2 - Revised BID SCHEDULE.pdf
PDF 130 KB Posted
- Solicitation number
- 36C25220B0025
About this file
This document includes a solicitation for the replacement of three high-pressure steam boilers, associated utility connections and equipment, and support piping at the Tomah VA Medical Center in Tomah, Wisconsin. The project is estimated at $10-20 million and includes removing and replacing boiler control devices and programming, as well as abating lead paint and asbestos.
The solicitation will be posted on August 21, 2020 to the SAM website, with bids due on September 23, 2020. The estimated period of performance is 490 calendar days from notice to proceed, divided into phases. The North American Industry Classification Code is 238220 and the size standard of $16.5 million applies. Pursuant to Public Law 109-461, this solicitation is set aside as a 100% Service Disabled Veteran Owned Small Business opportunity. Bidders must represent SDVOSB status, size standard compliance, and CVE verification in VIP at time of submission.
View the file
Other files
Show all 26
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
36C252-20-B-0025 A0005
BID SCHEDULE
Solicitation Number 36C252-20-B-0025
676-14-105: Replace Boilers, B415 Tomah VAMC, Tomah, WI
001 All-Inclusive Base Bid: Contractor shall provide for and furnish all labor, materials, equipment, qualified supervision, and other items designated in this contract in accordance with the specifications and drawings for the replacement of three existing high pressure steam boilers, boiler utility connections, selected boiler associated equipment and selected boiler support piping to complete Project # 676-14-105: Replace Boilers, Building 415 at the Tomah VA Medical Center in Tomah, Wisconsin. Included is the complete removal and replacement of boiler control devices and programming operations and full abatement of lead paint and asbestos within the facility.
All work shall be completed within 490 calendar days after receipt of the Notice to Proceed.
All-Inclusive Base Bid LUMP SUM: $ ___________________________
002 – Deductive Bid Alternate # 1: Furnish all labor, materials, equipment, and supervision in accordance with construction documents, drawings, and specifications to complete Project 676-14-105 as described in the All-Inclusive Base Bid with the following deductive alternative:
Omit all work associated with Phase III:
Phase III is the removal and disposal of existing Boiler # 1 and installation of a new Boiler # 1 and all specific related work such as roof work, venting, concrete slab, access platform, and all associated items. See description in General Requirements 01 00 00 1.3 Statement of Bid Items.
All work to be accomplished within 370 calendar days after receipt of the Notice to Proceed.
002 – Deductive Bid Alternate # 1: $_______________________________
File details come from the government source that posted it. Updated .