New combined drawing pdf set with updated AF101 and AS111.pdf
PDF 24 MB Posted
- Solicitation number
- 36C25021B0020
About this file
This document outlines a federal construction contract opportunity with the Department of Veterans Affairs. The solicitation is for project #583-18-102 to renovate the histology, cytology, and molecular labs at the Richard L. Roudebush - VHA Health Care System. The contractor will provide all labor, materials, and equipment to complete the renovation in accordance with the solicitation terms, conditions, specifications and drawings. The project is reserved solely for Service-Disabled Veteran-Owned Small Businesses and has a North American Industry Classification code of 236220. The construction value is estimated between $2,000,000 to $5,000,000.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONTRACTOR
STATEMENT OF BID ITEMS
ALTERNATE A - ELIMINATE RESIDENT AND TEACHING MICROSCOPE ROOMS
REMOVE RESIDENT ROOM (A-2099) AND TEACHING MICROSCOPE (A-2100) FROM SCOPE OF WORK. ALL WORK AND FINISHES IN
THESE ROOMS ARE TO BE OMITTED.
ALTERNATE B - ELIMINATE STERILE SOLUTION
REMOVE ALL BUILT-IN CASEWORK IN STERILE SOLUTION (A-2051) FROM THE SCOPE OF WORK.
A
B
BID ITEM #1: BASE BID.
CONTRACTOR HAULING
CONTRACTOR HAULING
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
Consultant:
GUIDON DESIGN INC.
1221 N. PENNSYLVANIA ST. | INDIANAPOLIS, IN. 46202
317.800.6388 | WWW.GUIDONDESIGN.COM
SUSTAINABLE ARCHITECTURE + ENGINEERING
PROJECT LEAD
Architect, Structural Engineer, Civil Engineer
C U s e rs
\d v a lla n d in g h a m \D o c u m e n ts
\1 .1
.0
V A
I n d ia n a p o lis
L a b
R e n o v a ti o n d v a lla n d in g h a m g u id o n d e s ig n .c o m
.r v t
/1
/2
:3
:5
P
M
GI000
COVER SHEET
HEAPY ENGINEERING
3850 PRIORITY WAY SOUTH SUITE 204
INDIANAPOLIS, IN 46240
317.571.8795
WWW.HEAPY.COM
RENOVATE LAB - HISTOLOGY,
CYTOLOGY, AND MOLECULAR
1481 W 10TH ST, INDIANAPOLIS, IN
583-18-102
06/24/2020 JC DV
BID DOCUMENTS
FULLY SPRINKLERED
RICHARD L. ROUDEBUSH VA MEDICAL CENTER
1481 W 10TH ST, INDIANAPOLIS, IN
BID DOCUMENTS
RENOVATE LAB - HISTOLOGY,
CYTOLOGY, AND MOLECULAR
583-18-102
SHEET LIST
SHEET
NUMBER SHEET NAME
GENERAL
GI000 COVER SHEET
GI101 LIFE SAFETY PLAN
GI102 PHASING PLAN - PHASE 1
GI103 PHASING PLAN - PHASE 2
GI104 PHASING PLAN - PHASE 3
GI105 PHASING PLAN - PHASE 4
GI106 PHASING PLAN - PHASE 5
GI107 PHASING PLAN - PHASE 6
GI108 PHASING PLAN - PHASE 7
GI109 PHASING PLAN - PHASE 8
GI110 PHASING PLAN - PHASE 9
GI111 PHASING PLAN - PHASE 10
GI112 PHASING PLAN - PHASE 11
GI113 PHASING PLAN - PHASE 12
GI114 EXISTING SECOND FLOOR EQUIPMENT PLAN
GI115 ICRA CLASS III (IDEAL)
GI116 ICRA CLASS III (ALTERNATIVE)
ARCHITECTURAL
AS001 ARCHITECTURAL SYMBOLS AND ABBREVIATIONS
AS002 ARCHITECTURAL STANDARDS
AD101 SECOND FLOOR DEMOLITION PLAN
AS101 SECOND FLOOR ARCHITECTURAL PLAN
AS111 SECOND FLOOR REFLECTED CEILING PLAN
AS502 CASEWORK SECTIONS
AS503 CASEWORK SECTIONS AND INTERIOR DETAILS
AS601 OPENING SCHEDULES
AF101 SECOND FLOOR FINISH PLAN
AQ101 SECOND FLOOR EQUIPMENT PLAN
AQ401 SECOND FLOOR ENLARGED EQUIPMENT PLANS
AQ402 SECOND FLOOR ENLARGED EQUIPMENT PLANS
AQ801 EQUIPMENT CASEWORK ELEVATIONS
AQ802 EQUIPMENT CASEWORK ELEVATIONS
AQ803 EQUIPMENT CASEWORK ELEVATIONS
FIRE PROTECTION
FP001 LEGEND, ABBREVIATIONS & INDEX OF DRAWINGS
