This document outlines the scope of work for an electrical systems upgrade project at the Tomah Veterans Medical Center. The project involves four main tasks: replacing surge protection devices at four buildings; replacing batteries for the primary service switchgear; mitigating water infiltration at three generator fuel tanks by raising concrete pads and installing protective rings around port openings; and removing and replacing snow/ice melt cable systems on seven rooftops. The period of performance is 180 calendar days. Bids are due by April 4, 2023 and will be evaluated based on the all-inclusive base bid as well as an alternate bid that excludes connecting one aspect of the snow/ice melt system to the building automation system. The awarded contractor must follow all safety and COVID-19 protocols required by the Department of Veterans Affairs. Relevant specifications and drawings are provided in the appendices.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 36C25223B0020 0008.docx | DOCX document | |
| 36C25223B0020 0007.docx | DOCX document | |
| 36C25223B0020 0006.docx | DOCX document | |
| 36C25223B0020 0005.docx | DOCX document | |
| 36C25223B0020 0004.docx | DOCX document | |
| 36C25223B0020 0003.docx | DOCX document | |
| S04 - 676-23-02 upgrade elec- site visit roster.pdf | ||
| 36C25223B0020 0002.docx | DOCX document | |
| S06 - 0001 Att 3 Appendix C - Example Design _ Building Dimensions REVISED.pdf | ||
| S06 - 0001 Att 1 676-23-002 Update Electrical System - Appendix A- Combined Specs REVISED.pdf | ||
| S06 - 0001 Att 2 676-23-002 Update Electric System - Appendix B- Tank Sketches.pdf | ||
| S02 - ATT 4 VHA COVID COMPLIANCE.pdf | ||
| S02 - ATT 1 Combined SOW - 676-23-002 Update Electric System.pdf | ||
| S02 - ATT 2 Wage Rates 3.30.23.pdf | ||
| S02 - ATT 3 VHA Directive 1192_01_D_2020-08-10 Seasonal Flu Shot.pdf | ||
| 36C25223B0020_2.docx | DOCX document |
Show all 16
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE
7.
ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF
PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE
OF YOUR
ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office.
is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERE
D CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES
SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendmen t, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED
STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER
16A. NAME AND TITLE OF
CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF
SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer) No Changes 676-23-007 36C252 Department of Veterans Affairs Great Lakes Acquisition Center (GLAC) 115 S 84th Street, Suite 101 Milwaukee WI 53214-1476 36C252 Department of Veterans Affairs Great Lakes Acquisition Center (GLAC) 115 S 84th Street, Suite 101 Milwaukee WI 53214-1476 To all Offerors/Bidders
36C25223B0020 04-04-2023
X X X
X This amendment is incorporated into this solicitation.
This amendment incorporates an updated Statement of Work.
Amy Burger Contract Specialist
676-23-002 Update Electrical Systems Tomah VAMC Statement of Work
I. Background This project will involve several tasks. Several electrical systems are in need of repair and a few tasks related to those systems are in need of attention. In summary:
· Surge protection devices (SPD) for buildings 240A, 400, 401, and 406 main service panels are not working. Those devices need to be replaced as soon as possible,
· Batteries for DC relay for the primary service switchgear are failing in building 428. The battery system needs to be replaced with new AGM batteries,
· Generator Fuel Tanks have surface water leaking into fuel and must be corrected, and
· Heat cable for melting roof snow and ice are needed on buildings 401, 402, 403, 404, 406, 407, and 408.
II. Scope of Work There four tasks in this scope of work. The contractor shall provide all materials, labor, qualified supervision, and equipment to demolish and then install new items outlined in the scope of work, specifications, sketches, descriptions, and follow-up discussions.
Task 1: Replace Surge Protection Device for Building 240A, 400,401, and 406 Main Service Panels The surge protectors are failing or no longer working in these buildings, and they need to be replaced. The surge protectors must be Type 2 per NFPA 70. The existing panels are Square D, QED, Series 2, REV80258-133-06, 60 HZ. Square D must be consulted for the proper size devices. The panel data are:
| Building |
| Volt |
| Max Supply Rate (A) |
| Phase |
| WHF |
| SN |
| 240A |
| 208 |
| 600 |
| 3 |
| 4 |
| 32953723-002 |
| 400 |
| 480 |
| - |
| - |
| - |
| Electrical Panel EQ-1-4 |
| 401 |
| 480/277 |
| 1200 |
| 3 |
| 4 |
| 30155958-1-015 |
| 402 |
| 480/277 |
| 1200 |
| 3 |
| 4 |
| 25667337-001 |
| 406 |
| 480/277 |
| 1200 |
| 3 |
| 4 |
| 30155958-012 |
The surge protectors shall be Square D compatible Surgelogic HL2IMA24C, HL4IMA24C or equal and suitably sized for service.
Task 2: Replace Batteries for DC relay for the Primary Service Switchgear in Building 428 Remove the existing batteries, charger, and storage rack and recycle the batteries in accordance with regulatory requirements. Provide disposal documentation to the COR.
