Attachment 2 - Pre-Bid RFI 550-26-205 answered final.xlsx

XLSX spreadsheet 18 KB Posted

Attached to
Z1LB--550-26-205 Pavement Maintenance and Repair and Striping
Solicitation number
36C25226B0021
Issued by

About this file

This file is a Pre-Bid Request for Information (RFI) Q&A document for solicitation 36C25226B0021 addressing pavement maintenance, repair, and striping services at a VA Danville facility. The document contains 66 numbered questions submitted by contractors (Panacea Construction Group, Construction Solutions, TimeBuilt Solutions, Troop Contracting, and IMS) between April 20 and May 21, 2026, with corresponding answers provided by the VA.

Key technical clarifications include: crackfill work is limited to cracks up to 1 inch wide with larger cracks filled with asphalt; cracks require only compressed air blowing (no routing); all roads and parking lots in the contract scope require both cracksealing and sealcoating with two coats of IDOT-approved sealer; striping is required in all areas with handicap parking spots painted blue; asphalt mix specifications allow IDOT IL-9.5, N50, "C" Surface mix with RAP above 25% and MC-30 prime coat; and parking spot designations should match existing markings unless directed otherwise by the Contracting Officer Representative (COR). Operational requirements specify that one parking lot can be closed at a time for resurfacing while up to three can be resealed simultaneously, with adjacent lots prohibited from simultaneous closure; work during normal business hours is permitted with proper traffic control, though weekend and night work are allowed with COR coordination and two weeks' notice for lot closures. Staffing provisions allow a Superintendent to be dual-hatted with the Site Safety Health Officer if properly qualified, and a QC manager with 20+ years supervision experience is acceptable in lieu of a graduate engineer. The VA will provide a tax exemption certificate, water for equipment (with backflow preventers required), drawings and site maps, and a laydown area for equipment storage between phases, though contractors must provide their own stencils for any lettering or numbers.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Pre-Bid RFIs

