFThere is a location for contractors to stage and work from outside the site located on south side of campus on the north/south maintenance road by the south water tower.0002
7610/27/26Please confirm that this project will be performed during normal working hours. If WHEN hours are required, please identify when these hours will ebr equired.TJFYes, normal working hours are Monday - Friday, 7:30am - 4pm0002
7710/27/26Is there an available asbestos report?TJFRefer to RFI #680002
7810/27/26Is there an available LBP report? Is any LBP known to be at the site?TJFRefer to RFI #660002
7910/27/26Will the project be tax exempt?JCGYes, See solicitation page 6.0002
8010/27/26Drawing sheets are 14” x 8.50” and a number of site sheets are NTS – are full size sheets/fully scaled drawings available?TJFNo fully scaled drawings available. However, there is a CAD file for building 100 where you are free to make your own measurements and scaled drawings0002
8110/27/26Section 3.7.B.3 establishes a base quantity of 100 CY of soil removal and six test locations, with additional work to be compensated through unit pricing. However, the solicitation contains only one lump-sum bid item.
Please confirm that contaminated soil removal exceeding 100 CY and sampling exceeding six test locations will be compensated through a contract modification. Additionally, please clarify whether the 100 CY allowance includes only contaminated soil or all soil excavated for UST removal.TJFYes, refer to spec 3.7.B.3 which is for all soils related to UST. Additional work will be compensated through contract modification.0002
8210/27/26Please provide available records identifying the underground storage tank's capacity, construction, last known contents, current liquid volume, operational status, and any previous environmental assessments or leak investigations. These details are necessary to establish the scope of tank cleaning, removal, and disposal.TJFNo additional records, refer to drawing/specifications.0002
8310/27/26Please confirm whether contaminated groundwater is anticipated within the UST excavation. If encountered, will groundwater characterization, treatment, disposal, and associated excavation dewatering be addressed through a contract modification?TJFPretest soil before removal and test after removal, remediate if found0002
8410/27/26Please confirm that the asbestos and lead-based paint surveys provided with the contract documents encompass all materials anticipated to be disturbed during demolition. If additional hazardous materials are discovered, will the resulting abatement and disposal be addressed through a contract modification?TJFYes concurrent with spec 02.82.11.1.2, additional work will be compensated through contract modification.0002
8510/27/26Please confirm that all utilities serving Building 100 have been identified and that existing utilities serving adjacent facilities will remain operational. Additionally, please clarify whether the Government will perform any required upstream utility isolations or whether all disconnections are the contractor's responsibility.TJFFollow design documents. Refer to RFI# 47.0002
8610/27/26Please confirm the required limits of foundation, footing, basement slab, and below-grade structure removal. Are all below-grade foundations required to be completely removed, or may designated elements remain below the final finished grade?TJFRefer to drawings and specifications.0002
8710/27/26Please clarify the required final site conditions following demolition, including backfill material, compaction requirements, final grades, and whether topsoil, seeding, or additional surface restoration is required throughout the former building footprint.TJFRefer to spec 31 20 00.0002
8810/27/26Please confirm whether existing underground tunnels, vaults, abandoned piping, utility structures, or other subsurface obstructions are known within the demolition footprint. If unidentified underground structures or utilities are encountered, will their removal or relocation be addressed through a contract modification?TJFYes, refer to the drawings for all known utilities and tunnels. Additional utilites not forseen in specifications, drawings, and asbuilts provided with be addressed with a contract modifcation.
8910/27/26Please clarify whether the Government has performed waste characterization testing of the existing building materials and demolition debris. If materials requiring special handling or hazardous waste disposal are identified beyond those expressly documented, will additional costs be addressed through a contract modification?TJFRefer to RFI #660002
9010/27/26Please identify any existing equipment, piping, electrical components, or other materials the Government intends to retain. For items designated for salvage, please confirm the required delivery location and whether the Government will assume custody upon delivery. Or whether the Government will remove prior to the construction phase.TJFNo existing equipment will be retained by the VA. There is grounds equipment in building 100 currently that will be moved before construction and NTP occurs.0002
9110/27/26Please provide any available geotechnical information and foundation drawings for structures adjacent to the demolition limits. Please clarify whether the Government has identified any existing foundations or utilities requiring engineered temporary support during basement and foundation demolition.TJFNo new related information to provide.0002
9210/27/26Specification 02 41 00 requires an engineering survey performed by a Professional Engineer, while Specification 01 35 26 requires a demolition plan as part of the Accident Prevention Plan.
Please clarify whether the Government requires the complete demolition plan, including demolition sequencing, means and methods, and equipment loading, to be developed and stamped by a licensed Professional Engineer, or whether the requirement is limited to a Professional Engineer's structural assessment with the demolition plan and sequencing developed by the demolition contractor.TJFYes, according to the specifications, only the engineering survey is required by PE.0002
9310/27/26Specification 01 74 19 requires the contractor to divert demolition debris from landfills where economically feasible. Section 1.3.C further establishes a minimum 50% recycling requirement for new materials.

