36C25224Q0416 0001.docx

DOCX document 20 KB Posted

Attached to
H259--ELECTRICAL DISTRIBUTION SYSTEM TESTING BASE + 2 OYS Federal contract opportunity
Solicitation number
36C25224Q0416
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 12

About this file

This document is an amendment to Solicitation 36C25224Q0416 for Electrical Distribution System Testing at the Milwaukee VA Medical Center. The amendment provides answers to questions submitted by offerors, incorporates a Construction Safety Guidebook as Attachment G, and corrects the number of option years from 4 to 2. The solicitation close date has been extended to May 22, 2024 at 10:00 AM local time. The contract structure is a base year (2024-2025) with 2 option years. Key details include that secondary injection testing can be used for bolt-on circuit breakers, subcontractors must be identified and accepted prior to work execution, and no drawings or one-line diagrams will be provided. Work is to be scheduled during nights and weekends to minimize disruptions.

View the file

Other files for this federal contract opportunity

Other files attached to H259--ELECTRICAL DISTRIBUTION SYSTEM TESTING BASE + 2 OYS, newest first.
File Type Posted
36C25224Q0416 0002_1.docx DOCX document
ATTACHMENT G - Construction Safety Guidebook.pdf PDF
ATTACHMENT D - Contractor VA System Outage Request Form Milwaukee.docx DOCX document
ATTACHMENT F - CONTRACTOR Non-Disclosure Agreement.docx DOCX document
ATTACHMENT E - VHA Directive 1028_2020-02-24.pdf PDF
ATTACHMENT C - OPTION YEAR 2.pdf PDF
ATTACHMENT B - OPTION YEAR 1.pdf PDF
ATTACHMENT A - BASE YEAR.pdf PDF
36C25224Q0416_2.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE

7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER

3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO.

1. CONTRACT ID CODE

FACILITY CODE

CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office.

is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER

16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30

PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer) None 695-24-2-6093-0052 Department of Veterans Affairs

GLAC (69D)

115 South 84th Street, Suite 101 Milwaukee

WI

53214-1476 Department of Veterans Affairs

GLAC-MILWAUKEE (69D)

Great Lakes Acquisition Center - HC 115 South 84th Street, Suite 101 Milwaukee

WI

53214-1476 To all Offerors/Bidders

36C25224Q0416 05-13-2024

X X

WEDNESDAY MAY 22, 2024 AT 10:00AM LOCAL

X REFERENCE SOLICITATION 36C25224Q0416 FOR ELECTRICAL DISTRIBUTION SYSTEM TESTING AT THE MILWAUKEE VA MEDICAL CENTER AND AMEND TO REFLECT THE FOLLOWING: Provide answers to questions submitted; incorporate Attachment G - Construction Safety Guidebook; Correct Box 20 on SF1149 by removing Option Years 3 and 4.

SOLICITATION CLOSE IS EXTENDED TO WEDNESDAY MAY 22, 2024 AT 10:00 AM LOCAL.

ALL OTHER TERMS AND CONDITIONS REMAIN THE SAME.

CC: COR; FILE

SUSAN PASHOLK

CONTRACTING OFFICER

Page 1 – Title Block – Block 8 – Offeror Due Date – Will there be an extension granted on bid due date? SOLICITATION close is extended to MAY 22, 2024 AT 10:00 AM LOCAL.

Page 1 – Title Block – Box 20 – This contract structure shows a base year (2024-2025) plus 4 option years. The Price / Cost Schedule on Page 6 A.1 states Base Year (Attachment A) Option Year 1 (Attachment B) then Triennial Testing Per SOW (mentioned contract period Option Year 1) and then Option Year 2 (Attachment C).

What is the correct number of option years / what attachment applies to triennial testing per SOW? There will be 2 option years; Box 20 is updated and removes Option Year 3 and Option Year 4

Page 5 – Security & Privacy Control – Visitor Passes – Is there any required site safety courses to be taken (online or in person) prior to gaining access to the job site? This amendment incorporates Attachment G - Construction Safety Guidebook; Contractor shall follow guidelines for their employee safety requirements.

Page 7 – 2.0 General Tasks – Bullet Point D-1. ANSI / NETA testing procedures. NETA standard states primary injection testing of circuit breakers, both bolt on to bus and drawout / rack able. From the information provided, it would appear most breakers are not drawout. Is secondary injection testing acceptable for breakers that are bolted on? Yes.

