Questions from potential Offerors in response to 36C25225Q0484
| Q: |
| Can you please provide a more detailed breakdown of the required inspection and testing procedures? The current documentation lacks specificity, making it difficult to fully understand the extent and expectations of this component. |
| R: |
| Refer to revised Statement of Work. Section 4, letters F & G. |
| Q: |
| If available, could you also provide any test reports or documentation from prior inspections? These would be extremely helpful in giving us context and aligning our proposal with past performance and expectations. |
| R: |
| Previous inspection report to be provided as attachment. |
| Q: |
| Could you please provide the one-line drawings for this project? |
| R: |
| One-line drawings to be provided as attachment. |
| Q: |
| We were not able to send personnel to attend the scheduled site visit yesterday, would it be possible to schedule an additional visit? |
| R: |
| Currently there is no plan to host an additional site visit. |
| Q: |
| On the Equipment List document In the Transformers Table - 2 and Switches, Air, Medium-Voltage, Metal-Enclosed Table - 4, we observed a column labeled “Circuit.” Could you please clarify the meaning of this column? Does it indicate the quantity of the equipment, or does it specify that the particular equipment is fed from this circuit? |
| R: |
| The column labeled “Circuit” specifies that the particular equipment is fed from this circuit. |
| Q: |
| Are 3" x 5" labels acceptable? (regarding the AF study labels that will be attached to the equipment) |
| R: |
| Yes, provided all the information is included and legible. |
| Q: |
| Electrical maintenance and power system analysis. Does the electrical maintenance part consist only of inspection and infrared scanning? |
| R: |
| Refer to the revised Statement of Work. Section 4, letters F & G. |
| Q: |
| Do circuit breakers need to be tested? |
| R: |
| Yes, according to the equipment list provided as an attachment. |
| Q: |
| Will any primary injection or secondary injection testing be required for Low Voltage Circuit Breakers? Which one? |
| R: |
| Yes, test functions of the trip unit by means of primary current injection testing. |
| Q: |
| Regarding tests on medium voltage transformers, if tests are required, are oil sampling, inspection and IR Scan sufficient? |
| Q: |
| If the answer to the previous question is no, should we perform tests for Polarization Index, Excitation Current, Turns Ratio, Insulation and Winding Resistance on the transformers? |
| R: |
| Please perform the following tests for medium voltage transformers: |
· Perform an insulation resistance test on each winding and winding to ground.
· Oil Sample for the following: Dielectric Breakdown, Acid #, Interfacial Tension, Color, Visual.
· Dissolved‐gas Analysis (DGA) Oil Sample.
· Perform resistance measurements through bolted connections with a low‐resistance ohmmeter.
· Perform turns‐ratio tests on “as‐found” tap positions.
· Measure core insulation resistance at 500 volts dc if the core is insulated and the core ground strap is removable.
· Test transformer neutral grounding impedance device, if applicable.
| Q: |
| Is it necessary to perform a complete test on the relays (i.e., long-time, short-time, instantaneous functions, etc.)? |
| R: |
| Please perform the following tests for the relays: |
· Apply voltage or current to all analog inputs and verify correct registration of the relay meter.
· Perform mechanical and functional operation checks.
· Perform testing of the protective relays in accordance with manufacturer recommendations.
· Verify the protective relays trip their associated main circuit breaker.
| Q: |
| What tests are required on MV Cables? |
| R: |
| Please perform the following tests for MV Cables: |
· Perform insulation‐resistance test on each conductor with respect to ground.