Please confirm whether the 50% recycling requirement applies to demolition debris generated from the existing Boiler Plant B100, or only to new construction materials as stated in Section 1.3.C.

Additionally, please clarify whether there is a minimum recycling/diversion percentage required for the overall demolition debris and whether concrete and masonry materials are required to be recycled rather than disposed of at an approved landfill.TJFYes, new materials only as stated in section 1.3.C. No minimum percentage for demolition recyclables. No requirement for concrete/masonry recycling.0002
9410/27/26Please identify all environmental permits, regulatory notifications, and agency approvals required for this project, including asbestos abatement, underground storage tank removal, and stormwater management. Please clarify which permits and notifications will be obtained by the Government and which are the contractor's responsibility.TJFRefer to specifications. The contractor shall apply for and have all required permits and licenses as required by Federal, State, and
Local regulations.0002
9510/27/26Please clarify whether the underground storage tank is currently registered with the appropriate Illinois regulatory agency and whether previous environmental investigations have been performed. Additionally, please confirm whether the contractor is responsible for obtaining regulatory closure documentation and whether any required remediation beyond tank removal will be addressed separately.TJFRefer to specifications. The contractor shall apply for and have all required permits and licenses as required by Federal, State, and
Local regulations.0002
9610/27/26Please clarify whether the contractor is responsible for all required asbestos demolition and abatement notifications, third-party air monitoring, final clearance testing, and associated regulatory fees, or whether any of these services will be provided by the GovernmentTJFThe contractor is responsible.0002
9710/27/26Please confirm whether the anticipated limits of disturbance require coverage under an Illinois EPA construction stormwater permit. If applicable, please clarify whether the contractor is responsible for preparing the Stormwater Pollution Prevention Plan (SWPPP), obtaining permit coverage, performing inspections, and completing permit closeout.TJFRefer to specifications. The contractor shall apply for and have all required permits and licenses as required by Federal, State, and
Local regulations.0002
9810/27/26The specifications require the contractor to retain a Professional Geotechnical Engineer to perform periodic inspections, evaluate excavation and groundwater conditions, maintain excavation and dewatering plans, and provide monthly reports.
Please confirm whether these requirements apply to the demolition and backfilling operations associated with Building 100, including the UST excavation, or whether they are intended for new construction activities not included in this project.TJFYes, concur with specifications.0002
9910/27/26Please clarify the required frequency and locations of field density testing for backfill associated with the building demolition, foundation removal, and UST excavation. Additionally, please confirm whether the contractor is responsible for retaining an independent testing laboratory for all compaction testing.TJFFollow specifications.0002
10010/27/26The specifications identify contractor pre-clearance sampling and final clearance testing performed by the VPIH/CIH, with certain laboratory services provided by the VA.
Please clarify which asbestos monitoring, clearance testing, and laboratory analysis services are to be provided by the Government versus the contractor, including responsibility for the associated costs.TJFRefer to Specifications.0002
10110/27/26The specifications require a minimum 7-foot-high chain-link construction fence around the construction areas indicated on the drawings.
Please confirm the required limits and approximate linear footage of temporary construction fencing, including the required number and locations of access gates. Additionally, please clarify whether freestanding temporary fence panels with weighted bases are acceptable in lieu of permanently installed fence posts.TJF6' temporary fencing with weighted bases will suffice.0002
10210/27/26Please identify the designated construction access points and approved haul routes for demolition debris removal, including any restrictions on truck sizes, vehicle weights, or hours of operation.
Additionally, please confirm whether existing Medical Center roadways are suitable for the anticipated heavy demolition equipment and loaded debris trucks, or whether temporary roadway improvements and protective measures will be required.TJFUse the VA service entrance which is north/south road which is adjacent to building 100.0002