FP102 PARTIAL SECOND FLOOR PLAN - FIRE SUPPRESSION
PLUMBING
P001 LEGEND, ABBREVIATIONS & INDEX OF DRAWINGS
PD102 PARTIAL FLOOR PLANS - REMOVALS
PD103 PARTIAL INTERSTITIAL SPACE PLAN - REMOVAL
PD104 PARTIAL THIRD FLOOR PLAN - REMOVALS
PP101 PARTIAL FIRST FLOOR PLANS - DRAINAGE & FIRE SUPPRESSION
PP102 PARTIAL SECOND FLOOR PLANS - DRAINAGE & DISTRIBUTION
PP103 PARTIAL SECOND FLOOR PLANS - DRAINAGE & DISTRIBUTION
PP104 PARTIAL THIRD FLOOR PLANS - DISTRIBUTION
PP105 PARTIAL THIRD FLOOR PLANS - DRAINAGE
P501 SCHEDULES & DIAGRAMS
P901 SOIL, WASTE AND VENT
MECHANICAL
M001 LEGEND, ABBREVIATIONS & INDEX OF DRAWINGS
MD102 PARTIAL SECOND FLOOR PLAN - REMOVALS
MD103 PARTIAL THIRD FLOOR PLAN - REMOVALS
MH102 PARTIAL SECOND FLOOR PLANS - DUCTWORK
MH103 PARTIAL THIRD FLOOR PLANS - DUCTWORK
MP102 PARTIAL SECOND FLOOR PLAN - PIPING
MP103 PARTIAL THIRD FLOOR PLAN - PIPING
M501 DETAILS
M502 DETAILS
M503 DETAILS
M601 SCHEDULES
M701 CONTROLS AND AUTOMATION
M702 CONTROLS AND AUTOMATION
ELECTRICAL
E001 LEGEND, ABBREVIATIONS & INDEX OF DRAWINGS
ED102 PARTIAL SECOND FLOOR PLAN - REMOVALS
EL102 PARTIAL SECOND FLOOR PLANS - LIGHTING, POWER
EP102 PARTIAL SECOND FLOOR PLANS - POWER
EP401 ENLARGED TEMPORARY PLANS
EY102 PARTIAL SECOND FLOOR PLANS - FIRE ALARM
E501 DETAILS
E601 SCHEDULES & DIAGRAMS
E602 PANEL SCHEDULE
TECHNOLOGY
T001 TECHNOLOGY LEGEND
TD102 PARTIAL SECOND FLOOR PLAN - TECHNOLOGY - REMOVALS
T101 PARTIAL SECOND FLOOR PLAN - TECHNOLOGY - TEMPORARY
T102 PARTIAL SECOND FLOOR PLAN - TECHNOLOGY - NEW WORK
T401 TECH ROOM
T501 TECHNOLOGY DETAILS
T502 SECURITY DETAILS
Contact:Contact:Contact: Contact: Contact:
HEAPY ENGINEERING
Joel Summers
Sr. Electrical Designer
ELECTRICAL
ENGINEER
HEAPY ENGINEERING
Luke Richter
Mechanical Engineer
3850 Priority Way South Suite 204 Indianapolis, IN 46240 p: 317.571.8795 ext. 3515 e: ldrichter@heapy.com
MECHANICAL
ENGINEER
RICHARD L. ROUDEBUSH
VA MEDICAL CENTER
Mary Piwowarski
Project Engineer / COR
Richard L. Roudebush VAMC Indianapolis, IN 46202 p: 317.988.4521 e: mary.piwowarski@va.gov
OWNER
GUIDON DESIGN INC.
David Vallandingham
Architect / Project Manager
1221 N. Pennsylvania St.
Suite 200 Indianapolis, IN 46202 p: 317.800.6388 x 130 e: dvallandingham@guidondesign.com
ARCHITECT
HEAPY ENGINEER
Matthew Graham
Principal, Healthcare Practice
LEAD ENGINEER
3850 Priority Way South Suite 204 Indianapolis, IN 46240 p: 317.571.8795 e: jasummers@heapy.com
1400 West Dorothy Lane Dayton, OH 45409 p: 937.224.0861 e: msgraham@heapy.com
AREA MAP
VICINITY MAP
Contact:
HEAPY ENGINEERING
Russell Gill
Sr. Technology Designer
TECHNOLOGY
ENGINEER
3850 Priority Way South Suite 204 Indianapolis, IN 46240 p: 317.571.8795 e: rsgill@heapy.com
Revisions: Date:
CONTRACTOR HAULING PATH - SECOND FLOOR CONTRACTOR HAULING PATH - BASEMENT
UP
UP
CODE CRITERIA
GENERAL: THIS SUMMARY OF CODE REQUIREMENTS IS BASED PRIMARILY ON NFPA 101 (LSC). DESIGN FEATURES NOT ADDRESSED BY NFPA 101 OR DOCUMENTS REFERENCED THEREIN SHALL COMPLY WITH THE REQUIREMENTS OF THE LATEST EDITION OF THE IBC OR AS OTHERWISE IDENTIFIED. FOR DESIGN FEATURES THAT ARE ADDRESSED BY BOTH THE IBC AS WELL AS NFPA 101 OR A DOCUMENT REFERENCED BY NFPA 101, THE REQUIREMENTS OF NFPA 101 OR THE DOCUMENT REFERENCED BY NFPA 101 SHALL BE USED EXCLUSIVELY (THIS APPLIES EVEN IF THE IBC REQUIREMENTS ARE DIFFERENT).