Provide and install new Absorbent Glass Mat (AGM) batteries, compatible charging system, and storage rack sufficient to hold the new equipment, and fits into the available space (6’ Wide X 3’ Deep X 8’ High). The battery system must connect to an existing alarm system that notifies when the relay is activated. Provide commissioning of the battery system. Perform a system test to verify that the new system operates properly. VA shops personnel and COR shall witness the test.
Currently we have 109 cells of 80 A-hr capacity rated at 1.2 V/cell (higher AH to end cell voltage of 1.10V and more to 1.05 V/cell). We will need the same capacity with the AGM battery bank.
Task 3: Mitigate Water Infiltration to Generator Fuel Tanks located at B445, B448 and B424 Tanks 445 and 448 Currently water is infiltrating into the fuel tanks. We want to raise the tank pads and each port hole above the surrounding ground elevation by six inches. The contractor is responsible for measuring the tank pads and port openings for each pad.
Tanks at generator building 445 and 448: We would like to have a six-inch ring added to each tank port (Interstitial Monitoring, Supply & Return Pipes, Vent, and Fill) openings. The rings should have a seal or be welded to prevent water infiltration. A new concrete pad shall be added to the top of the existing pad. Concrete shall be contoured such that the concrete slopes away from the ring of each port to the outer edges of the pad. At the ring, the concrete will be 6-inches thick and taper to about four inches at the edges. This configuration will promote drainage away from the port openings. A layer of tack coat shall be placed between the concrete layers to bond the two slabs together. Include:
· Identification Tags - ports shall be tagged with aluminum name plates embedded in the concrete.
· Paint the fill port as shown in the photos,
· Bollards - An 8-foot tall (4-feet in ground and 4-feet above ground) bollard, 6-inch diameter bollard shall be placed just outside the pad at each corner of the pad. Bollards shall be covered with yellow plastic covers. Holes for the bollards shall be hand dug. The photo shows the typical existing layout.
Tank Pad 445 behind B403 Tank Pad 448 behind B407
Tank 424 (Replace fuel lines and raise pad) Tank at 424 - This tank is in a parking lot. Replace the supply and return pipes because they are deteriorating from exposure to water in the sump. This section of the pad should be dug up as needed to gain access to the pipes for repair. Once the pipes are replaced, the backfill material around the sump should be pea gravel. Patch asphalt around tank pad as needed. Replace demolished concrete pad.
Supply and Return Lines needing replacement.
Additionally, each port on this tank pad will be raised six-inches. This pad will become an island in the parking lot to prevent parking over the tank. The new pad should have a curb that is about 5 inches high. The new concrete at the raised ports will be about six-inches thick. The elevation difference between the ports and the curb edge will provide a small amount of drainage away from the ports. A layer of tack coat shall be placed between the concrete layers to bond the two slabs together. Include:
· Identification Tags - ports shall be tagged with aluminum name plates embedded in the concrete.
· Paint the fill port as shown in the photo,
· Bollards - Six 8-foot tall (4-feet in ground and 4-feet above ground) bollards having a 6-inch diameter. Each bollard shall be covered by a yellow, plastic cover. Each bollard shall be placed just outside the pad at each corner of the pad and at the mid-point of the long side. Bollards shall be hand dug. The photo shows the typical existing layout.
Tank Pad 424 behind B424 (Kitchen Dock) See Appendix B for sketches of existing and proposed conditions.
Task 4: Remove and Replace Snow/Ice Melt Trace on Buildings 401, 402, 403, 404, 406, 407, and 408.
· Remove and dispose of the existing snow/ice melt system on the seven buildings listed.
· Provide and install a new snowmelt system installed along roof edges, valleys, and down spouts in accordance with manufacturer’s recommended layout and installation requirements.
Snow and ice melting systems shall include automatic controls capable of and configured to shut off the systems when the roof temperature is above 45°F and no precipitation is falling, and an automatic control that will allow the system to turn on when the outdoor temperature is 38°F and precipitation is falling so that the potential for snow or ice accumulation is negligible. The specifications (22 05 33 Snow Melt Trace) provide the salient features of the system.
· The snow/icemelt system shall be connected to the building automation system (BAS). The BAS system shall indicate that the snowmelt system is off or on and shall report to the maintenance office in Building 40 through the BAS system. Building 401 has a Siemens BAS system reporting to Metasys. The remaining buildings have a Johnson Control BAS system reporting to Metasys.
A design for a snow/ice melt system was recently completed and installed on Building 400. We are providing this design as an example of our intent for the snow/ice melt system for each of the buildings listed. We are also providing building sketches with rough estimates of wall dimensions. Together, the example design, the building data, and the specifications can be used to assist the contractor in designing the layout plan and estimating quantities of materials. The contractor shall be responsible for determining and confirming final lengths and layouts for the cable system. The sketches and recent design are provided in Appendix C.