10310/27/26Please identify the designated contractor staging and laydown areas available for demolition equipment, debris containers, material stockpiles, and temporary facilities.
Additionally, please confirm whether these areas will be available exclusively to the contractor throughout the entirey of the construction phase.TJFThere is a location for contractors to stage and work from outside the site located on south side of campus on the north/south maintenance road by the south water tower.0002
10410/27/26Please confirm the Superintendent can have any shared duties as a SSHO.TJFRefer to RFI #480002
10510/27/26Please confirm the QCM shall not have any shared duties as the SSHO, Superintendent or any other role on the project.TJFRefer to RFI #480002
10610/27/26Spec section 06 10 00 rough carpentry is called out but there is no rough carpentry shown in drawings. Please confirm if it’s required or not.TJFSee drawing AD102 detail 2.0002
10710/27/26Please provide the soil report and confirm if asbestos is present in the soil.TJFNo soil report. Refer to specifications for testing.0002
10810/27/26Does VA have Lead Based Paint report? A lot of the paint during site walk looked suspicious but it’s not mentioned in the Asbestos Spec. Please confirm.TJFRefer to RFI #660002
10910/27/26Drawings GI003 and GI004 states, “The VA Grounds Keeping Equipment Will be Removed by the VA, Prior to Demolition”. Please confirm which equipment falls under this statement.TJFOil drums, Fluid storae, Storage containers, storage lockers, vehicles, tools, lifts, tool boxes and grounds equipment accessories, etc.0002
11010/27/26Please confirm if the refractory brick inside of the boilers tested for ACM?TJFThe yellow fire brick for Boilers 1-3 were tested. See egulated building materials survey report by Mabbett & Associates, Inc. in 2021. This will be provided.0002
11110/27/26Please confirm if the bricks / materials inside of the incinerator ever tested for ACM?TJFSee egulated building materials survey report by Mabbett & Associates, Inc. in 2021. This will be provided. Nothing indicates testing of the incinerator. Refer to page 15 (drawing RBM-1) in report.0002
11210/27/26Can the Asbestos survey be provided in full?TJFRefer to RFI #680002
11310/27/26Please provide drawings for the existing conditions.TJFThe drawing set provided is most recent.0002
11410/27/26In reference to the following Note #7 found on drawing HA102, what are the setting and packing materials referring to? Is this inside or outside of the boiler?
TJFSee regulated building materials survey report by Mabbett & Associates, Inc. in 2021. This will be provided.0002
11510/27/26Please provide the environmental assessment that was conducted to determine areas of asbestos and lead?TJFSee regulated building materials survey report by Mabbett & Associates, Inc. in 2021. This will be provided.0002
11610/27/26Lead-Based Paint Removal and Disposal Spec section 02 83 33.13 has been included. The drawings only show the asbestos abatement work, but nothing indicates where any lead material may be located. What existing materials contain lead? Please provide testing reports.TJFRefer to RFI #660002
11710/27/26Please advise of any nearby facilities that may be affected by the noise and/or vibration created during demolition or site restoration work? If any, please advise of any measures that are to be taken.TJFNone.0002
11810/27/26Will any nearby facilities require us to utilize noise and/or vibration monitoring devices?TJFNo.0002
11910/27/26Will any nearby facilities require settlement monitoring prior to and during demolition or site restoration work?TJFNo.0002
12010/27/26If a Prime Contractor is awarded multiple projects at the same VA Medical Center location: Can the Superintendent be shared across multiple projects at the same site/location, or should they only be dedicated full-time to this project only?TJFYes they can.0002
12110/27/26Can one person serve as the Superintendent, Quality Control Manager, & the SSHO?TJFRefer to RFI #480002
12210/27/26Can the Superintendent also serve as the Quality Control Manager

A.

If the Super can’t be the QCM, is the QCM required to be onsite full-time, or can they make site visits as required for inspections?

B.

If the Super can’t be the QCM and the QCM is required to be onsite full-time, should they be assigned to this project only, or can they be assigned to another project as well on the same property?

C.

If the Super can’t be the QCM, can a subcontractor fulfill the QCM role?TJFyes, a-refer to spec 01 45 00 3.4.B. b- multiple projects are allowed for super. c- employed by the general contractor0002
12310/27/26Can the Superintendent also serve as the Site Safety & Health Officer (SSHO)

A.

