Specifications
Edward Hines, Jr. VA Hospital
5000 South 5 th
Avenue
Hines, Illinois 60141
Legionella Suppression Design
Task Order #1 | Building 228
Contract No. VA69D-17-D-0067
Station Project No. 578-17-005
Bancroft-AE Project No. 17-107
100% Issue for Bid
Divisions 00 - 28
January 18, 2019
DIVISION 00
SPECIAL SECTIONS
LEGIONELLA SUPPRESSION DESIGN
TASK ORDER #1 BUILDING 228
Bancroft Architects + Engineers
04-01-18
Contract No. VA69D-17-D-0067
Bancroft-AE Project No. 17-107 00 01 10-0 1-18-2019
DEPARTMENT OF VETERANS AFFAIRS
VHA MASTER SPECIFICATIONS
TABLE OF CONTENTS
SECTION 00 01 10
DIVISION 00 - SPECIAL SECTIONS DATE
00 01 15 List of Drawing Sheets 07-15
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 General Requirements 10-17
01 32 16.15 Project Schedules (Small Projects – Design/Bid/Build 04-13
01 33 23 Shop Drawings, Product Data, and Samples 05-17
01 35 26 Safety Requirements 02-17
01 42 19 Reference Standards 05-16
01 57 19 Temporary Environmental Controls 01-11
01 58 16 Temporary Interior Signage 07-15
01 74 19 Construction Waste Management 09-13
01 81 13 Sustainable Construction Requirements 10-17
DIVISION 02 – EXISTING CONDITIONS
02 41 00 Demolition 08-17
DIVISION 03 – CONCRETE (NOT USED)
DIVISION 04 – MASONRY (NOT USED)
DIVISION 05 – METALS (NOT USED)
DIVISION 06 – WOOD,PLASTICS AND COMPOSITES
06 10 00 Rough Carpentry 10-17
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 21 13 Thermal Insulation 10-17
07 84 00 Firestopping 02-16
07 92 00 Joint Sealants 10-17
DIVISION 08 - OPENINGS
08 11 13 Hollow Metal Doors and Frames 08-16
08 14 00 Interior Wood Doors 02-16
08 71 00 Door Hardware 01-16
LEGIONELLA SUPPRESSION DESIGN
TASK ORDER #1 BUILDING 228
Bancroft Architects + Engineers
04-01-18
Contract No. VA69D-17-D-0067
Station Project No. 578-17-005
Bancroft-AE Project No. 17-107 00 01 10-1 1-18-2019
08 80 00 Glazing 10-15
DIVISION 09 – FINISHES
09 05 16 Subsurface Preparation for Floor Finishes 02-15
09 22 16 Non-Structural Metal Framing 05-16
09 29 00 Gypsum Board 11-14
09 30 13 Ceramic/Porcelain Tiling 09-15
09 51 00 Acoustical Ceilings 12-16
09 54 23 Linear Metal Ceilings 10-15
09 65 13 Resilient Base and Accessories 02-16
09 65 19 Resilient Tile Flooring 12-15
09 91 00 Painting 01-16
DIVISION 10 – SPECIALTIES
10 14 00 Signage 10-15
10 26 00 Wall and Door Protection 10-15
10 28 00 Toilet, Bath, and Laundry Accessories 02-16
10 44 13 Fire Extinguisher Cabinets 08-14
DIVISION 11 – EQUIPMENT (NOT USED)
DIVISION 12 – FURNISHINGS (NOT USED)
DIVISION 13 - SPECIAL CONSTRUCTION (NOT USED)
DIVISION 14 – CONVEYING EQUIPEMENT (NOT USED)
DIVISION 21 - FIRE SUPPRESSION
21 13 13 Wet-Pipe Sprinkler Systems 06-15
DIVISION 22 – PLUMBING
22 05 11 Common Work Results for Plumbing 07-16
22 05 12 General Motor Requirements for Plumbing Equipment 09-15
22 05 19 Meters and Gages for Plumbing Piping 09-15
22 05 23 General-Duty Valves for Plumbing Piping 09-15
22 07 11 Plumbing Insulation 09-15
22 11 00 Facility Water Distribution 09-15
22 13 00 Facility Sanitary and Vent Piping 09-15
22 32 00 Domestic Water Treatment System
DIVISION 23 – HEATING, VENTILATING, AND AIR
CONDITIONING (HVAC)
23 05 11 Common Work Results for HVAC 08-17
23 05 93 Testing, Adjusting, and Balancing for HVAC 02-15
LEGIONELLA SUPPRESSION DESIGN
TASK ORDER #1 BUILDING 228
Bancroft Architects + Engineers
04-01-18
Contract No. VA69D-17-D-0067
Station Project No. 578-17-005
Bancroft-AE Project No. 17-107 00 01 10-2 1-18-2019
23 07 11 HVAC and Boiler Plant Insulation 02-15
23 09 23 Direct-Digital Control System for HVAC 09-11
23 21 13 Hydronic Piping 08-17
23 31 00 HVAC Ducts and Casings 03-13
23 36 00 Air Terminal Units 02-15
23 37 00 Air Outlets and Inlets 02-15
23 82 00 Convection Heating and Cooling Units 04-11
DIVISION 25 – INTEGRATED AUTOMATION
25 10 10 Advanced Utility Metering System 02-10
DIVISION 26 – ELECTRICAL
26 05 11 Requirements for Electrical Installations 01-16
26 05 19 Low-Voltage Electrical Power Conductors and Cables 01-17
26 05 26 Grounding and Bonding for Electrical Systems 01-17
26 05 33 Raceway and Boxes for Electrical Systems 05-14
26 09 23 Lighting Controls 05-14
26 24 16 Panelboards 05-14
26 27 26 Wiring Devices 01-16
26 29 21 Enclosed Switches and Circuit Breakers 01-17
26 51 00 Interior Lighting 08-14
DIVISION 27 – COMMUNICATIONS
27 05 11 Requirements for Communications Installations 06-15
27 05 26 Grounding and Bonding for Communications Systems 06-15
27 05 33 Raceways and Boxes for Communications Systems 06-15
27 10 00 Control, Communication and Signal Wiring 06-15
27 11 00 Communications Equipment Room Fittings 06-15
27 15 00 Communications Structured Cabling 01-16
27 31 00 Voice Communications Switching and Routing Equipment 06-15
DIVISION 28 – ELECTRONIC SAFETY AND SECURITY
28 05 00 Common Work Results for Electronic Safety and Security 09-11
28 05 13 Conductors and Cables for Electronic Safety and
Security
09-11
28 05 26 Grounding and Bonding for Electronic Safety and
Security
09-11
28 05 28.33 Conduits and Backboxes for Electronic Safety and
Security
09-11
28 13 53 Security Access Detection 09-11
28 23 00 Video Surveillance 09-11
28 31 00 Fire Detection and Alarm 10-11
DIVISION 31 – EARTHWORK (NOT USED)
DIVISION 32 – EXTERIOR IMPROVEMENTS (NOT USED)
LEGIONELLA SUPPRESSION DESIGN
TASK ORDER #1 BUILDING 228
Bancroft Architects + Engineers
04-01-18
Contract No. VA69D-17-D-0067
Bancroft-AE Project No. 17-107 00 01 10-3 1-18-2019
DIVISION 33 – UTILITIES (NOT USED)
DIVISION 34 – TRANSPORTATION (NOT USED)
DIVISION 48 – ELECTRICAL POWER GENERATION (NOT USED)
LEGIONELLA SUPPRESSION DESIGN
TASK ORDER #1 BUILDING 228
Bancroft Architects + Engineers
07-01-15
Bancroft-AE Project No. 17-107 00 01 15-1 1-18-2019
SECTION 00 01 15
LIST OF DRAWINGS
The drawings listed below accompanying this specification form a part of the contract.