550-26-205 Pavement Maintenance and Repair and Striping
Pre-Bid RFIs - 36C25226B0021
No.Date SubmittedRequested By: (Name of Firm)SUBJECT/COMMENTAmendment #
14/20/26Panacea Construction GroupDoes the Superintendent need to be directly employed by the Prime Contractor?Amend 0004No
24/20/26Panacea Construction GroupMust the Superintendent be on site at all times while work is commencing?Amend 0004yes
34/20/26Panacea Construction GroupDoes the SSHO (Site Safety Health Officer) need to be directly employed by the Prime Contractor?Amend 0004no
44/20/26Panacea Construction GroupMust the SSHO be on site at all times while work is commencing?Amend 0004yes
54/20/26Panacea Construction GroupCan the Superintendent & SSHO be a dual-hatted individual assuming that individual is qualified for both roles?Amend 0004The VA will accept the superintendent as SSHO provided that adequate qualifications are provided.
64/20/26Panacea Construction GroupWill a tax exemption certificate be provided to the awarded contractor?Amend 0004yes a tax exemption certificate will be provided to awarded contractor
74/20/26Panacea Construction GroupAre there any ICRA requirements for this project?Amend 0004no
84/20/26Panacea Construction GroupWill any plans or drawings be provided?Amend 0004yes
94/20/26Panacea Construction GroupWill a map be provided of each area to be worked in and which type of service will be required in each area?Amend 0004yes
104/20/26Panacea Construction GroupIs work expected to take place after hours/weekends? What are the expected working hours? Do the hours differ depnding on parking lot/road?Amend 0004Work to be done during normal business hours, see specs. Working hours are standard across the project. Weekend work is allowed but must be coordinated with COR.
114/20/26Panacea Construction GroupHow many parking lots/roadways are allowed to be down at a given time?Amend 0004One parking lot can be closed at a time for resurfacing. Up to 3 parking lots can be resealed at once. Adjacent parking lots cannot be closed at the same time. Road work should allow for normal operation of the hospital. All closures must be approved by COR.
124/20/26Panacea Construction GroupWill each work area be totally shut down to VA visitors while they are worked onAmend 0004work areas must be closed off by contractor with proper detour signage
134/20/26Panacea Construction GroupDoes each work area need to be surrounded by temporary fencing, or will cones/barricades for drivers suffice?Amend 0004Cones and barricades will suffice, caution tape should be used when appropriate.
144/20/26Panacea Construction GroupHow will this project be phased? Need to know how many mobilizations.Amend 0004Phasing will be up to contractor and COR approval.
154/20/26Panacea Construction GroupCan we store equipment on site between phases?Amend 0004There will be a laydown area provided to contractor
164/20/26Panacea Construction GroupWhere will this be located?Amend 0004See attachment "550-26-205 Parking lot, road, and laydown area"
174/20/26Panacea Construction GroupIs a secured temporary fence required for laydown areas?Amend 0004no
184/20/26Panacea Construction GroupWill Water be provided for rollers and grinder? Will there be a charge for water?Amend 0004Water will be available, contractor will not be charged for water. Back flow preventers shall be used at hydrants.
194/20/26Panacea Construction GroupAre we routing the cracks or just clean and fill?Amend 0004Clean and fill
204/20/26Panacea Construction GroupAre we responsible for any testing?Amend 0004yes
214/20/26Panacea Construction GroupCan we have a drop tanker on site for sealer?Amend 0004yes
224/20/26Panacea Construction GroupCan lineal feet be provided for crackfills?Amend 0004no
234/20/26Panacea Construction GroupNeed clarification for all Crackfill limits?Amend 0004Crackfill limit is 1 inch any thing bigger than 1 inch should be filled with asphalt.
244/20/26Panacea Construction GroupIs Curb painting required? If so, please quantify for bidding purposesAmend 0004no
254/20/26Panacea Construction GroupWill all Roads & Parking Lots be crackfilled & sealcoated?Amend 0004All roads included in contract will be cracksealed and sealcoated
264/20/26Panacea Construction GroupWill there be an additional RFI deadline after drawings are provided?Amend 0004Drawings were posted via Amend 0001/ RFI Due date was changed to 5/5/2026.
274/20/26Panacea Construction GroupWe understand there are differences between VA standards for DA parking designation and the MUTCD. Will there be a detail confirming which standard to use?Amend 0004Parkings spots shall be painted the same as existing unless otherwise directed by COR.
284/20/26Panacea Construction GroupWill cracks need to be routed prior to sealing or just blown with compressed air?Amend 0004Blown with compressed air
294/20/26Panacea Construction GroupTypically, we use an IDOT IL-9.5, N50, “C” Surface mix with RAP above 25% which leads to a reduction in the asphalt binder from PG64-22 to PG58-28 per IDOT specifications. (See attached) Will this mix be acceptable for this project?Amend 0004yes
304/20/26Panacea Construction GroupThe project specifications call for MC-250 prime coat on the aggregate. We typically use MC-30 according to IDOT Specs. Will this be permitted?Amend 0004yes
314/20/26Panacea Construction GroupIf there are any letters or numbers that get painted will the VA supply necessary stencils?Amend 0004no
324/20/26Panacea Construction Groupwould it be possible to receive a Google Earth view or similar reference showing the areas associated with each of the four task typesAmend 0004drawings were provided
334/27/26Construction SolutionsYou mention sealing, but there are no areas listed below in the task that call out for sealingAmend 0004SOW has been amended
344/27/26Construction SolutionsThere is no type of sealer called out for.Amend 0004Use sealer approved by Illinois Department of Transportation (IDOT).