Follow up question – If Primary Injection is required, will the site supply a 100A temp power source to power any test benches / sets? (In same note, temp lighting for when systems are de-energized?) No.

Page 7 – 2.0 General Tasks – Bullet Point D-3. Equipment inventory – Per above question, there are only 3 attachments but the title block page calls out base year + 4 options, are any workscopes / asset lists to be repeated in option years 3 and 4? There will be only 2 option years.

Page 8 – 2.0 General Tasks – Bullet Point D-H – Will one line diagrams / riser diagrams be provided before award for quotation purposes? No.

Page 8 – 3.0 Inspection & Tests – Bullet Point B. If a subcontractor is to be used for IR Scanning, does the company need to be identified ahead of award? Or can companies be confirmed before execution of work scope? Subcontractor must be confirmed and accepted before execution of work. Since this is a Small Business set-aside, Limitations on Subcontracting apply. Prime contractor must sign limitations certification clause.

Page 8 – 4.0 Basic Year Specific Tasks – Referring to attachment A – In the first table, top of the page that identifies SWBD / SWGR lineups – how many sections are in each lineup? (Example: Bldg 111, lineup noted SG-1LS – how many sections are in this lineup?) Are there ancillary devices in the lineups like meters, surge suppression, throw over schemes? There would be (2) sections of rackable breakers that feed to (2) sections of bolt on breakers. There are tie-breakers but no meters or surge suppression in this gear.

Page 8 – 4.0 Basic Year Specific Tasks – Referring to attachment A – First page, Second Table – These assets are listed as panelboards… Are these items single section SWBD Section / Panelboard or are they multiple section Switchboards? (Essentially trying to establish the flow down from SWBD to SWGR to assets downstream to breakers in each lineup.) These are still sections of the switchboards.

Page 8 – 4.0 Basic year Specific Tasks – Referring to Attachment A - Page 4 Table, Items listed “Solid State” – Are these individual circuit breakers that are to be tested? Is primary injection testing required if the breakers are bolt on bus? Do thermal magnetic breakers also require primary injection testing? These are individual circuit breakers that need testing. Secondary testing can be done they are bolt on. Same with thermal Magnetic.

Page 8 – 4.0 Basic year specific tasks – Referring to Attachment A – Page 6 Second Table – What is the difference between “Solid State” Assets and “Low Voltage Breakers”? Different testing procedures? Or are LV Breakers drawout type? Some are Draw out, some are bolted on.

Page 8 – 4.0 Base Year Specific Tasks – Referring to Attachment A – Page 8 – Table Type Motor Control Center – How many sections / buckets are in each MCC? Is the device count = number of feeders / taps? Are they all feeder breaker buckets? Drives, Starters? They are mostly drives and starters, just the feeder breaker would need testing.

Page 8 – 4.0 Base Year Specific Tasks – Referring to Attachment A – Page 8 – Table Type PTs – Where are the PTs located in this table? Basement of building 111.

Page 8 – 5.0 Option Year 1 Specific Tasks – The verbiage in the contract doc mentions testing of “the” substation – Does this refer to one single lineup? And (4) main transformers – Is that the whole scope for Option Year 1? Or are we planning to PM everything on attachment B for Option Year 1? Testing everything on option year 1, however the substation and the four main transformers get done on our Triennial test, that’s when we have to have total utility power loss to the entire campus for (4) hours and run on generators. Perfect time to test sub and 4 mains to minimize affect to the main hospital.

Page 8 – 5.0 Option Year 1 Specific Tasks – Page 1 – Table 1 - How many sections are in each of the SWGR / SWBD Lineups? Are there any ancillary devices like meters, surge protection, throwover schemes? (1) section in each listed.

Page 8 – 5.0 Option Year 1 Specific Tasks – Page 9 Bottom of Page – There is a mention of a Bldg 1 one line diagram paired with the cables… Can drawings / one lines be provided for quotation purposes? No.

Page 9 – 8.0 Hours of Operation – Bullet Point A – Referencing labor to be performed outside of normal working hours. How long of an outage will be granted each day? No longer than 12 hours.

Page 10 – 9.0 Contractor Qualifications – Bullet Point A. Will NICET certifications be accepted as an approved alternate to NETA certified? No.

Will we have access to the previous reports for the testing that was completed under the previous contract? No.

The base year starts July 1. Is there a time frame when you want the work scheduled? After contract is awarded, dates will be discussed.

Should we consider doing all the work at night, or can some be done during the day? Nights and weekends.

See attached document: ATTACHMENT G - Construction Safety Guidebook.