Drawing No. Title
GENERAL
GI000 GENERAL – COVER SHEET
GI001 GENERAL - DRAWING INDEX
GI002 GENERAL - NOTES
GI003 GENERAL – NOTES
GI004 GENERAL – SYMBOLS, ABBREVIATIONS & TYPICAL
MOUNTING HEIGHTS
GI103 GENERAL – THIRD FLOOR LIFE SAFETY PLAN
GI104 GENERAL – FOURTH FLOOR LIFE SAFETY PLAN
GP101A GENERAL – PHASE 1-4 PLAN
GP101B GENERAL – PHASE 5-8 PLAN
ARCHITECTURAL
AD103A ARCHITECTURAL – PARTIAL THIRD FLOOR DEMOLITION
PLAN – A
AD103B ARCHITECTURAL – PARTIAL THIRD FLOOR DEMOLITION
PLAN – B
AD104A ARCHITECTURAL – PARTIAL FOURTH FLOOR DEMOLITION
PLAN – A
AD104B ARCHITECTURAL – PARTIAL FOURTH FLOOR DEMOLITION
PLAN – B
ACD101A ARCHITECTURAL – FIRST FLOO REFLECTED CEILING
DEMOLITION PLAN - A
ACD102A ARCHITECTURAL – SECOND FLOOR REFLECTED CEILING
DEMOLITION PLAN – A
ACD102B ARCHITECTURAL – SECOND FLOOR REFLECTED CEILING
DEMOLITION PLAN - B
ACD103A ARCHITECTURAL – THIRD FLOOR REFLECTED CEILING
DEMOLITION PLAN – A
LEGIONELLA SUPPRESSION DESIGN
TASK ORDER #1 BUILDING 228
Bancroft-AE Project No. 17-107 00 01 15-2 1-18-2019
ACD103B ARCHITECURAL – THIRD FLOOR REFLECTED CEILING
DEMOLITION PLAN – B
ACD104A ARCHITECTURAL – FOURTH FLOOR REFLECTED CEILING
DEMOLITION PLAN – A
ACD104B ARCHITECTURAL – FOURTH FLOOR REFLECTED CEILING
DEMOLITION PLAN – B
A103A ARCHITECTURAL – THIRD FLOOR PLAN – A
A103B ARCHITECTURAL – THIRD FLOOR PLAN – B
A104A ARCHITECTURAL – FOURTH FLOOR PLAN – A
A104B ARCHITECTURAL – FOURTH FLOOR PLAN – B
AC103A ARCHITECTURAL – THIRD FLOOR REFLECTED CEILING
PLAN – A
AC103B ARCHITECTURAL – THIRD FLOOR REFLECTED CEILING
PLAN – B
AC104A ARCHITECTURAL – FOURTH FLOOR REFLECTED CEILING
PLAN – A
AC104B ARCHITECTURAL – FOURTH FLOOR REFLECTED CEILING
PLAN – B
A401 ARCHITECTURAL – TYPICAL INTERIOR ELEVATIONS
A501 ARCHITECTURAL – DETAILS
A502 ARCHITECTURAL – CEILING DETAILS
A601 ARCHITECTURAL – PARTITION TYPES AND DETAILS
A602 ARCHITECTURAL – DOOR AND WINDOW SCHEDULES AND
DETAILS
INTERIOR
IN103A INTERIOR – THIRD FLOOR FINISH PLAN – A
IN103B INTERIOR – THIRD FLOOR FINISH PLAN – B
IN104A INTERIOR – FOURTH FLOOR FINISH PLAN – A
IN104B INTERIOR – FOURTH FLOOR FINISH PLAN – B
IG103A INTERIOR – THIRD FLOOR SIGNAGE PLAN AND DETAILS
– A
IG103B INTERIOR – THIRD FLOOR SIGNAGE PLAN AND DETAILS
– B
LEGIONELLA SUPPRESSION DESIGN
TASK ORDER #1 BUILDING 228
Bancroft-AE Project No. 17-107 00 01 15-3 1-18-2019
IG104A INTERIOR – FOURTH FLOOR SIGNAGE PLAN AND
DETAILS – A
IG104B INTERIOR – FOURTH FLOOR SIGNAGE PLAN AND
DETAILS – B
IF103A INTERIOR – THIRD FLOOR FURNITURE PLAN – A
IF103B INTERIOR – THIRD FLOOR FURNITURE PLAN – B
IF104A INTERIOR – FOURTH FLOOR FURNITURE PLAN – A
IF104B INTERIOR – FOURTH FLOOR FURNITURE PLAN – B
IF401 INTERIOR- TYPICAL FURNITURE AND EQUIPMENT PLANS
AND SCHEDULE
IN601 INTERIOR – ROOF FINISH SCHEDULE AND LEGEND
FIRE PROTECTION
FP001 FIRE PROTECTION – GENERAL NOTES, SYMBOLS, AND
ABBREVIATIONS
FPD103A FIRE PROTECTION – THIRD FLOOR DEMOLITION PLAN –
A
FPD103B FIRE PROTECTION – THIRD FLOOR DEMOLITION PLAN –
B
FPD104A FIRE PROTECTION – FOURTH FLOOR DEMOLITION PLAN
– A
FPD104B FIRE PROTECTION – FOURTH FLOOR DEMOLITION PLAN
– B
FP103A FIRE PROTECTION – THIRD FLOOR PLAN – A
FP103B FIRE PROTECTION – THIRD FLOOR PLAN – B
FP104A FIRE PROTECTION – FOURTH FLOOR PLAN – A
FP104B FIRE PROTECTION – FOURTH FLOOR PLAN – B
FP501 FIRE PROTECTION - DETAILS
PLUMBING
P001 PLUMBING – GENERAL NOTES, SYMBOLS, AND
ABBREVIATIONS
PD100 PLUMBING – BASEMENT DEMOLITION PLAN
LEGIONELLA SUPPRESSION DESIGN
TASK ORDER #1 BUILDING 228
Bancroft-AE Project No. 17-107 00 01 15-4 1-18-2019
PD102A PLUMBING – SECOND FLOOR DEMOLITION PLAN – A
