P09 - SOW 506-25-502 R2 Final.docx

DOCX document 13 KB Posted

Attached to
Z1DA--Correct SPS Ceiling System Finding 506-25-502 Federal contract opportunity
Solicitation number
36C25025B0012
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 10

About this file

This Statement of Work outlines a construction project at the Ann Arbor VA Medical Center to correct the SPS (Sterile Processing Service) ceiling system. The project involves demolishing the existing acoustical lay-in ceiling system in room DB34 and replacing it with a suspended gypsum board ceiling, including all required labor and materials.

The work schedule operates on two shifts Monday through Friday (6 AM to midnight) and one shift on weekends (6 AM to 5 PM). The project must be completed within 9 consecutive work weeks, with 4 weeks allocated for each of two phases, plus one week for activation between phases. A 4-day period between Phase 1 and Phase 2 is reserved for VA personnel to move and sterilize furniture and equipment. Due to the sterile environment, the pre-bid walkthrough is limited to two employees per general contractor.

View the file

Other files for this federal contract opportunity

Other files attached to Z1DA--Correct SPS Ceiling System Finding 506-25-502, newest first.
File Type Posted
36C25025B0012 0004.docx DOCX document
506-25-502 VA Ann Arbor site plan - Exhibit A 1.pdf PDF
36C25025B0012 0003.docx DOCX document
ATTACHMENT VAAR 852.219-75 DEVIATION Jan 2023 LIMITATIONS OF SUBCONTRACTING COMPLIANCE CERTIFICATION.docx DOCX document
S04 506-25-502 SPS Ceiling - Pre Bid sign in sheet 2025 02 25.pdf PDF
S04 Pre-Bid Site Visit Agenda 506-25-502 - complete.pdf PDF
36C25025B0012 0002.docx DOCX document
36C25025B0012 0001.docx DOCX document
506-25-502 Correct SPS Ceiling System Finding - Bid drawings.pdf PDF
Wage Determination MI20240100 01292025.pdf PDF
Contractor EMR Certification Form - 506-25-502.docx DOCX document
36C25025B0012_1.docx DOCX document
Spec- Bid Documents.pdf PDF
RFI Form - 506-25-502.doc DOC document
Show all 14

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Scope of Work 506-25-502 Correct SPS Ceiling System Findings

Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, and furnish labor and materials and perform work for Ann Arbor VA Medical Center to Correct SPS Ceiling System Finding, Project No. 506-25- 502 as required by drawings and specifications.

Provide all labor and materials required to execute the subject project per specifications and drawings.

Work to include but not be limited to the following: Removal of the existing Acoustical Lay-in ceiling system in SPS room DB34 and replace with a suspended gypsum board ceiling.

Period of Performance - The Contractor shall follow the work periods noted below:

(2) Shifts - Monday thru Friday: 6 AM thru Midnight
(1) Shift - Saturday & Sunday: 6 am thru 5 PM

Allow (4) working days (weekdays) between Phase 1 & Phase 2 for the VA to move and sterilize the furniture and equipment.

Construction of both Phases is to be completed within a period of no more than (9) consecutive work weeks. (4) weeks per Phases (including punch list) then one week for activation between.

The Prebid walk thru will be limited to (2) employees per each General contractor due the Sterilize environment of the Sterile Process room.