LOCAL CODES: AS AN AGENCY OF THE FEDERAL GOVERNMENT, VA IS NOT SUBJECT TO LOCAL IMPOSITION OF CODE ENFORCEMENT PROCEDURES (DRAWING REVIEWS, BUILDING PERMITS, INSPECTIONS, FEES, ETC.). VA MUST FUNCTION AS THE AUTHORITY HAVING JURISDICTION (AHJ) AND THUS HAS THE RESPONSIBILITY TO GUARD
PUBLIC HEALTH AND SAFETY THROUGH ENFORCING ITS ADOPTED CODES.
NOTES:
CONFLICTS BETWEEN NATIONALLY RECOGNIZED CODES AND STANDARDS AND VA REQUIREMENTS – SHOULD A CONFLICT EXIST BETWEEN VA REQUIREMENTS AND VA ADOPTED NATIONALLY RECOGNIZED CODES AND STANDARDS, THE CONFLICT SHALL BE BROUGHT TO THE ATTENTION OF VA. THE RESOLUTION OF THE CONFLICT SHALL BE MADE BY THE AUTHORITY HAVING JURISDICTION FOR VA TO ENSURE A CONSISTENCY SYSTEM WIDE.
CODE REVIEW
THE 2018 EDITION OF THE LIFE SAFETY CODE, NFPA 101, HAS BEEN USED TO REVIEW THIS PROJECT FOR COMPLIANCE WITH THE FIRE AND LIFE SAFETY REQUIREMENTS.
FOR FEATURES NOT ADDRESSED BY NFPA 101 AND THE REFERENCED NATIONAL FIRE CODES, THE 2018 EDITION OF THE INTERNATIONAL BUILDING CODE HAS BEEN
USED.
PROJECT SCOPE
THE PROJECT SCOPE INCLUDES RENOVATION OF APPROXIMATELY 6,800 SF OF AN EXISTING 8,730 SF PATHOLOGY AND MICROBIOLOGY LAB SUITE. THE PROJECT INCLUDES DEMOLITION OF MUCH OF THE EXISTING SUITE. THE RENOVATION INCLUDES NEW WALLS, DOORS, CEILINGS AND FINISHES. IT ALSO INCLUDES NEW
MECHANICAL DISTRIBUTION, PLUMBING, AND ELECTRICAL.
CODE ANALYSIS
THE CONSTRUCTION TYPE IS DETERMINED BASED UPON THE ALLOWABLE AREA AND HEIGHT REQUIREMENTS OF CHAPTER 5 OF THE 2018 IBC. CONSTRUCTION TYPE AND MATERIALS SHALL BE PER CHAPTER 6 OF THE IBC FOR TYPE1A (IBC CHAPTER 5) 333 (NFPA 101) CONSTRUCTION AS FOLLOWS:
1. OCCUPANCY TYPE: B USINESS OCCUPANCY ADJACENT TO AN I-2 INSTITUTIONAL, IBC CHAPTER 3/LSC CHAPTER 18 HEALTHCARE
2. CONSTRUCTION TYPE: 1A (IBC CHAPTER 5) 333 (NFPA 101)
3. FIRE RESISTIVE RATINGS TYPE 1A CONSTRUCTION, CHAPTER 6 IBC/NFPA 101:
STRUCTURAL FRAME: NONCOMBUSTIBLE, 3-HOUR FIRE RESISTIVE
BEARING WALLS
EXTERIOR: NONCOMBUSTIBLE,3-HOUR FIRE RESISTIVE
INTERIOR: NONCOMBUSTIBLE, 3-HOUR FIRE RESISTIVE
NON-BEARING WALLS AND PARTITIONS
EXTERIOR: NONCOMBUSTIBLE, 1-HOUR FIRE RESISTIVE
INTERIOR: NONCOMBUSTIBLE, 0-HOUR FIRE-RESISTIVE
FLOOR: NONCOMBUSTIBLE, 2-HOUR FIRE RESISTIVE
ROOF: NONCOMBUSTIBLE, 1 1/2-HOUR FIRE RESISTIVE
SHAFT ENCLOSURES 2-HOUR FIRE RESISTIVE >4 STORIES (IBC 713.4, LSC 12.3.6)
SHAFT ENCLOSURES 1-HOUR FIRE RESISTIVE <4 STORIES (IBC 713.4, LSC 12.3.6)