PD102B PLUMBING – SECOND FLOOR DEMOLITION PLAN - B
PD103A PLUMBING – THIRD FLOOR DEMOLITION PLAN – A
PD103B PLUMBING – THIRD FLOOR DEMOLITION PLAN – B
PD104A PLUMBING – FOURTH FLOOR DEMOLITION PLAN – A
PD104B PLUMBING – FOURTH FLOOR DEMOLITION PLAN – B
P100 PLUMBING – BASEMENT PLAN
P101A PLUMBING – FIRST FLOOR PLAN - A
P102A PLUMBING – SECOND FLOOR PLAN – A
P102B PLUMBING – SECOND FLOOR PLAN – B
P103A PLUMBING – THIRD FLOOR PLAN – A
P103B PLUMBING – THIRD FLOOR PLAN - B
P104A PLUMBING – FOURTH FLOOR PLAN – A
P104B PLUMBING – FOURTH FLOOR PLAN – B
P400 PLUMBING – BASEMENT MECHANICAL ROOM ENLARGED
PLAN
P500 PLUMBING – DETAILS
P501 PLUMBING – DETAILS
P600 PLUMBING - SCHEDULES
P601 PLUMBING RISER DIAGRAM – SANITARY AND VENT
DEMOLITION PLAN
P602 PLUMBING RISER DIAGRAM – SANITARY AND VENT
DEMOLITION PLAN
P603 PLUMBING RISER DIAGRAM – SANITARY AND VENT
DEMOLITION PLAN
P604 PLUMBING RISER DIAGRAM – SANITARY AND VENT
DEMOLITION PLAN
P605 PLUMBING RISER DIAGRAM – SANITARY AND VENT
DEMOLITION PLAN
P606 PLUMBING RISER DIAGRAM – SANITARY AND VENT PLAN
P607 PLUMBING RISER DIAGRAM – SANITARY AND VENT PLAN
P608 PLUMBING RISER DIAGRAM – SANITARY AND VENT PLAN
P609 PLUMBING RISER DIAGRAM – SANITARY AND VENT PLAN
P610 PLUMBING RISER DIAGRAM – SANITARY AND VENT PLAN
LEGIONELLA SUPPRESSION DESIGN
TASK ORDER #1 BUILDING 228
Bancroft-AE Project No. 17-107 00 01 15-5 1-18-2019
P611 PLUMBING RISER DIAGRAM – DOMESTIC WATER
DEMOLITION PLAN
P612 PLUMBING RISER DIAGRAM – DOMESTIC WATER
DEMOLITION PLAN
P613 PLUMBING RISER DIAGRAM – DOMESTIC WATER
DEMOLITION PLAN
P614 PLUMBING RISER DIAGRAM – DOMESTIC WATER
DEMOLITION PLAN
P615 PLUMBING RISER DIAGRAM – DOMESTIC WATER
DEMOLITION PLAN
P616 PLUMBING RISER DIAGRAM – DOMESTIC WATER PLAN
P617 PLUMBING RISER DIAGRAM – DOMESTIC WATER PLAN
P618 PLUMBING RISER DIAGRAM – DOMESTIC WATER PLAN
P619 PLUMBING RISER DIAGRAM – DOMESTIC WATER PLAN
P620 PLUMBING RISER DIAGRAM – DOMESTIC WATER PLAN
MECHANICAL
M001 MECHANICAL – GENERAL NOTES, SYMBOLS, AND
ABBREVATIONS
MVD103AB THIRD FLOOR MECHANICAL VENTILATION DEMOLITIION
PLAN – AB
MVD103CD THIRD FLOOR MECHANICAL VENTILATION DEMOLITION
PLAN – CD
MHD103AB THIRD FLOOR MECHANICAL PIPING DEMOLTION PLAN –
AB
MHD103CD THIRD FLOOR MECHANICAL PIPING DEMOLITION PLAN –
CD
MVD104AB FOURTH FLOOR MECHANICAL VENTILATION DEMOLITION
PLAN – AB
MVD104CD FOURTH FLOOR MECHANICAL VENTILATION DEMOLITION
PLAN – CD
MHD104AB FOURTH FLOOR MECHANICAL PIPING DEMOLITION PLAN
– AB
MHD104CD FOURTH FLOOR MECHANICAL PIPING DEMOLITION PLAN
– CD
LEGIONELLA SUPPRESSION DESIGN
TASK ORDER #1 BUILDING 228
Bancroft-AE Project No. 17-107 00 01 15-6 1-18-2019
MV103A THIRD FLOOR MECHANICAL VENTILATION PLAN – A
MV103B THIRD FLOOR MECHANICAL VENTILATION PLAN - B
MV103C THIRD FLOOR MECHANICAL VENTILATION PLAN – C
MV103D THIRD FLOOR MECHANICAL VENTILATION PLAN – D
MH103A THIRD FLOOR MECHANICAL PIPING PLAN – A
MH103B THIRD FLOOR MECHANICAL PIPING PLAN - B
MH103C THIRD FLOOR MECHANICAL PIPING PLAN – C
MH103D THIRD FLOOR MECHANICAL PIPING PLAN – D
MV104A FOURTH FLOOR MECHANICAL VENTILATION PLAN – A
MV104B FOURTH FLOOR MECHANICAL VENTILATION PLAN – B
MV104C FOURTH FLOOR MECHANICAL VENTILATION PLAN – C
MV104D FOURTH FLOOR MECHANICAL VENTILATION PLAN – D
MH104A FOURTH FLOOR MECHANICAL PIPING PLAN – A
MH104B FOURTH FLOOR MECHANICAL PIPING PLAN – B
MH104C FOURTH FLOOR MECHANICAL PIPING PLAN – C
MH104D FOURTH FLOOR MECHANICAL PIPING PLAN – D
M500 MECHANICAL DETAILS
M501 MECHANICAL DETAILS
M502 MECHANICAL DETAILS
M600 MECHANICAL EQUIPMENT SCHEDULES
M700 TEMPERATURE CONTROLS
M701 TEMPERATURE CONTROLS
ELECTRICAL
