This document is an amendment to Solicitation 36C25024Q0617, a service-disabled veteran-owned small business (SDVOSB) set-aside issued by the Department of Veterans Affairs Network Contracting Office 10. The key details are:
The amendment provides additional questions and answers, announces a site visit on 6/24/2024, and specifies that quotes are due by 7/3/2024. The solicitation is for roof top fall protection maintenance and repair at the Cleveland VA Medical Center. Technically acceptable quotes must include a critical fall protection detail plan, existing safety protocols, review by a Certified Safety Professional, and the ability to use the VA's safety database. Roof plans will be provided in a separate amendment. Contractors are required to submit the critical fall protection plan prior to contract award, not just the notice to proceed. The contract period of performance is one year, with a possible option to extend.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C25024Q0617 0011.docx | DOCX document | |
| 36C25024Q0617 0010.docx | DOCX document | |
| 36C25024Q0617 0009.docx | DOCX document | |
| 36C25024Q0617 0008.docx | DOCX document | |
| 36C25024Q0617 0007.docx | DOCX document | |
| 36C25024Q0617 0006.docx | DOCX document | |
| QUESTIONS REGARDING SOLICITATION 36C25024Q0617.docx | DOCX document | |
| 36C25024Q0617 0005.docx | DOCX document | |
| 36C25024Q0617 0003.docx | DOCX document | |
| 36C25024Q0617 0002.docx | DOCX document | |
| 36C25024Q0617 0001.docx | DOCX document | |
| P07. WAGE DETERMINATION LIST-2015-4727-REVISION 23.pdf | ||
| 36C25024Q0617.docx | DOCX document | |
| P07. WAGE DETERMINATION LIST-2015-4727-REVISION 22.pdf |
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE
7.
ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF
PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE
OF YOUR
ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office.
is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERE
D CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES
SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendmen t, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED
STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER
16A. NAME AND TITLE OF
CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF
SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer) 541-24-1-2076-0027
NONE
36C250 Department of Veterans Affairs Network Contracting Office (NCO) 10 6100 Oak Tree Blvd., Suite 490 Independence OH 44131 36C250 Department of Veterans Affairs Network Contracting Office (NCO) 10 6100 Oak Tree Blvd., Suite 490 Independence OH 44131 To all Offerors/Bidders
36C25024Q0617 06-20-2024
X
X Please note the following amendment to Solicitation 36C25024Q0617:
1. Attached is additional questions and answers regarding the solicitation.
2. A site visit will take place on 6-24-2024 at 11 am at the Cleveland VA Medical Center.
3. Quotes are due by email by 7-3-2024 by 3 pm est.
4. Please continue to look on Contract Opportunities for any further updates.
Roman Savino Contract Specialist
CONTINUATION PAGE
QUESTIONS REGARDING SOLICITATION 36C25024Q0617
1. Will a Site Visit be provided?
Answer: A site visit will be scheduled for Monday June 24th, 2024, at 11 am. Please gather at the Atrium Level by the front door at the Cleveland VA Medical Center Wade Park Campus (10701 East Blvd, Cleveland, Ohio 44106)
2. Is there a Budget amount for this project?
Answer: The pricing to complete this requirement will be determined by the contracting submitting a quote for evaluate.
3. Is there a Technical Write Up required with the proposal submission?
Answer:
a. This requirement Authority for this solicitation is FAR Part 13 (Simplified Acquisition Procedures). The Government will award a contract resulting from this solicitation to the responsible offeror whose offer conforms to the solicitation requirements. The following factors shall be used to evaluate conforming quotes: (1) Lowest Price Technically Acceptable
b. To be technically acceptable the quote must show:
· Contractor must provide a critical fall protection detail plan associated with this project which will need to be incorporated into the existing VA Cleveland Safety database.
· The plan must include existing safety protocols for Lockout/Tagout, Permit-Required Confined Space Entry and associated Job Hazard Analysis (JHA) and/or Safe Operating Procedure (SOP.)
· The project must be reviewed by a CSP (Certified Safety Professional) from the contractor.
· Contractor must be able to use the required VA Cleveland Safety database Microsoft Access.
· Contractor must provide training to select VA employees that will be interacting and/or modifying procedures using the VA Cleveland Safety Database.
4. Is solicitation 36C25024Q0617 a SDVOSB Set-Aside:
Answer: Yes, it is a Service-Disabled Veteran Owned Small Business Set-Aside
5. Will there by roof plans or drawings available?
Answer: Another amendment (0003) will have the attached roof plans
6. Per amendment 36C25024Q0617-0002 Section 3.B states that offers are required to submit a CRITICAL FALL PROTECTION PLAN prior to contract award. Are contractors required to incur the administrative costs of providing a job specific critical safety plan prior to contract award? In our contracting experience this should be a required submittal prior to the issuance of the NTP (Notice to Proceed).
Answer: To be technically acceptable for this requirement, by submitting a quote, a contractor is stating they are able to provide and meet all the requirements that are stated in the solicitation. The Critical Fall Protection Plan should be submitted prior to the issuance of the NTP.