4. STRUCTURAL DESIGN SHALL COMPLY WITH CHAPTER 16 OF THE IBC.
5. ALLOWABLE HEIGHT:UNLIMITED FT (IBC, TABLE 504.3)
6. ALLOWABLE NUMBER OF STORIES ABOVE GRADE PLAN: UNLIMITED (IBC, TABLE 504.4)
7. ALLOWABLE AREA: BASED UPON B OCCUPANCY, 1A CONSTRUCTION TYPE, AND FULLY SPRINKLED: ALLOWABLE AREA: UNLIMITED (IBC, TABLE 506.2)
8. BUILDING SEPARATION: BASED ON A 30 FEET PLUS FIRE SEPARATION DISTANCE A 0-HOUR FIRE RESISTANCE WALL RATING IS REQUIRED. (IBC, TABLE 602)
9. OCCUPANCY SEPARATION: A 1- HOUR OCCUPANCY SEPARATION IS REQUIRED BETWEEN THE AMBULATORY CLINIC B OCCUPANCY (LCS CHAPTER 18) AND OTHER
OCCUPANCIES. (LSC 20.1.3.2)
SECTIONS OF HEALTH CARE FACILITIES SHALL BE PERMITTED TO BE CLASSIFIED AS OTHER OCCUPANCIES, PROVIDED THAT THEY MEET BOTH OF THE FOLLOWING
CONDITIONS: (LSC 18.1.3.3)
(1) THEY ARE NOT INTENDED TO PROVIDE SERVICES SIMULTANEOUSLY FOR FOUR OR MORE INPATIENTS FOR PURPOSES OF HOUSING, TREATMENT, OR CUSTOMARY
ACCESS BY INPATIENTS INCAPABLE OF SELF-PRESERVATION.
(2) THEY ARE SEPARATED FROM AREAS OF HEALTH CARE OCCUPANCIES BY CONSTRUCTION HAVING A MINIMUM 2-HOUR FIRE RESISTANCE RATING IN ACCORDANCE
WITH CHAPTER 8.18.1.3.4 CONTIGUOUS NON-HEALTH CARE OCCUPANCIES.
10. MEANS OF EGRESS
• CLEAR WIDTH OF CORRIDORS SHALL BE CLEAR 8 FEET.
• AISLES, CORRIDORS, AND RAMPS IN ADJUNCT AREAS NOT INTENDED FOR THE HOUSING, TREATMENT, OR USE OF INPATIENTS SHALL BENT LESS THAN 44 IN.
(1120 MM) IN CLEAR AND UNOBSTRUCTED WIDTH.
• CLEAR WIDTH OF DOORS SHALL BE CLEAR 42 INCHES FROM SLEEPING ROOMS; DIAGNOSTIC AND TREATMENT AREAS, SUCH AS X-RAY, SURGERY, OR PHYSICAL
THERAPY;.
• CLEAR WIDTH OF DOORS SHALL BE CLEAR 32 INCHES
• NOT LESS THAN 2 EXITS SHALL BE PROVIDED PER FLOOR.
• ADDITION OCCUPANCY LOAD: <500 THEREFORE 2 EXITS REQUIRED (LSC 7.4.1)
• MAXIMUM TRAVEL DISTANCE, FULLY SPRINKLED: 200 FEET (LSC 18.2.6.2.1)
• COMMON PATH OF TRAVEL SHALL NOT EXCEED 100 FEET (LSC 18.2.5.3)
• DEAD END CORRIDORS SHALL NOT EXCEED 30 FEET. (LSC 18.2.5.2)
• MEANS OF EGRESS SHALL BE ILLUMINATED PER 7.9. (LSC 18.2.6.2.1)
• EMERGENCY LIGHTING SHALL BE PER 7.9. (LSC 18.2.9)
• EXIT SIGNAGE SHALL BE PROVIDED 7.10. (LSC 18.2.10)
11. WHERE GENERAL ANESTHESIA OR LIFE SUPPORT EQUIPMENT IS USED AND ESSENTIAL ELECTRICAL SYSTEM PER NFPA 99 SHALL BE PROVIDED.
12. HAZARDOUS AREAS. ANY HAZARDOUS AREAS SHALL BE PROTECTED IN ACCORDANCE WITH SECTION 8.7, AND THE AREAS DESCRIBED IN TABLE 18.3.2.1 SHALL BE
PROTECTED AS INDICATED. (LSC 18.3.2.2)
TABLE 18.3.2.1
• HAZARDOUS AREA PROTECTION HAZARDOUS AREA DESCRIPTION PROTECTION/SEPARATION BOILER AND FUEL-FIRED HEATER ROOMS 1 HOUR CENTRAL/BULK
LAUNDRIES LARGER THAN 100 FT2 (9.3 M2)1 HOUR
• LABORATORIES EMPLOYING FLAMMABLE OR COMBUSTIBLE MATERIALS IN QUANTITIES LESS THAN THOSE THAT WOULD BE CONSIDERED A SEVERE HAZARD SEE
18.3.6.3.11.
