36C25025B0012 0003.docx

DOCX document 27 KB Posted

Attached to
Z1DA--Correct SPS Ceiling System Finding 506-25-502 Federal contract opportunity
Solicitation number
36C25025B0012
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 10

About this file

This document is an Amendment (Amendment #0003) to a federal solicitation for a construction project at a Veterans Affairs Medical Center. The solicitation (36C25025B0012) is for correcting a Sprinkler Protection System (SPS) ceiling system finding, located in Ann Arbor, Michigan. The project involves two consecutive construction phases with a total performance period of 63 calendar days, requiring work from Monday-Friday (two shifts) and weekend shifts to accelerate the schedule. The contract includes specific requirements for fire suppression system modifications, with four existing sprinkler heads to be replaced in Phase 1 and six heads in Phase 2.

Key amendment details include adding the VAAR 852.219-75 clause related to subcontracting limitations, incorporating responses to multiple Request for Information (RFI) questions, and extending the offer receipt deadline to March 26, 2025, at 14:00 EDT. The project requires an OSHA 30-hour competent person on-site, provides limited Personal Protective Equipment (PPE) by the VA (gowns, foot covers, hair nets), and mandates contractors work shifts consecutively to expedite the work schedule. Contractors are instructed to submit a single bid price on the SF1442 form for the entire project.

View the file

Other files for this federal contract opportunity

Other files attached to Z1DA--Correct SPS Ceiling System Finding 506-25-502, newest first.
File Type Posted
36C25025B0012 0004.docx DOCX document
506-25-502 VA Ann Arbor site plan - Exhibit A 1.pdf PDF
ATTACHMENT VAAR 852.219-75 DEVIATION Jan 2023 LIMITATIONS OF SUBCONTRACTING COMPLIANCE CERTIFICATION.docx DOCX document
S04 Pre-Bid Site Visit Agenda 506-25-502 - complete.pdf PDF
36C25025B0012 0002.docx DOCX document
S04 506-25-502 SPS Ceiling - Pre Bid sign in sheet 2025 02 25.pdf PDF
36C25025B0012 0001.docx DOCX document
506-25-502 Correct SPS Ceiling System Finding - Bid drawings.pdf PDF
P09 - SOW 506-25-502 R2 Final.docx DOCX document
Wage Determination MI20240100 01292025.pdf PDF
Spec- Bid Documents.pdf PDF
RFI Form - 506-25-502.doc DOC document
Contractor EMR Certification Form - 506-25-502.docx DOCX document
36C25025B0012_1.docx DOCX document
Show all 14

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

36C25025B0012 0003 Attachments

5. PROJECT NUMBER (if applicable)

CODE

7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER

3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO.

1. CONTRACT ID CODE

FACILITY CODE

CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office.

is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER

16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30

PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer) 03-12-2025 506-25-502 36C250 Department of Veterans Affairs Network Contracting Office (NCO) 10 24 Frank Lloyd Wright Drive, Suite M-2200 Ann Arbor

MI

48105 Y Same as Block 6

To all Offerors/Bidders

36C25025B0012 02-12-2025

X X X ** HOUR & DATE for Receipt of Offers is EXTENDED to: 03-26-2025 14:00 EDT The purpose of Amendment #0003 is to:

1. Add the referenced VAAR clause.

2. Provide responses to the Request for Information (RFI).

3. Include VAAR Clause attachment referenced in an RFI.

See Continuation Pages for details.

SF 30 CONTINUATION PAGE 36C25025B0012 AMENDMENT 0003

1. VAAR Clause 852.219-75 is hereby incorporated into this solicitation and any resultant contract.

Failure to provide a correctly completed certification shall result in the proposal/offer being determined non-responsive and shall be rejected.

852.219-75 VA Notice of Limitations on Subcontracting—Certificate of Compliance for Services and Construction.

VA NOTICE OF LIMITATIONS ON SUBCONTRACTING—CERTIFICATE OF COMPLIANCE FOR SERVICES AND CONSTRUCTION (JAN 2023) (DEVIATION)

(a) Pursuant to 38 U.S.C. 8127(l)(2), the offeror certifies that—

(1) If awarded a contract (see FAR 2.101 definition), it will comply with the limitations on subcontracting requirement as provided in the solicitation and the resultant contract, as follows: [Contracting Officer check the appropriate box below based on the predominant NAICS code assigned to the instant acquisition as set forth in FAR 19.102.]

(i) [ ] Services. In the case of a contract for services (except construction), the contractor will not pay more than 50% of the amount paid by the government to it to firms that are not certified SDVOSBs listed in the SBA certification database as set forth in 852.219-73 or certified VOSBs listed in the SBA certification database as set forth in 852.219-74. Any work that a similarly situated certified SDVOSB/VOSB subcontractor further subcontracts will count towards the 50% subcontract amount that cannot be exceeded. Other direct costs may be excluded to the extent they are not the principal purpose of the acquisition and small business concerns do not provide the service as set forth in 13 CFR 125.6.

(ii) [X] General construction. In the case of a contract for general construction, the contractor will not pay more than 85% of the amount paid by the government to it to firms that are not certified SDVOSBs listed in the SBA certification database as set forth in 852.219-73 or certified VOSBs listed in the SBA certification database as set forth in 852.219-74. Any work that a similarly situated certified SDBOSB/VOSB subcontractor further subcontracts will count towards the 85% subcontract amount that cannot be exceeded. Cost of materials are excluded and not considered to be subcontracted.

(iii) [ ] Special trade construction contractors. In the case of a contract for special trade contractors, the contractor will not pay more than 75% of the amount paid by the government to it to firms that are not certified SDVOSBs listed in the SBA certification database as set forth in 852.219-73 or certified VOSBs listed in the SBA certification database as set forth in 852.219-74. Any work that a similarly situated certified SDBOSB/VOSB subcontractor further subcontracts will count towards the 75% subcontract amount that cannot be exceeded. Cost of materials are excluded and not considered to be subcontracted.

