This amendment to a solicitation provides additional drawings and a project schedule for opportunity number 36C25021B0033. The Department of Veterans Affairs seeks to upgrade and expand security camera systems at the VA Medical Center in Battle Creek, Michigan. The contractor will remove all existing cameras, wiring, and DVRs, and install new POIP cameras using CAT6A and fiber optic cable. Additional equipment to be installed includes patch panels, network switches, and NVRs to support the new cameras and minimize bandwidth usage. New software will also be provided to access and monitor network recordings. The contractor will have 180 days to complete the work. The NAICS code is 238990 and size standard is $16.5 million. The government intends to award a firm fixed price contract within 180 days of bid receipt.

View the file

Other files for this federal contract opportunity

Other files attached to Z1DA--Upgrade and Expand Security Camera's 515-18-201, newest first.
File Type Posted
36C25021B0033 0005.docx DOCX document
RFI - combined.docx DOCX document
10-A.120 - RCP - BASEMENT.pdf PDF
08-A.121 - RCP - FIRST FLOOR.pdf PDF
10-A.122 - RCP - SECOND FLOOR.pdf PDF
04-A.122 - RCP - SECOND FLOOR.pdf PDF
07-A.122 - RCP - SECOND FLOOR.pdf PDF
02-A.121 - RCP - FIRST FLOOR.pdf PDF
36C25021B0033 0003.docx DOCX document
06-A.121 - RCP - FIRST FLOOR.pdf PDF
05-A.121 - RCP - FIRST FLOOR.pdf PDF
07-A.120 - RCP - BASEMENT.pdf PDF
03-A.121 - RCP - FIRST FLOOR.pdf PDF
01-A.122 - RCP - SECOND FLOOR.pdf PDF
22-A.121 - RCP - FIRST FLOOR.pdf PDF
22-A.120 - RCP - BASEMENT.pdf PDF
13-A.122 - RCP - SECOND FLOOR.pdf PDF
13-A.123 - RCP - THIRD FLOOR.pdf PDF
50 10EY101 - BLDG 10 FIRST FLOOR NEW WORK PLAN.pdf PDF
13-A.120 - RCP - BASEMENT.pdf PDF
example project schedule.pdf PDF
14-A.120 - RCP - BASEMENT.pdf PDF
13-A.121 - RCP - FIRST FLOOR.pdf PDF
14-A.121 - RCP - FIRST FLOOR.pdf PDF
14-A.122 - RCP - SECOND FLOOR.pdf PDF
20 02EY102A - BLDG 02 PARTIAL SECOND FLOOR NEW WORK PLAN - AREA A.pdf PDF
02-A.120 - RCP - BASEMENT.pdf PDF
01-A.121 - RCP - FIRST FLOOR.pdf PDF
05-A.122 - RCP -SECOND FLOOR.pdf PDF
02-A.122 - RCP - SECOND FLOOR.pdf PDF
04-A.121 - RCP - FIRST FLOOR.pdf PDF
08-A.120 - RCP - BASEMENT.pdf PDF
08-A.122 - RCP - SECOND FLOOR.pdf PDF
10-A.121 - RCP - FIRST FLOOR.pdf PDF
06-A.122 - RCP - SECOND FLOOR.pdf PDF
07-A.121 - RCP - FIRST FLOOR.pdf PDF
05-A.120 - RCP - BASEMENT.pdf PDF
01-A.120 - RCP - BASEMENT.pdf PDF
36C25021B0033 0002.docx DOCX document
36C25021B0033 0001.docx DOCX document
18-201 Pre-bid attendance.pdf PDF
515-18-201 - Contractor EMR Certification Form 2021.docx DOCX document
515-18-201 - UPGRADE AND EXPAND SECURITY CAMERA SYSTEM Specifications.pdf PDF
515-18-201 - WD-MI20210079 01-29-2021.docx DOCX document
36C25021B0033_1.docx DOCX document
515-18-201 - RFI Form.docx DOCX document
515-18-201 Drawings.pdf PDF
Show all 47

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

36C25021B0033 0003 Attachments

5. PROJECT NUMBER (if applicable)

CODE

7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER

3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO.

1. CONTRACT ID CODE

FACILITY CODE

CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office.

is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER

16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30

PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer)

06-15-2021

515-18-201

Department of Veterans Affairs Network Contracting Office (NCO) 10 6150 Oak Tree Blvd., Suite 300

Independence OH 44131

Department of Veterans Affairs Network Contracting Office (NCO) 10 6150 Oak Tree Blvd., Suite 300

Independence OH 44131 To all Offerors/Bidders

36C25021B0033 05-19-2021

X x x

1. The purpose of this amendment is to:

2. Provide additional Drawings and project schedule

Contract Specialist

See attached document: 13-A.120 - RCP - BASEMENT.

See attached document: 13-A.121 - RCP - FIRST FLOOR.

See attached document: 13-A.122 - RCP - SECOND FLOOR.

See attached document: 13-A.123 - RCP - THIRD FLOOR.

See attached document: example project schedule.

See attached document: 22-A.121 - RCP - FIRST FLOOR.

See attached document: 14-A.122 - RCP - SECOND FLOOR.

See attached document: 14-A.120 - RCP - BASEMENT.

See attached document: 50 10EY101 - BLDG 10 FIRST FLOOR NEW WORK PLAN.

See attached document: 20 02EY102A - BLDG 02 PARTIAL SECOND FLOOR NEW WORK PLAN - AREA A.

See attached document: 14-A.121 - RCP - FIRST FLOOR.