• LABORATORIES THAT USE HAZARDOUS MATERIALS THAT WOULD BE CLASSIFIED AS A SEVERE HAZARD IN ACCORDANCE WITH NFPA 99, STANDARD FOR HEALTH
CARE FACILITIES 1 HOUR
• PAINT SHOPS EMPLOYING HAZARDOUS SUBSTANCES AND MATERIALS IN QUANTITIES LESS THAN THOSE THAT WOULD BE CLASSIFIED AS A SEVERE HAZARD 1
HOUR
• PHYSICAL PLANT MAINTENANCE SHOPS 1 HOUR
• ROOMS WITH SOILED LINEN IN VOLUME EXCEEDING 64 GAL (242 L)1 HOUR
• STORAGE ROOMS LARGER THAN 50 FT2(4.6 M2) BUT NOT EXCEEDING 100 FT2 (9.3 M2) AND STORING COMBUSTIBLE MATERIAL SEE 18.3.6.3.11.
• STORAGE ROOMS LARGER THAN 100 FT2 (9.3 M2) AND STORING COMBUSTIBLE MATERIAL 1 HOUR
• ROOMS WITH COLLECTED TRASH IN VOLUME EXCEEDING 64 GAL (242 L)1 HOUR† MINIMUM FIRE RESISTANCE RATING.
13. INTERIOR FINISH
• WALLS AND CEILINGS: INTERIOR FINISH FLAME SPREAD SHALL BE LIMITED PER CHAPTER 10.2 OF THE NFPA 101 TO CLASS A MATERIALS. (LSC 18.4.3.6.2)
• · CLASS A: FLAME SPREAD 0-25; SMOKE DEVELOPED 0-450.
• FLOORS: INTERIOR FLOOR FINISH SHALL BE CLASS I.
• FABRIC DRAPERIES, CURTAINS (EXCLUDING SHOWER CURTAINS, BUT INCLUDING CUBICLE CURTAINS), AND OTHER LOOSELY HANGING FABRICS AND FILMS
SERVING AS FURNISHINGS OR DECORATIONS IN HEALTH CARE OCCUPANCIES MUST MEET THE FLAME RESISTANCE REQUIREMENTS OF NFPA 701, STANDARD
METHODS OF FIRE TESTS FOR FLAME-RESISTANT TEXTILES AND FILMS.
• UPHOLSTERED FURNITURE AND MATTRESSES. UPHOLSTERED FURNITURE AND MATTRESSES MUST ALSO MEET SPECIFIED REQUIREMENTS, BASED ON NFPA
260, NFPA 261, NFPA 266, 16 CFR 1632, ASTME E1537, AND ASTME E1590
14. EXTINGUISHMENTS REQUIREMENTS, PORTABLE FIRE EXTINGUISHERS SHALL BE PROVIDED PER NFPA 10.
15. DETECTION, ALARM, AND COMMUNICATIONS SYSTEMS.
• FIRE ALARM SYSTEM SHALL BE PROVIDED LSC, NFPA 70 (NEC) AND NFPA 72. (LSC 9.6.1)
• FIRE ALARM MAY BE BY MANUAL MEANS (LSC 18.3.4.2.1)(LSC 9.6.2)
• OCCUPANT NOTIFICATION SHALL BE THROUGH AUTOMATIC MEANS PER 9.6.3. (LSC 18.3.4.3)
• SMOKE DETECTION SHALL BE PROVIDED PER NFPA 72.
• EMERGENCY RESPONDER NOTIFICATION SHALL BE NOTIFIED BY ALARM AND DETECTION SYSTEM PER 9.6.4. (LSC 18.3.4.3.2)
16. FIRE SUPPRESSION:
SPRINKLER SYSTEM: BUILDING IS REQUIRED TO BE SPRINKLED THROUGHOUT IN ACCORDANCE WITH NFPA 13.
THE SPRINKLER SYSTEM SHALL BE HYDRAULICALLY DESIGNED IN ACCORDANCE WITH 2013 EDITION OF NFPA 13 AND THE SIXTH EDITION OF THE DEPARTMENT OF
VETERANS AFFAIRS FIRE PROTECTION DESIGN MANUAL: MINIMUM DESIGN REQUIREMENTS:
STORAGE MECHANICAL AND ELECTRICAL ROOMS SHALL BE PROTECTED AS:
ORDINARY HAZARD OCCUPANCY, GROUP 1: 0.15 GPM/FT2 OVER 1,500 FT2.
HOSE STREAM ALLOWANCE: 250 GPM
ALL OTHER AREAS SHALL BE PROTECTED AS:
LIGHT HAZARD OCCUPANCY: 0.10 GPM/FT2 OVER 1,500 FT2.