E001 ELECTRICAL – NOTES, SYMBOLS AND ABBREVIATIONS
E002 ELECTRICAL – NOTES, SYMBOLS AND ABBREVIATIONS
EDL103A ELECTRICAL LIGHTING – PARTIAL THIRD FLOOR
DEMOLITION PLAN – A
EDL103B ELECTRICAL LIGHTING – PARTIAL THIRD FLOOR
DEMOLTION PLAN – B
EDL104A PARTIAL FOURTH FLOOR ELECTRICAL POWER
DEMOLITION PLAN – A
EDL104B PARTIAL FOURTH FLOOR ELECTRICAL POWER
DEMOLITION PLAN – B
LEGIONELLA SUPPRESSION DESIGN
TASK ORDER #1 BUILDING 228
Bancroft-AE Project No. 17-107 00 01 15-7 1-18-2019
EDP103A ELECTRICAL POWER – PARTIAL THIRD FLOOR
DEMOLITION PLAN – A
EDP103B ELECTRICAL POWER – PARTIAL THIRD FLOOR
DEMOLITION PLAN – B
EDP104A PARTIAL FOURTH FLOOR ELECTRICAL POWER
DEMOLITION PLAN – A
EDP104B PARTIAL FOURTH FLOOR ELECTRICAL POWER
DEMOLITION PLAN – B
EL103A ELECTRICAL LIGHTING – THIRD FLOOR PLAN – A
EL103B ELECTRICAL LIGHTING – THIRD FLOOR PLAN – B
EL104A ELECTRICAL LIGHTING – FOURTH FLOOR PLAN – A
EL104B ELECTRICAL LIGHTING – FOURTH FLOOR PLAN – B
EP100 ELECTRICAL POWER – BASEMENT PLAN AND PANEL
SCHEDULE
EP103A ELECTRICAL POWER – THIRD FLOOR PLAN – A
EP103B ELECTRICAL POWER – THIRD FLOOR PLAN – B
EP104A ELECTRICAL POWER – FOURTH FLOOR PLAN – A
EP104B ELECTRICAL POWER – FOURTH FLOOR PLAN – B
ET103A COMMUNICATION AND SECURITY – THIRD FLOOR PLAN –
A
ET103B COMMUNICATION AND SECURITYY – THIRD FLOOR PLAN
– B
ET104A COMMUNICATIONS AND SECURITY – FOURTH FLOOR PLAN
– A
ET104B COMMUNICATIONS AND SECURITYY – FOURTH FLOOR
PLAN – B
EF103A ELECTRICAL FIRE ALARM – THIRD FLOOR PLAN – A
EF103B ELECTRICAL FIRE ALARM – THIRD FLOOR PLAN – B
EF104A ELECTRICAL FIRE ALARM – FOURTH FLOOR PLAN – A
EF104B ELECTRICAL FIRE ALARM – FOURTH FLOOR PLAN – B
E300 LIGHTING FIXTURE SCHEDULE AND CONTROL DETAILS
E400A1 THIRD FLOOR ELECTRICAL PANEL SCHEDULES
E400A2 THIRD FLOOR ELECTRICAL PANEL SCHEDULES
E400B1 FOURTH FLOOR ELECTRICAL PANEL SCHEDULES
E400B2 FOURTH FLOOR ELECTRICAL PANEL SCHEDULE
LEGIONELLA SUPPRESSION DESIGN
TASK ORDER #1 BUILDING 228
Bancroft-AE Project No. 17-107 00 01 15-8 1-18-2019
E400C MOTOR AND EQUIPMENT SCHEDULE
E500 ELECTRICAL SINGLE LINE DIAGRAM
E501 ELECTRICAL DETAILS
E600 DATA DETAILS
E700 DATA DETAILS
- - - E N D - - -
DIVISION 01
GENERAL REQUIREMENTS
LEGIONELLA SUPPRESSION DESIGN
TASK ORDER #1 BUILDING 228
Bancroft-AE Project No. 17-107 01 00 00-1 1-18-2019
SECTION 01 00 00
GENERAL REQUIREMENTS
TABLE OF CONTENTS
1.1 SAFETY REQUIREMENTS
1.2 GENERAL INTENTION
1.3 STATEMENT OF BID ITEM(S)
1.4 DOCUMENTS FOR CONTRACTOR
1.5 LOGISTICS PLAN REQUIREMENTS
1.6 CONSTRUCTION SECURITY REQUIREMENTS
1.7 OPERATIONS AND STORAGE AREAS
1.8 ALTERATIONS
1.9 RESTORATION
1.10 DISPOSAL AND RETENTION
1.11 SUBMITTAL REGISTRY
1.12 REQUESTS FOR INFORMATION
1.13 PROFESSIONAL SURVEYING SERVICES
1.14 LAYOUT OF WORK
1.15 AS-BUILT DRAWINGS
1.16 USE OF ROADWAYS
1.17 PROTECTIONF OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT,
UTILITIES AND IMPROVEMENTS
1.18 TEMPORARY USE OF MECHANICAL AND ELECTRIAL EQUIPMENT
1.19 TEMPORARY USE OF EXISTING ELEVATORS
1.20 TEMPORARY TOILETS
1.21 AVAILABILITY AND USE OF UTILITY SERVICES
1.22 NEW TELEPHONE EQUIPMENT
LEGIONELLA SUPPRESSION DESIGN
Bancroft-AE Project No. 17-107 01 00 00-2 1-18-2019
1.23 TESTS
1.24 INSTRUCTIONS
1.25 GOVERNMENT-FURNISHED PROPERTY
1.26 RELOCATED EQUIPMENT
1.27 EXTERIOR CONSTRUCTION SIGN
1.28 EXTERIOR SAFETY SIGN
1.29 PHOTOGRAPHIC DOCUMENTATION
1.30 HISTORIC PRESERVATION
LEGIONELLA SUPPRESSION DESIGN
Bancroft-AE Project No. 17-107 01 00 00-3 1-18-2019
SECTION 01 00 00
GENERAL REQUIREMENTS
1.1 SAFETY REQUIREMENTS
Refer to Section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.