354/27/26Construction SolutionsI have never heard of a troweled-on sealer, explain what this is.Amend 0004disregard troweling
364/27/26Construction SolutionsDo you have a drawing of the lots needing attention? :see attached pictureAmend 0004Drawings were posted via Amend 0001/ RFI Due date was changed to 5/5/2026.
374/28/26Panacea Construction GroupIs the VA going to provide bid quantities or have actual plans for us to use for takeoffs? Or do we base our bid on the original approximate SOW quantity of 307,580 s.f.?Amend 0004See Updated SOW for corrected square footage. Bid on approximate square footage provided in SOW.
384/28/26Panacea Construction GroupWhat if there is a significant difference between what is on the map and what was in the SOW?Amend 0004SOW has been amended to match map
394/28/26Panacea Construction GroupIs there a difference between the red parking areas and the red parking areas on the map?Amend 0004Red is areas that will be resurfaced and green are areas that will be resealed
404/30/26TimeBuilt SolutionsCan you clarify the limits of crackfill work? Specifically, which areas are included and what the acceptable crack width thresholds are for treatment.Amend 0004Crackfill limit is 1 inch.
414/30/26TimeBuilt SolutionsAre parking lots and roads required to be completed after hours and on weekends to avoid disruption to VA operations, or is daytime work permitted with proper traffic control in place?Amend 0004Daytime work is permitted with proper traffic control.
424/30/26TimeBuilt SolutionsIs curb painting included in the scope of work? If so, please clarify the extent and any color requirements.Amend 0004no
434/30/26TimeBuilt SolutionsWill all roads and parking lots on the project site be crackfilled and sealcoated, or is the scope limited to specific areas? Please confirm whether any areas are excluded.Amend 0004See drawings for scope.
444/30/26TimeBuilt SolutionsWhen will the full drawing set be made available, and what is the deadline for submitting RFIs following receipt of drawings?Amend 0004Drawings were posted via Amend 0001/ RFI Due date was changed to 5/5/2026.
455/5/26Panacea Construction GroupCan the VA specifically call out Crackfill limit at roads by loop road contract?Amend 0004Crackfill limit is 1 inch.
465/5/26Panacea Construction GroupAlso which areas on addenda2 map are for milling, green or red?Amend 0004Red is areas that will be resurfaced and green are areas that will be resealed
475/5/26Panacea Construction GroupCan the colors on the map be defined?Amend 0004Red is areas that will be resurfaced and green are areas that will be resealed
485/5/26Construction SolutionsWill you be posting another amendment with the actual scopes of work and products you want?Amend 0004done
495/5/26Construction SolutionsWhat type of sealer do you want?Amend 0004Use sealer approved by Illinois Department of Transportation (IDOT).
505/5/26Construction Solutions2.4 SEALER specifies a “consistency suitable for troweling”. I have never heard of a sealer that you trowel on.Amend 0004disregard troweling
515/5/26Construction SolutionsHow many coats of sealer do you want?Amend 00042 coats
525/5/26Construction SolutionsWhich tasks below require asphalt paving?Amend 0004Red is areas that will be resurfaced and green are areas that will be resealed
535/5/26Construction SolutionsWhat type of asphalt do you want?Amend 0004See question 32.
545/5/26Construction SolutionsWhich areas do you want crack filled?Amend 0004Green shaded areas
555/5/26Construction SolutionsWhich tasks require striping? Which lots will be striped so we know how to count the stripes?Amend 0004All areas will require striping
565/5/26Construction SolutionsWhich areas in these tasks do the square footage provided correspond to on the site?Amend 0004See drawing and updated SOW.
575/5/26Construction SolutionsThe parking map provided does not specifically show anything.Amend 0004See drawing and updated SOW.
585/7/26Troop ContractingWe understand there are differences between VA standards for ADA parking designation and the MUTCD standards. Will there be a detail confirming which standard to use?Amend 0004see question 30.
595/7/26Troop ContractingWill cracks need to be routed prior to sealing or just blown with compressed air?Amend 0004compressed air
605/7/26Troop ContractingTypically, we use an IDOT IL-9.5, N50, “C” Surface mix with RAP above 25% which leads to a reduction in the asphalt binder from PG64-22 to PG58-28 per IDOT specifications. (See attached) Will this mix be acceptable for this project?Amend 0004see question 32
615/7/26Troop ContractingThe project specifications call for MC-250 prime coat on the aggregate. We typically use MC-30 according to IDOT Specs. Will this be permitted?Amend 0004see question 33
625/7/26Troop ContractingIf there are any letters or numbers that get painted will the VA supply necessary stencils?Amend 0004no
635/7/26Troop ContractingThere are few available empty spaces to relocate cars to in other lots. Will night work be permitted? Will it be required?Amend 0004Night work is allowed. Each parking lot will require a 2 week notice for closure,
645/7/26Troop ContractingWhat are the actual quantities for pavement marking per lineal foot, crack sealing per lineal foot, asphalt milling, and paving. We only have an approximate quantity given in the SOW.Amend 0004see question 40
655/12/26IMSRef 01 45 00- Will an onsite QC manager with 20 plus years supervision experience be acceptable in lieu of a graduate engineer, graduate architect, or graduate of construction management QC Manager ?Amend 0004yes
665/12/26IMSRef specification 01 35 26 & 01 45 00- Can the superintendent cover roles of the safety manager and the QC manager for this project?Amend 0004yes
665/21/26VAIs there a Specific Color needed for Handicap Parking spots?Amend 0004Handicap blue should be used for Handicap parking spots. Paint colors shall be approved by COR before construction.