HOSE STREAM ALLOWANCE: 100 GPM
CODE ANALYSIS - NFPA 101, INSTITUTIONAL HEALTHCARE CHAPTER 18
CODE ANALYSIS LEGEND
TOTAL OCCUPANCY
FEC
EXIT
OCCUPANCY LOAD FACTOR
EXITS REQUIRED
SQUARE FOOTAGE
OCCUPANCY TYPE
EGRESS EXIT SIGNAGE
FIRE EXTINGUISHER CABINET
DIAGONAL DISTANCE
EXIT SEPARATION DISTANCE
EGRESS PATH
2 HR - FIRE SEPARATION
1 HR - FIRE SEPARATION
SMOKE RESISTIVE HAZARDOUS AREA
B
1500 SF
VA DIRECTIVES, DESIGN MANUALS, MASTER SPECIFICATIONS, VA NATIONAL CAD
STANDARD APPLICATION GUIDE, AND OTHER GUIDANCE ON THE TECHNICAL
INFORMATION LIBRARY (TIL) (HTTP://WWW.CFM.VA.GOV/TIL/).
VA MENTAL HEALTH FACILITIES DESIGN GUIDE, DECEMBER 2010 (REV. 08/01/2014)
VA BARRIER FREE DESIGN GUIDE PG-18-13, ABAAS
ARCHITECTURAL, AUGUST 1, 2014
ASBESTOS ABATEMENT, JULY 2011
CMP SCHEDULE AND RISK MANAGEMENT, VOL. 1 & 2, DECEMBER 2012
ELECTRICAL, DECEMBER 2015
ENERGY SUSTAINABILITY, MAY 2014
EQUIPMENT, JANUARY 2006
ESTIMATING, MARCH 8, 2011
NFPA INTERIM GUIDANCE FOR PROJECTS, PG-18-17, SEPTEMBER 30, 2010
FIRE PROTECTION, SEVENTH EDITION REVISED DECEMBER 2015
HVAC FOR NEW, REPLACEMENT, ADD. AND REN. OF EXIST. CA FACILITIES, MARCH 2011
INTERIOR DESIGN, MAY 2008
PHYSICAL SECURITY DESIGN MANUAL, JANUARY 2015
PLUMBING, NOVEMBER 2014
STRUCTURAL, FEBRUARY 1, 2014
WAY FINDING AND SIGNAGE, INTERIOR, DECEMBER 2012
SEISMIC DESIGN REQUIREMENTS, H-18-8, AUGUST 2013
ENVIRONMENTAL PLANNING GUIDANCE PG-18-17 NEPA INTERIM GUIDELINES FOR
PROJECTS SEPTEMBER 30, 2010
ELEVATOR DESIGN MANUAL, AUGUST 2016
EPA GUIDELINES CHECKLIST
VA DESIGN MANUALS PG-18-10:
GOVERNING CODES:
REFER TO VA MANUAL PG-18-3 FOR ADDITIONAL CODES, STANDARDS, GUIDELINES AND
REGULATIONS, BELOW LISTING IS NOT COMPREHENSIVE.
ICC, INTERNATIONAL BUILDING CODES, 2018 EDITION (IBC)
ASCE-07-10
ACI 318-11
ACI 530-11
AISC 341-10
AISC 360-10
PCI MNL 120-10, DESIGN HANDBOOK
NFPA 10, STANDARD FOR PORTABLE FIRE EXTINGUISHERS, 2018 EDITION
NFPA 13, STANDARD FOR THE INSTALLATION OF SPRINKLER SYSTEMS, 2019 EDITION
NFPA 14, STANDARD FOR THE INSTALLATION OF STANDPIPE AND HOSE SYSTEM, 2019
EDITION
NFPA 20, STANDARD FOR THE INSTALLATION OF STATIONARY PUMPS FOR FIRE
PROTECTION, 2019 EDITION
NFPA 24, STANDARD FOR THE INSTALLATION OF PRIVATE FIRE SERVICE MAINS AND
THEIR APPURTENANCE, 2019 EDITION.
NFPA 54 NATOINAL FUEL GAS CODE, 2018 EDITION
NFPA 70, NATIONAL ELECTRIC CODE, 2017 EDITION
NFPA 72, NATIONAL FIRE ALARM CODE, 2019 EDITION
NFPA 75, STANDARD FOR THE PROTECTION OF ELECTRICAL COMPUTER/DATA
PROCESSING EQUIPMENT, 2017 EDITION
NFPA 77, RECOMMENDED PRACTICE ON STATIC ELECTRICITY, 2019 EDITION
NFPA 80, STANDARD FOR FIRE DOORS AND FIRE WINDOWS, 2019 EDITION
NFPA 90A, STANDARD FOR THE INSTALLATION OF AIR-CONDITIONING AND VENTILATING
SYSTEMS, 2018 EDITION.