1.2 GENERAL INTENTION
A. Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, and furnish labor and materials and perform work as required by this procurement package.
B. Visits to the site by Bidders may be made only by appointment with the
Contracting Officer’s Representative (COR) and through coordination with the Contracting Specialist (CS) assigned to the project by the
Contracting Officer (CO).
C. Before placement and installation of work subject to tests by testing laboratory retained by Department of Veterans Affairs, the Contractor shall notify the COR in sufficient time to enable testing laboratory personnel to be present at the site in time for proper taking and testing of specimens and field inspection. Such prior notice shall be not less than three work days unless otherwise designated by the COR.
D. All employees of General Contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access. Refer to the Contractor PIV Instructions included with the Statement of Work (SOW).
1.3 STATEMENT OF BID ITEM(S)
A. To avoid any potential confusion, all work, services, testing, materials, labor, supervision, safety, security, manuals, and instructions necessary to complete this project as indicated in the procurement package, Statement of Work, Drawings, and/or specifications shall be the responsibility of the Contractor to provide unless expressly stated otherwise.
LEGIONELLA SUPPRESSION DESIGN
Bancroft-AE Project No. 17-107 01 00 00-4 1-18-2019
B. GENERAL CONSTRUCTION: Work includes all general conditions, management, demolition, construction, and trade work necessary to successfully complete this project as outlined in the Statement of Work.
1.4 DOCUMENTS FOR CONTRACTOR
A. Drawings, contract documents, attachments, and reference documents may be obtained from the website where the solicitation is posted or available upon request when noted. Additional copies will be at
Contractor's expense.
1.5 LOGISTICS PLAN REQUIREMENTS
Before any work is started, the Contractor shall submit and receive approval for an accepted Logistics Plan. The Logistics Plan will include
(but is not limited to) the following:
A. An Organizational Chart of all Key Personnel including:
1. The General Contractor’s management personnel.
2. The competent person identified with their corresponding credentials.
3. The Quality Control person.
4. The Site Safety Health Officer.
5. Contact information for all key personnel.
6. Listing of the subcontractors by name and trade.
B. Hourly Rates of the General Contractor and all their subcontractor’s personnel assigned to this project.
1. Total rate = base labor rate + fringes.
2. Fringes = Union dues + FICA + Public Liability Insurance + Workman’s
Compensation.
C. Staging Plan. (Include all that apply)
1. Location of Site Office.
LEGIONELLA SUPPRESSION DESIGN
Bancroft-AE Project No. 17-107 01 00 00-5 1-18-2019
2. Material Storage.
3. Dumpster Location.
4. Site security (fence) and Access Points.
5. Equipment Location.
6. Infection Control Barrier. (refer to the Infection Control Risk
Assessment)
7. Interior construction and safety signage and placement.
8. Fire extinguisher location and other safety devices.
9. Contractor parking.
10. Travel routes for delivery and removal.
11. Closure routes and directional signage for VA vehicular and pedestrian traffic.
D. Description of Means and Method Activities.
1. Management, supervision, and security.
2. Demolition.
3. Construction.
4. Material storage.
5. Inspections and punch list.
E. Hours of Work.
1. Normal working hours.
a. The competent person is always present whenever any work is being performed by either the subcontractor or the General Contractor’s own workforce.
2. Any planned off-hours work.
LEGIONELLA SUPPRESSION DESIGN
Bancroft-AE Project No. 17-107 01 00 00-6 1-18-2019
3. Hours for delivery and disposal.
4. Hours to transport materials to the site and/or through a building.
1.6 CONSTRUCTION SECURITY REQUIREMENTS
A. Security Plan:
1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.
2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.
B. Security Procedures:
1. General Contractor’s employees shall not enter the project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.
2. Before starting work the General Contractor shall give two weeks’ notice to the Contracting Officer so that security arrangements can be provided for the employees. This notice is separate from any notices required for utility shutdown described later in this section.
3. No photography of VA premises is allowed without written permission of the COR in coordination with the Hines Public Affairs Officer
(PAO).
4. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The General Contractor may return to the site only with the written approval of the Contracting Officer.
LEGIONELLA SUPPRESSION DESIGN
Bancroft-AE Project No. 17-107 01 00 00-7 1-18-2019
C. Site Perimeter:
1. The General Contractor shall be responsible for the site security for the project 24 hours a day, 7 days a week.
2. The General Contractor will be responsible for all material and tools stored within the jobsite area and remotely, including those of their subcontractor.