(2)The offeror acknowledges that this certification concerns a matter within the jurisdiction of an Agency of the United States. The offeror further acknowledges that this certification is subject to Title 18, United States Code, Section 1001, and, as such, a false, fictitious, or fraudulent certification may render the offeror subject to criminal, civil, or administrative penalties, including prosecution.

(3) If VA determines that an SDVOSB/VOSB awarded a contract pursuant to 38 U.S.C. 8127 did not act in good faith, such SDVOSB/VOSB shall be subject to any or all of the following:

(i) Referral to the VA Suspension and Debarment Committee;

(ii) A fine under section 16(g)(1) of the Small Business Act (15 U.S.C. 645(g)(1)); and

(iii) Prosecution for violating 18 U.S.C. 1001.

(b)The offeror represents and understands that by submission of its offer and award of a contract it may be required to provide copies of documents or records to VA that VA may review to determine whether the offeror complied with the limitations on subcontracting requirement specified in the contract. Contracting officers may, at their discretion, require the contractor to demonstrate its compliance with the limitations on subcontracting at any time during performance and upon completion of a contract if the information regarding such compliance is not already available to the contracting officer. Evidence of compliance includes, but is not limited to, invoices, copies of subcontracts, or a list of the value of tasks performed.

(c)The offeror further agrees to cooperate fully and make available any documents or records as may be required to enable VA to determine compliance with the limitations on subcontracting requirement. The offeror understands that failure to provide documents as requested by VA may result in remedial action as the Government deems appropriate.

(d)Offeror completed certification/fill-in required. The formal certification must be completed, signed and returned with the offeror’s bid, quotation, or proposal. The Government will not consider offers for award from offerors that do not provide the certification, and all such responses will be deemed ineligible for evaluation and award.

Certification:

I hereby certify that if awarded the contract, [insert name of offeror] will comply with the limitations on subcontracting specified in this clause and in the resultant contract. I further certify that I am authorized to execute this certification on behalf of [insert name of offeror].

Printed Name of Signee:________________________________________ Printed Title of Signee:_________________________________________ Signature:___________________________________________________ Date:_____________________ Company Name and Address:______________________________________ (End of clause)

2. The following answers to requests for information questions are hereby provided to clarify, update, revise, or correct contract specifications and/or drawings.

QUESTIONS AND ANSWERS

1. RFI #1 Question: Per the bid submission requirements, where are hand delivered bids to be sent to?

Answer: The bids are to be hand-delivered to Network Contracting Office (NCO) 10 – Ann Arbor, 24 Frank Lloyd Wright Drive, Suite M-2200, Ann Arbor, MI 48105.

2. RFI #2 Question: A bid schedule was not attached with the solicitation documents so are contractors only required to be input pricing on the SF1442 form?

Answer: There is Not a bid schedule. A single bid price for the Entire Project is to be entered on page-2 of the SF1442 in block 17, Offeror Amount. Ensure to complete all lines within Block 17 (Offeror Amount, Offeror Email Address, Offeror Federal Tax ID, and Offeror Unique Entity ID (SAM UEI #).

3. RFI #3 Question: The VAAR 852.219-75 section was not included in the solicitation package. Can the VA please advise if this form can be included.

Answer: See attached document, ATTACHMENT VAAR 852.219-75 (DEVIATION Jan 2023) LIMITATIONS OF SUBCONTRACTING COMPLIANCE CERTIFICATION.

4. RFI #4 Question: The scheduling requirements show 2 shifts from Monday-Friday 6am-12pm and 1 shfit on Saturday to Sunday 6am-5pm. Is the intent to have these shifts work consecutively by the prime contractor in order to accelerate the schedule or is it just the timing that the space is available to be worked on?

Answer: The prime contractor shall work the shifts consecutively to accelerate and expedite the work schedule including the weekends to comply with the period of performance.

5. RFI #5 Question: Temporary construction notes on page G-100 state that PPE is to be provided by the VAMC. Can the VA please advise what is included in the PPE that will be furnished?

Answer: Gowns, foot covers, hair nets & hair nets for facial hair.

6. RFI #6 Question: Is air sampling throughout the project still required if monitors are provided during construction? Is a log to be kept of levels every 3-4 hours?

Answer: Comply with the all-General Infection Controls notes on sheet G-100.

7. RFI #7 Question: Are design drawings and calculations required by a NICET Level IV engineer for the new sprinkler head install?

Answer: No.

8. RFI #8 Question: Are any flow tests required as part of the new sprinkler head installation?

Answer: No

9. RFI #9 Question: What is the period of performance for this contract?

Answer: A total of 63 Calendar days from the Notice to Proceed is the Period of Performance for this project. This is for construction of both Phases of the project of no more than Nine (9) consecutive work weeks. Four (4) weeks per Phase (including Punch List) then one week for activation between Phases.

10. RFI #10 Question: Is a separate quality control manager required for this project? If so, are triple hatting efforts allowed between superintendent, site safety health officer, and the quality control manager?

Answer: No, however an approved, OSHA 30-hour competent person for the prime contractor is required on-site at all times when work is being performed.

11. RFI #11 Question: Are as-built drawings available for the fire suppression systems? If they are available and pending how detailed they are, the cost of engineering design drawings would drop significantly.

Answer: No as-builts are available. Four (4) existing head will require replacement in Phase 1, and Six (6) existing heads will require replacement in Phase 2

See attached document: ATTACHMENT VAAR 852.219-75 DEVIATION Jan 2023 LIMITATIONS OF SUBCONTRACTING COMPLIANCE CERTIFICATION.