NFPA 92, STANDARD FOR SMOKE CONTROL SYSTEMS, 2018 EDITION
NFPA 99, STANDARD FOR HEALTHCARE FACILITIES, 2018 EDITION
NFPA,99B, STANDARD FOR HYPOBARIC FACILITIES, 2018 EDITION
NFPA 101, LIFE SAFETY CODE, 2018 EDITION
NFPA 110, STANDARD FOR EMERGENCY AND STANDBY POWER SYSTEMS
NFPA 220, STANDARD TYPES OF BUILDING CONSTRUCTION, 2018 EDITION.
NFPA 780, STANDARD FOR INSTALLATION OF LIGHTING PROTECTION SYSTEMS, 2017
EDITION
NFPA 54 TYPE 2 CLOTHES DRYER UL 705 DEDPY, 2015 EDITION
MOST RECENT EDITION OF NFPA NATIONAL FIRE CODES WITH THE EXCEPTION OF NFPA
5000 AND NFPA 900
ANSI A117.1-2017 STANDARD ON ACCESSIBLE & USABLE BUILDINGS AND FACILITIES
2010 ADA STANDARDS FOR ACCESSIBLE DESIGN
OCCUPATIONAL, SAFETY AND HEALTH ADMINISTRATION (OSHA) STANDARDS
ENERGY POLICY ACT OF 2005 (EPACT)
EXECUTIVE ORDER 13423: STRENGTHENING FEDERAL ENVIRONMENTAL, ENERGY, AND
TRANSPORTATION MANAGEMENT.
SUITE
EXIT
ACCESS
SUITE
EXIT
ACCESS
SUITE
EXIT
ACCESS
A
B
C
D
E
F
F.3
16 15 14 13 12
E G
R E
S S
D
IS
T A
N C
E T
O S
U
IT
E E
X
IT
6"
E X
IS
T
IN
G
E G
R E
S S
D
IS
T A
N C
E T
O S
U
IT
E E
X
IT
8'
0"
G
G.6
11 10 9
EXIT
EXIT
9535 SF
10096
B
FEC
FEC
FEC
E G
R E
S S
D
IS
T A
N C
E T
O E
X
IT
: 7 8'
T O
T A
L E
G R
E S
S D
IS
T
A N
C E
T O
E X
IT
9'
4"
SUITE
EXIT
ACCESS
EGRESS DISTANCE
TO SUITE EXIT: 95' - 6"
PROVIDED EXIT WIDTHS = 148"
REQURIED EXIT WIDTHS = 19.2"
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
Consultant:
GUIDON DESIGN INC.
1221 N. PENNSYLVANIA ST. | INDIANAPOLIS, IN. 46202
317.800.6388 | WWW.GUIDONDESIGN.COM
SUSTAINABLE ARCHITECTURE + ENGINEERING
PROJECT LEAD
Architect, Structural Engineer, Civil Engineer
C U s e rs
\d v a lla n d in g h a m \D o c u m e n ts
\1 .1
.0
V A
I n d ia n a p o lis
L a b
R e n o v a ti o n d v a lla n d in g h a m g u id o n d e s ig n .c o m
.r v t
/1
/2
:3
:5
P
M
GI101
LIFE SAFETY PLAN
HEAPY ENGINEERING
3850 PRIORITY WAY SOUTH SUITE 204
INDIANAPOLIS, IN 46240
317.571.8795
WWW.HEAPY.COM
RENOVATE LAB - HISTOLOGY,
CYTOLOGY, AND MOLECULAR
1481 W 10TH ST, INDIANAPOLIS, IN
583-18-102
06/24/2020 JC DV
BID DOCUMENTS
FULLY SPRINKLERED
SCALE: 3/32" = 1'-0"GI101
1 PARTIAL SECOND FLOOR LIFE SAFETY PLAN
N
SCALE: 1" = 100'-0"
KEY PLAN
N
A
B
C
D
E
F
16 15 14 13 12
DEVELOP.
(F.I.S.H.)
A-2063
EM SCOPE
A-2065
RESIDENTS
A-2099
LAB
INFORMATION
MANAGER
A-2078
PROCEDURE
ROOM
A-2077
MOLECULAR
PATHOLOGY
LABORATORY
A-2043
WALK-IN
LABORATORY
A-2053
STORAGE
A-2054A
TELE. ROOM
A-2056
ELEC. ROOM
A-2057
TANK
A-2055
FINISH
A-2060
FILES
A-2061
H.A.C.
A-2103
LIFT
C-2 REFRIGERATOR
A-2101
TEACHING
MICROSCOPY
A-2100
STAFF
PATHOLOGIST
A2038
STAFF
PATHOLOGIST
A-2039
STAFF
PATHOLOGIST
A-2040
A-2045
SUPERVISOR
A-2046
MYCOBACT.
A-2047
BIOSAFETY
A-2049
PROSTATE
CANCER
RESEARCH
A-2133
A-2132A
SUPERVISOR
A-2058
CONTAIN.