D. Key Control:
1. The General Contractor shall obtain Construction Cores for all locking devices used temporarily during the course of this project.
The Construction Cores shall be provided by the Station. The General
Contractor shall request the Construction Cores in writing to the
COR and will include the number of cores requested, their location to be installed, and the keys requested.
2. Keys for the Construction Cores shall only be assigned to key personnel of the General Contractor including the competent person, the Quality Control person, the Site Safety Health Officer, and other management staff. No keys are to be assigned to subcontractors. All keys are to be returned the COR at the conclusion of the project. Lost keys are to be reported to the COR immediately.
3. The General Contractor shall turn over all permanent lock cylinders to the VA locksmith for permanent installation. See Section
08 71 00, DOOR HARDWARE and coordinate.
E. Document Control:
1. Before starting any work, the General Contractor/Sub Contractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of
“sensitive information”.
2. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This
LEGIONELLA SUPPRESSION DESIGN
Bancroft-AE Project No. 17-107 01 00 00-8 1-18-2019 information shall be shared only with those with a specific need to accomplish the project.
3. Certain documents, sketches, videos or photographs and drawings may be marked “Law Enforcement Sensitive” or “Sensitive Unclassified”.
Secure such information in separate containers and limit the access to only those who will need it for the project. Return the information to the Contracting Officer upon request.
4. These security documents shall not be removed or transmitted from the project site without the written approval of Contracting
Officer.
5. All paper waste or electronic media such as CD’s and portable USB drives shall be shredded and destroyed in a manner acceptable to the
VA.
6. Notify Contracting Officer and Site Security Officer immediately when there is a loss or compromise of “sensitive information”.
7. All electronic information shall be stored in specified location following VA standards and procedures using an Engineering Document
Management Software (EDMS).
a. Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the
EDMS system.
b. “Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.
F. Motor Vehicle Restrictions
1. All requested information of this Section shall be included with the
Logistics Plan of Section 1.5.
2. Vehicle authorization request shall be required for any vehicle entering the site and such request shall be submitted 24 hours
LEGIONELLA SUPPRESSION DESIGN
Bancroft-AE Project No. 17-107 01 00 00-9 1-18-2019 before the date and time of access. Access shall be restricted to picking up and dropping off materials and supplies.
3. A limited number of (2 to 5) permits shall be issued for General
Contractor and its employees for parking in designated areas only.
1.7 OPERATIONS AND STORAGE AREAS
A. All requested information of this Section shall be included with the
Logistics Plan of Section 1.5.
B. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the
Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.
C. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the
Contracting Officer and shall be built with labor and materials furnished by the Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the
Contractor and shall be removed by the Contractor at its expense upon completion of the work. With the written consent of the Contracting
Officer, the buildings and utilities may be abandoned and need not be removed.
D. The Contractor shall, under regulations prescribed by the Contracting
Officer, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the Contracting
Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The
Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.
LEGIONELLA SUPPRESSION DESIGN
Bancroft-AE Project No. 17-107 01 00 00-10 1-18-2019
E. Working space and space available for storing materials shall be coordinated with the COR.
F. All Workmen are subject to rules of the Medical Center applicable to their conduct.
G. The Medical Center spaces including all adjacent spaces above, below, and next to the designated project area are intended to function normally during this project. Execute work so as to interfere as little as possible with normal functioning of Medical Center which will as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others.
Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and Contractor's personnel, except as permitted by the COR.
1. Do not store materials and equipment in other than assigned areas.
2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by the Medical
Center in quantities sufficient for not more than two work days.
3. Provide unobstructed access to the Medical Center areas required to remain in operation.
4. Where access by the Medical Center personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment will be permitted subject to fire and safety requirements.
H. Utilities Services: Where necessary to cut existing pipes, electrical wires, conduits, cables, etc., of utility services, or of fire protection systems or communications systems (except telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by the COR. All such actions shall be coordinated with the COR or Utility Company involved:
1. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction
LEGIONELLA SUPPRESSION DESIGN
Bancroft-AE Project No. 17-107 01 00 00-11 1-18-2019 project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.
I. Phasing:
The Medical Center must maintain its operation 24 hours a day 7 days a week. Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses in operation occur.
It is the CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks. The work to be outlined shall include, but not be limited to:
1. Unless specified elsewhere in the Statement of Work, the project is to be completed in one singular, uninterrupted phase.
2. When more than one phase is required to complete the project, the
Contractor shall furnish the COR with a schedule of approximate phasing dates on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the COR 45 calendar days in advance of the proposed date of starting work in each specific area of site, building or portion thereof. Arrange such phasing dates to insure accomplishment of this work in successive phases mutually agreeable to the Medical Center Director, COR, and Contractor.
3. The Contractor shall take all measures and provide all material necessary for protecting existing equipment and property in affected areas of construction against dust and debris, so that equipment and affected areas to be used in the Medical Centers operations will not be hindered. Contractor shall permit access to Medical Center personnel and patients through other construction areas which serve as routes of access to such affected areas and equipment. These routes whether access or egress shall be isolated from the construction area by temporary partitions and have walking surfaces, LEGIONELLA SUPPRESSION DESIGN
Bancroft-AE Project No. 17-107 01 00 00-12 1-18-2019 lighting, etc., to facilitate patient and staff access. Coordinate alteration work in areas occupied by the Medical Center so that
Medical Center operations will continue during the construction period.
J. Construction Fence: Before construction operations begin, Contractor shall provide a chain link construction fence, seven feet minimum height, around the construction area. Provide gates as required for access with necessary hardware, including hasps and padlocks. Fasten fence fabric to terminal posts with tension bands and to line posts and top and bottom rails with tie wires spaced at maximum 15 inches. Bottom of fences shall extend to one inch above grade. Provide a mesh screen to limit the transmission of dust. Remove the fence when directed by the COR.