The snow/ice melt cable system is being requested as a sole source item. The reason to use the same system is for consistency across the campus. Providing a consistent system on campus reduces maintenance costs for training, number of spare parts being held on-hand, specialty tools for repairs, and better familiarity of the system with maintenance staff. The system being sole sourced is nVent, Raychem Rim2, IceStop Self-Regulating Heating Cable, GM-2X, as provided in the example design in Appendix C. All associated fixtures, controllers, clips and sensors shall be compatible with the system.
The contractor shall be responsible for all new electrical requirements as needed including but not limited to: conduit, breakers, cabling, sensors, mounting brackets, circuits or controls.
III. ADDITIONAL REQUIREMENTS
A. All work shall be accomplished to reduce impact to normal operational requirements. Systems that must be de-energized for work to be performed must be scheduled two weeks in advance of the shutdown. Work shall be scheduled with the COR and written permission shall be obtained before work starts.
B. Normal working hours are between 7:00 am to 4:30 pm.
C. Contractor shall be required to comply with the General Requirements, Specification 01 00 00.
D. Work shall be scheduled as materials are approved, available, delivered on site and ready for installation and shall be installed according to the manufacturer’s instructions and according to the specifications. Submittal requirements include:
1. Safety Data Sheets (SDS) for all hazardous materials to be used/kept on the contract site,
2. Manufacturer’s literature, hardware, and installation instructions.
E. The contractor will be responsible for organizing, scheduling, and facilitating the progress of work and coordinate with the COR.
F. Contractors shall be required to obtain, wear, and return VA Contractor badges.
G. Contractors and sub-contractors shall wear proper PPE including safety shoes, safety glasses, and hardhat and additional PPE as required by the task being completed. In this case ARC Flash gear may be required.
H. Contractors shall obtain the 2022-23 flu vaccination when available and as appropriate during the period of performance. Evidence of inoculation will be required.
I. The contractor will be required to follow COVID check-in procedures in effect during the period of performance. Generally, this means answering questions about physical condition and having a temperature taken. The contractor will wear a sticker indicating compliance with daily check-in. Current COVID requirements will be reviewed after award during the project kick-off meeting.
J. The work area shall be clean and picked up at the end of each day’s work.
K. The VA does not anticipate lead or asbestos abatement in the project.
IV. PERIOD OF PERFORMANCE
The work tasks have significantly different time requirements. It is anticipated that the roofing heat cable installation will take the longest time. The priority for work to be completed is Task 1 and Task 2. These two tasks should be completed in the first half of the time permitted or the first 90 days or so. Task 3 shall be completed at a time when weather conditions are conducive to concrete placement. In general, the Period of Performance for all work tasks shall be 180 calendar days.
V. BID DEDUCTS
Bid deducts shall be implemented as necessary and as funding permits:
All Inclusive Base Bid: Furnish all labor, materials, equipment and qualified supervision in accordance with the Scope of Work outlined in items I. through IV. above, and the construction documents, drawings and specifications to complete Project 676-23-002 “Upgrade Electrical Systems” at the Tomah Veterans Hospital, Tomah, WI. Work includes, but is not limited to:
· Surge protection devices (SPD) for buildings 240A, 400, 401, and 406 main service panels are not working. Those devices need to be replaced as soon as possible,
· Batteries for DC relay for the primary service switchgear are failing in building 428. The battery system needs to be replaced with new AGM batteries,
· Generator Fuel Tanks have surface water leaking into fuel and must be corrected, and
· Heat cable for melting roof ice are needed on buildings 401, 402, 403, 404, 406, 407, and 408.
All work shall be completed with 180 calendar days after receiving Notice to Proceed.
Alternate Bid Item A: Includes all work in the Base Bid with the following changes:
1) In Task 4, the contractor shall exclude all work related to connecting the snow/ice melt system to the building automation system.
All work shall be completed within 180 calendar days after receiving Notice to Proceed.
NOTICE TO BIDDERS:
· A single award will be made on the Base Bid, subject to available funding. In the event bids on the Base Bid exceed available funding, a single award will be made exclusively on the amount of funding available in the following order: Deductive Bid Total #1. Award will be made to the lowest priced, responsive, and responsible bidder.
· For Alternate Bid Items, bidders should ensure that the all-inclusive price after the deductions are subtracted has been entered. Do not enter the amount of the deduction.
• BIDDERS MUST BID ON ALL BID ITEMS. ONLY ONE AWARD WILL BE MADE AS A RESULT OF THIS SOLICITATION
Prepared by:
Beth Heim 1/31/2023
Appendix A – Specifications Appendix B – Fuel Tank Sketches Appendix C –
· Recent Design Example for Building 400 - Snow Melt Trace
(FOR REFERENCE ONLY)
· Roof Sketches showing rough dimensions
(FOR REFERENCE ONLY)
See attached document: S06 - 0001 Att 1 676-23-002 Update Electrical System - Appendix A- Combined Specs REVISED.
See attached document: S06 - 0001 Att 2 676-23-002 Update Electric System - Appendix B- Tank Sketches.
See attached document: S06 - 0001 Att 3 Appendix C - Example Design _ Building Dimensions REVISED.
image4.jpeg image1.jpeg image2.jpeg image3.jpeg