If the Super can’t be the SSHO, is the SSHO required to be on-site full-time, or can they visit the site daily for safety inspections?

B.

If the Super can’t be the SSHO and the SSHO is required to be onsite full-time, should they be assigned to this project only, or can they be assigned to another project as well on the same property?

C.

If the Super can’t be the SSHO, can a subcontractor fulfill the SSHO role or does the SSHO need to be directly employed by the General Contractor?TJFYes if it meets qualifications., a,b- Refer to spec 01 35 26 1.7.C. c- N/A0002
12410/27/26Can the SSHO also serve as the QCM?TJFRefer to RFI #480002
12510/27/26Will the VA issue an Administrative NTP for preconstruction activities, including subcontracting, scheduling, and submittals, before issuing the construction NTP? If not, please confirm these activities must be completed within the 180-calendar-day period of performance.TJFAll activity is expected within the 180 day timeframe.0002
12610/27/26Please provide call-in details and instructions for the bid opening to ensure transparency for all bidders.JCGSee solicitation page 5 for bid opening instructions. There is no call-in number.0002
12710/27/26Please confirm whether fire alarm programming, terminations, and testing must be performed by the VA's existing fire alarm contractor. If so, please provide the contractor's contact information.TJFYes, JCI Services.0002
12810/27/26Please confirm whether standard exterior dust suppression and site containment will satisfy ICRA requirements. If additional measures, including temporary fire-rated partitions, negative air, or specialized containment, are required, please identify their locations and requirements.TJFStandard dust suppression and site containment will satisfy.0002
12910/27/26Please identify any work required outside normal working hours, including utility shutdowns, tie-ins, and crane operations, and specify applicable restrictions.TJFNo known work to be performed outside normal working hours.0002
13010/27/26Please identify the available electrical connection point, voltage, and amperage for temporary construction power. Is a 208V, 125A connection available? Please clarify whether the contractor must provide a temporary pole, meter, breakers, or underground feeder, including any required pavement crossings.TJFUse power center mentioned in RFI# 20. Contractor is to provide all temporary power equipment if needed. There is pavement between B100 and the power center location.0002
13110/27/26Will the VA provide space for the Prime Contractor’s Superintendent to set up, or should we add costs to our bid for a mobile office?

A.

Where can the mobile office be located?

B.

Is space available for a 8’ x 40’ temporary ground-level office?

C.

Are contractors required to set a pole and meter for electric usage in the mobile office?

D.

Where is the electrical connection for power to the mobile office?

E.

What is the distance between the electrical connection and the proposed location of the mobile office?

F.

Is a 208V, 125A breaker available for connection to the mobile office?TJFNo VA provided space, mobile office space available. a-c: Contractor row for mobile sites is located south of B41. d: The 2nd northmost mobile site is where the connection point is located. e: This will be based on the available space amongst other contractor mobile sites. But the available space starts adjacent to the connection point and doesn't cross roads. F: Evaluate with Glesco Electric, they are first trailer by connection point.0002
13210/27/26Where are the designated contractors' and subcontractors' parking area?TJFThere is available parking space by the demo site. North and west of B100 is parking lot.0002
13310/27/26Where shall contractor dumpsters be located?TJFDumpsters can be located on the grounds near B100.0002
13410/27/26If required, can Porta Johns be placed within a 100’ radius of the job site / work area?TJFYes0002
13510/27/26Is temporary construction fencing required anywhere on the project or at the laydown area?

A.

If required, please confirm that 6’ tall temporary construction fencing is acceptable. We ask this because the standard VA specification is a minimum of 2.1m (seven feet) tall, which is not an industry standard height and would require a custom fence to be made at that height. Alternatively, an 8’ high fence generally tends to blow over even B2 Constructors RFI Questions Page 3 of 4

with sandbags on the bases when the fabric is required to be fastened to the fence, since 8’ tall panels with fabric have to potential to cause damage to property and injury to personal, we strongly recommend using 6’ tall temporary construction fencing.TJFYes, around B100 during demolition of outside structures. 6' fencing will suffice0002
13610/27/26Can contractors perform crane lifts during regular hours?TJFYes0002
13710/27/26Can utility tie-ins be performed during regular hours?TJFYes0002