K. When a building and/or construction site is turned over to Contractor, Contractor shall accept entire responsibility including upkeep and maintenance therefore:
1. Contractor shall maintain a minimum temperature of 50 degrees F at all times, except as otherwise specified.
2. Contractor shall maintain in operating condition existing fire protection and alarm equipment. In connection with fire alarm equipment, Contractor shall make arrangements for pre-inspection of site with Fire Department or Company (Department of Veterans Affairs or municipal) whichever will be required to respond to an alarm from
Contractor's employee or watchman.
L. Utilities Services: Maintain existing utility services for the Medical
Center at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services.
Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by the COR.
LEGIONELLA SUPPRESSION DESIGN
Bancroft-AE Project No. 17-107 01 00 00-13 1-18-2019
1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of the COR. Electrical work shall be accomplished with all affected circuits or equipment de-energized. When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without a detailed work plan, the Medical Center Director’s prior knowledge and written approval.
2. Contractor shall submit a request to interrupt any such services to the COR, in writing, 3 weeks in advance of proposed interruption.
Request shall state reason, date, exact time of, and approximate duration of such interruption.
3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of the Medical Center. Interruption time approved by Medical Center may occur at other than Contractor's normal working hours.
4. Major interruptions of any system must be requested, in writing, at least 3 weeks prior to the desired time and shall be performed as directed by the COR.
5. In case of a contract construction emergency, service will be interrupted on approval of the COR. Such approval will be confirmed in writing as soon as practical.
6. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.
M. Abandoned Lines: When demolition work creates a condition of abandoned lines, all service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, which are to be abandoned shall be removed to the greatest extent possible from the work zone
LEGIONELLA SUPPRESSION DESIGN
Bancroft-AE Project No. 17-107 01 00 00-14 1-18-2019 area. All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, which are to be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged at the main, branch or panel they originate from. The lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or partitions; so that they are completely behind the finished surfaces. Consult with COR for if any questions exist regarding identification and treatment of abandoned lines.
N. To minimize interference of construction activities with flow of
Medical Center traffic, comply with the following:
1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles.
2. Wherever excavation for new utility lines cross existing roads, at least one lane must be open to traffic at all times with approval.
3. Method and scheduling of required cutting, altering and removal of existing roads, walks and entrances must be approved by the COR.
O. Coordinate the work for this contract with other construction operations as directed by the COR. This includes the scheduling of traffic and the use of roadways.
1.8 ALTERATIONS
A. Survey: Before any work is started, the Contractor shall make a thorough survey with the COR of the buildings or areas of buildings in which alterations occur and areas which are anticipated routes of access, and furnish a report, signed by both, to the Contracting
Officer. This report shall list by rooms and spaces:
1. Existing condition and types of resilient flooring, doors, windows, walls and other surfaces not required to be altered throughout affected areas of the building or buildings.
LEGIONELLA SUPPRESSION DESIGN
Bancroft-AE Project No. 17-107 01 00 00-15 1-18-2019
2. Existence and conditions of items such as plumbing fixtures and accessories, electrical fixtures, equipment, window blinds, shades, etc., required to be either reused or relocated, or both.
3. Shall note any discrepancies between drawings and existing conditions at site.
4. Shall designate areas for working space, materials storage and routes of access to areas within buildings where alterations occur and which have been agreed upon by Contractor and the COR.
B. Any items required by Statement of Work to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of the COR, to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by
Contractor with new items in accordance with specifications which will be furnished by Government. Provided the contract work is changed by reason of this subparagraph B, the contract will be modified accordingly, under provisions of clause entitled "DIFFERING SITE
CONDITIONS" (FAR 52.236-2) and "CHANGES" (FAR 52.243-4 and VAAR
852.236-88).
C. Re-Survey: Thirty days before expected partial or final inspection date, the Contractor and the COR together shall make a thorough re-survey of the areas of buildings involved. They shall furnish a report on conditions then existing, of resilient flooring, doors, windows, walls and other surfaces as compared with conditions of same as noted in first condition survey report:
1. Re-survey report shall also list any damage caused by Contractor to such flooring and other surfaces, despite protection measures; and, will form basis for determining extent of repair work required of
Contractor to restore damage caused by Contractor's workmen in executing work of this contract.
2. Where damage as a result of the Contractor’s means and methods has been determined it shall be the responsibility of the Contractor to
LEGIONELLA SUPPRESSION DESIGN
Bancroft-AE Project No. 17-107 01 00 00-16 1-18-2019 repair subsurfaces in kind and to match finish surfaces with adjacent materials. Such repairs shall be coordinated with the COR.
D. Protection: Provide the following protective measures:
1. Wherever existing roof surfaces are disturbed they shall be protected against water infiltration. In case of leaks, they shall be repaired immediately upon discovery.
2. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled and equipment moved and/or relocated.
3. Protection of interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, floor surfaces that are to remain in place shall be adequately protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.
E. Cutting and Patching: Provide the following measures:
1. Cutting: Cut in-place construction by sawing, drilling, breaking, chipping, grinding, and similar operations, including excavation, using methods least likely to damage elements retained or adjoining construction. If possible, review proposed procedures with original
Installer; comply with original Installer's written recommendations.
2. Patching: Patch construction by filling, repairing, refinishing, closing up, and similar operations following performance of other
Work. Patch with durable seams that are as invisible as possible.
Provide materials and comply with installation requirements specified in other Sections.
3. Do not cut and patch miscellaneous elements or related components in a manner that could change their load-carrying capacity, that results in reducing their capacity to perform as intended, or results in increased maintenance or decreased operational life or safety.
LEGIONELLA SUPPRESSION DESIGN
Bancroft-AE Project No. 17-107 01 00 00-17 1-18-2019
4. Do not cut and patch construction in a manner that results in visual evidence of cutting and patching. Do not cut and patch construction exposed on the exterior or in occupied spaces in a manner that would, in the COR's opinion, reduce the building's aesthetic qualities. Remove and replace construction that has been cut and patched in a visually unsatisfactory manner.
1.9 RESTORATION
A. Remove, cut, alter, replace, patch, and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the
COR. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the COR before it is disturbed. Materials and workmanship used in restoring work shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.
