RFI QUESTIONS AND ANSWERS FOR PROJECT 550-20-121 .docx
DOCX document 20 KB Posted
- Solicitation number
- 36C25227B0002
About this file
This is a Questions and Answers document for RFI (Request for Information) related to solicitation 36C25227B0002, concerning the demolition of Old Boiler Plant B100 at a Department of Veterans Affairs facility under Veterans Integrated Service Network 12. The document, dated October 21, 2026, addresses bidder inquiries regarding site visit scheduling, bid submission procedures, and deadline confirmation.
Key administrative details include: the bid due date is November 18, 2026 at 1:00 PM Central Standard Time, with no pending amendments affecting this deadline; a single mandatory site visit was conducted on October 20, 2026 at 11:00 AM with no additional site visits planned; bid submissions must be submitted in person or by mail in sealed envelopes only, with electronic submissions explicitly not accepted; and all bids must be addressed to Juan C. Gaytan at the Great Lakes Acquisition Center (GLAC), 115 S. 84th Street, Suite 101, Milwaukee, WI 53214-1476. Amendment 1 was posted on October 21, 2026 with no changes to bid submission requirements or deadlines.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation # 36C25227B0002 550-20-121 Demo Old Boiler Plant B100 (CON) RFI Questions and Answers (As of 10/21/2026)
Question #: 01 Would the VA consider approving a second site visit at some point prior to the November 18, 2026 bid deadline? Alternatively, would it be possible to arrange individual site visits for subcontractors who are unable to attend on October 20?
Answer: No, there are no plans for a second site visit for this project besides the Site visit conducted on October 20, 2026 at 11am.
Question #: 02 We are unable to attend the pre-bid meeting and site visit scheduled for Tuesday, October 20th at 11AM. Would it be possible to schedule a second meeting/visit for the following week? Possibly on the 27th or 28th?
Answer: No, there are no plans for a second site visit for this project besides the Site visit conducted on October 20, 2026 at 11am.
Question #: 03 Please confirm that bid opening stands at 18 November 2026 at 1:00 PM Central, and that no amendment is pending that would move it.
Answer: Yes, the bid due date is November 18, 2026, at 1pm CST. We are posting amendment 1 today, October 21, 2026 and there are no changes to the bid due date.
Question #: 04 The presolicitation notice of 22 September stated that a pre-bid conference would be held and that details would be included in the solicitation package. Please confirm the date, time and location, and how to register. If those details are already in the posted package, point me to the file and page and I will take it from there.
Answer: The Site visit was listed on SF 1442 Page 1 and page 4. Site visit was conducted on October 20, 2026 at 11am. There are no plans for a second site visit for this project.
Question #: 05 Please confirm the address and method for bid submission, and whether bids are accepted electronically.
Answer: Per solicitation instructions (See page 4 and 5), No email bid submissions will be considered, only in person hard copy and mailed bid submissions will be accepted. All submissions must be received no later than the required bid due date and time. All submissions must be received in a sealed envelope and addressed to the following:
ATTN: Juan C. Gaytan Solicitation: 36C25227B0002 Great Lakes Acquisition Center (GLAC) 115 S. 84th Street, Suite 101 Milwaukee, WI 53214-1476
File details come from the government source that posted it. Updated .