· Perform a shield continuity test on each power cable.
| Q: |
| Total number of facilities included in the scope of work and their respective square footages |
| R: |
| Total number of facilities included = 29. Individual square footage is as follows: |
· Building 14 – 25,193 SF
· Building 19 – 33,405 SF
· Building 22 – 11,247 SF
· Building 25 – 4,464 SF
· Building 49 – 6,198 SF
· Building 58 – 119,965 SF
· Building 60 – 5,974 SF
· Building 64 – 7,404 SF
· Building 69 – 8,638 SF
· Building 72 – 7,020 SF
· Building 93 – 596 SF
· Building 98 – 125,919 SF
· Building 99 – 405 SF
· Building 101 – 85,045 SF
· Building 102 – 85,590 SF
· Building 103 – 87,195 SF
· Building 104 – 62,772 SF
· Building 125 – 11,391 SF
· Building 128 – 7,982 SF
· Building 129 – 7,982 SF
· Building 130 – 10,570 SF
· Building 131 – 10,570 SF
· Building 132 – 10,744 SF
· Building 133 – 10,744 SF
· Building 140 – 17,072 SF
· Building 211 – 2,679 SF
· Building 212 – 2,599 SF
· Building 214 – 1,876 SF
· Building 216 – 1,995 SF
| Q: |
| Provide Panelboard locations per area or building, if available |
| R: |
| Refer to the one-line drawings and 6390 drawings. |
| Q: |
| Provide cable lengths between equipment and panels, if known |
| R: |
| Information provided on one-line drawings. |
| Q: |
| Provide status of overall online electrical drawings – are updated versions available for review? |
| R: |
| One-line drawings to be provided as attachment. |
| Q: |
| Is a site visit required or recommended? |
| R: |
| The site visit is open to all vendors and is not required. |
| Q: |
| If so, please confirm the date(s), location(s), and access procedures. |
| R: |
| The site visit information was provided in the Solicitation document. |
| Q: |
| What is the expected timeline for completion of the study and deliverables? |
| R: |
| The period of performance is expected to be 6 months or less. |
| Q: |
| Are there any known restricted areas or clearance requirements we should be aware of? |
| R: |
| Coordination will be required to access any OIT areas. The contractor shall coordinate access with COR. |
| Q: |
| Are existing one-line diagrams accurate and up to date, or will field verification be expected as part of the scope? |
| R: |
| One-line drawings were updated during the last inspection (2022). Contractor to note any discrepancies. |
| Q: |
| Are there existing equipment nameplate data or breaker settings available electronically? |
| R: |
| Refer to the one-line drawings. |
| Q: |
| Will a coordination study or protective device settings review be part of the deliverables in addition to the arc flash study? |
| R: |
| Yes, both a coordination study and protective device settings review are required as part of the deliverables. |
| Q: |
| Is infrared thermography expected as part of the inspection and testing scope? |
| Q: |
| What specific type(s) of cable testing is required for this project? |
| R: |
| Please perform the following tests for Medium – and – High Voltage Cables: |
· Perform insulation‐resistance test on each conductor with respect to ground.
· Perform a shield continuity test on each power cable.
| Q: |
| Will the cables be accessible for testing, and are we expected to enter manholes to perform this work? |
| R: |
| Our switches are located above ground. Cables should be able to be tested at termination points in switches, transformers, and switchgear. T99 cables to main substation owned by Ameren Illinois testing and/or outage to be coordinated with Ameren. |
| Q: |
| If access to manholes is required, can you confirm whether the cable terminations are present at those locations? |
| Q: |
| For the infrared (IR) portion of the testing, will someone from the VA be available to open up the electrical cabinets, or will Contractor staff be responsible for providing a technician to do so? |
| R: |
| VA staff will provide access to equipment. Contactor to provide appropriate PPE for rating of equipment. |
| Q: |
| Have specific electrical tests been established for the various types of equipment or are we to quote all NETA recommended tests. |
| R: |
| Refer to the revised Statement of Work. Section 4, letters F & G. |
| Q: |
| Please provide details on the requirement of ‘System Function Tests’ referenced in Letter A of the scope of work. |
| R: |
| Refer to the revised Statement of Work. Section 4, letters F & G. |
| Q: |
| Please provide the type of tests required for the cable testing and description of location/access to cable terminations. Are there confined space requirements to be considered. |
| R: |
| Our switches are located above ground. Cables should be able to be tested at termination points in switches, transformers, and switchgear. T99 cables to main substation owned by Ameren Illinois testing and/or outage to be coordinated with Ameren. |
pg. 2