B. Upon completion of contract, deliver work complete and undamaged.
Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.) disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.
C. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workmen to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems (including telephone) which are not scheduled for discontinuance or abandonment.
D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract time and price in accordance with clause entitled "CHANGES"
(FAR 52.243-4 and VAAR 852.236-88) and "DIFFERING SITE CONDITIONS" (FAR
52.236-2).
LEGIONELLA SUPPRESSION DESIGN
Bancroft-AE Project No. 17-107 01 00 00-18 1-18-2019
1.10 DISPOSAL AND RETENTION
A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:
1. Reserved items which are to remain property of the Government are noted in the Statement of Work as items to be stored. Items that remain property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re-installation and reuse. Store such items where directed by the COR.
2. Items not reserved shall become property of the Contractor and be removed by Contractor from the Medical Center.
3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Government. When rooms and spaces are vacated by the Medical Center during the alteration period, such items which are NOT required by Statement of Work to be either relocated or reused will be removed by the Government in advance of work to avoid interfering with Contractor's operation.
4. All disposed material including general demolition, hazardous materials, recycled material, and construction spoils shall be documented with receipts and waste reports to be submitted with each pay application.
1.11 SUBMITTAL REGISTRY
A. Before any work is started, the Contractor shall submit and receive approval for an accepted Submittal Registry. The Submittal Registry shall include a listing of all documentation required for pre-approved submissions including shop drawings, technical data, product performance information, calculations, and samples. The Submittal
Registry shall indicate the name and corresponding CSI numbering, the intended date of delivery by the General Contractor, a government review period of 7 calendar days from date of submission, the return
LEGIONELLA SUPPRESSION DESIGN
Bancroft-AE Project No. 17-107 01 00 00-19 1-18-2019 date by the government, the indication of “acceptance without comments”, “accepted with comments”, “revise and resubmit”, or
“rejected for non-conformance”. Revised submissions shall be indicated with the suffix “-R1” for the first revision, “-R2” for the second revision, and so forth.
B. The Contractor shall review all submittals for conformance with the
Statement of Work and shall indicate their approval with a sticker or label affixed to the submission with the submittal number, reviewer’s signature (not typed or scanned), and date. Any submittal missing this information will promptly be returned to the Contractor without review by the government.
C. Items to be included can be found in the Statement of Work and other specification sections included with the procurement package. Unless otherwise stated, the Submittal Registry shall always include the following (as they apply):
1. Finish materials including ceiling systems, paint, tile, carpet, sheet vinyl, wall base, wall guards, corner cards, and wall protection.
2. Light fixtures.
3. All telecommunication components.
4. Plumbing fixtures including toilets, urinals, sinks, vanities, toilet partitions, and toilet accessories.
5. Doors, frames, hardware, and keying.
6. Millwork and cabinet hardware.
7. Construction and Safety sign design and mounting.
1.12 REQUESTS FOR INFORMATION
A. All Requests for Information (RFI) shall be submitted in writing to the
COR and copied to the Contracting Specialist.
LEGIONELLA SUPPRESSION DESIGN
Bancroft-AE Project No. 17-107 01 00 00-20 1-18-2019
B. Whenever an RFI is submitted the Contractor shall include the following:
1. A detailed description of the issue including references to drawings and/or specifications, photographs (when permitted), and sketches necessary to adequately communicate to the COR.
2. A possible solution for the issue.
3. An assessment as to whether or not the Contractor anticipates the issue will require a Modification to their contract and reasons why a Modification may be necessary.
1.13 PROFESSIONAL SURVEYING SERVICES
A. Where exterior work requires ground excavation, a registered professional land surveyor, registered civil engineer, or certified equivalent professional whose services are retained and paid for by the
Contractor shall perform all utility locate services. The Contractor shall certify that the land surveyor, civil engineer, or equivalent professional is not one who is a regular employee of the Contractor, and that the land surveyor, engineer, or equivalent professional has no financial interest in this contract.
1.14 LAYOUT OF WORK
A. The Contractor shall lay out the work from Government established base lines and bench marks, indicated on the drawings, and shall be responsible for all measurements in connection with the layout. The
Contractor shall furnish, at Contractor's own expense, all stakes, templates, platforms, equipment, tools, materials, and labor required to lay out any part of the work.
B. The Contractor shall be responsible for executing the work to the lines and grades that may be established or indicated by the Contracting
Officer. The Contractor shall also be responsible for maintaining and preserving all stakes and other marks established by the Contracting
Officer until authorized to remove them. If such marks are destroyed by the Contractor or through Contractor's negligence before their removal is authorized, the Contracting Officer may replace them and deduct the
LEGIONELLA SUPPRESSION DESIGN
Bancroft-AE Project No. 17-107 01 00 00-21 1-18-2019 expense of the replacement from any amounts due or to become due to the
Contractor.
1.15 AS-BUILT DRAWINGS
A. The Contractor shall maintain two full size sets of identical as-built drawings which will be kept current during construction of the project, to include all contract changes, modifications and clarifications. One set shall be for the Contractor and the other shall be submitted to the
COR as indicated below.
B. All variations shall be shown in the same general detail as used in the contract drawings. To insure compliance, as-built drawings shall be made available for the COR review, as often as requested.
C. The Contractor shall deliver one approved completed sets of as-built drawings in a hard copy format and another in the electronic version
(scanned PDF) to the COR within 15 calendar days after each completed phase and after the acceptance of the project by the COR.
D. Paragraphs A, B, & C shall also apply to all shop drawings.
1.16 USE OF ROADWAYS
A. All requested information of this Section shall be included with the
Logistics Plan of Section 1.5.
B. For hauling, use only established public roads and roads on Medical
Center property and, when authorized by the COR, such temporary roads which are necessary in the performance of contract work. Temporary roads shall be constructed and restoration performed by the Contractor at Contractor's expense. When necessary to cross curbing, sidewalks, or similar construction, they must be protected by well-constructed bridges.
C. When new permanent roads are to be a part of this contract, Contractor may construct them immediately for use to facilitate building operations. These roads may be used by all who have business thereon within zone of building operations.