A-2048
CYTOLOGY
A-2067
HISTOLOGY
A-2042
CYTOLOGY
A-2041
CORRIDOR
C2-6
CORRIDOR
C2-5
A-2059
MICROBIOLOGY
A-2044
CORRIDOR
C2-2
CORRIDOR
C2-3
CORRIDOR
A2-8
SPEC. CHEM
A-2132
ATRIUMATRIUM
FLUOR. MS.
A-2054
INAC. SLD. BLK.
A-2066
LIFT
C-1
CORRIDOR
C2-4
CORRIDOR
C2-9
M51A
M51B
M51C
A48
A38
A39
M21
M20
M37
A34
A35
A36A37
M35B
M35A
A40
A20C
A20B
A20D
A19B
A19D
A19C
A19A20M46
M29
M42
M45
M43
M17
M25 M44
M26
M19 M39
M30
A27A
M22
M12
A27BA27C
A28
A40
A7A A24A
A7CA7B
A9A
A9B
A8A12A
A10A
A11AA12BA10B
A11BA11C
A12C A10C
A10D
A12D
A11D
A17BA17AA16
A26A
A60
A61
M53M52
A3
M15 M6M16
M7 M5
M13
M17
M8
M9
M10
M17
M12
MIN.
5' - 0"
CONTRACTOR
1M
IN
5'
". 22
STERILE
SOLUTION
A-2051
STERILIZER
A-2050GIP STORAGE
A-2054A
PHASING NARRATIVE: PHASE 1A
PHASE 1:
DURING THIS PHASE THE STERILE SOLUTIONS ROOM WILL
BE CONSTRUCTED. GIP STORAGE IS MOVED FROM ITS
EXISTING LOCATION TO THE NEW GIP STORAGE ROOM
WHICH IS ALSO CONSTRUCTED IN THIS PHASE.
CONTINUOUS FIRESAFE SEALANT
TOP AND BOTTOM, & BOTH SIDES
3 1/2" SOUND ATTENUATION
BATT.
5/8" TYPE X GYPSUM BOARD, BOTH
SIDES
3 5/8" METAL STUD @ 16" O.C.
WITH RUNNER CHANNELS ALONG
TOP AND BOTTOM
CONSTRUCTION
SIDE
PUBLIC
SIDE
6 MIL. FIRE RETARDANT VISQUEEN
MEMBRANE. CONTINUOUSLY
ADHERE TO THE STRUCTURAL DECK
ABOVE AND TO THE FLOOR BELOW
WITH TAPE.
UNDERSIDE OF STRUCTURAL DECK
UL LISTING:
U465
COORDINATE WITH EXISTING
CEILING
PUBLIC
SIDE
1 HOUR FIRE RATED METAL DOOR ASSEMBLY
AND FRAME WITH SEALS, BLUE CORE (SEE
COR), HARDWARE AND CLOSER
TRIATEK MONITOR
HAND SANITIZER
SEAL ALL EDGES WITH TAPE
SEAL ALL EDGES WITH TAPE
REFER TO TEMPORARY BARRIER TYPE
FOR REQUIRED CONDITION TO
STRUCTURE ABOVE
VA / OSHA TEMPORARY SIGNAGE
IC/PHASING LEGEND
TEMPORARY WALLS. SEE PLAN AND
PLAN NOTES
TEMPORARY CONSTRUCTION ACCESS
DOORS
REFERENCE AREA FOR ABOVE
CEILING WORK ON FLOOR BELOW.
REFER TO ENGINEERING DRAWINGS
FOR FULL SCOPE OF WORK
BEYOND PROJECT BOUNDARY
PROJECT BOUNDARY
INFECTION CONTROL PLAN NOTES #
INFECTION CONTROL PROJECT INFORMATION
CONSTRUCTION ACTIVITY - FIRE RISK: TYPE C
PATIENT RISK GROUP: HIGH
CLASS OF PRECAUTION MATRIX: III
PROVIDE TEMPORARY 1 HR FIRE RATED SMOKE BARRIER WALL
CONSTRUCTION PER NFPA 241. REFER TO DETAIL 2/GI102.
PROVIDE TEMPORARY INFECTION CONTROL CONSTRUCTION DOOR WITH BLUE
CORE. REFER TO ELEVATION 4/GI102.
NOT USED
PROVIDE TEMPORARY INFECTION CONTROL PLASTIC BARRIER WALL
CONSTRUCTION. REFER TO SPECIFICATION FOR ADDITIONAL INFORMATION.
REFER TO LIST OF REQUIRED INFECTION CONTROL PRECAUTIONS OUTLINED
BY CLASS IN SPECIFICATION 010110 AND ADDITIONAL INFORMATION.
REFER TO DRAWINGS, SPECIFICATIONS AND DOOR HARDWARE SCHEDULE
FOR ADDITIONAL INFORMATION.
PROJECT SHALL BE COMPLETED IN 12 PHASES.
COORDINATE FULL SCOPE OF WORK WITH ENGINEERING DRAWINGS AND
FIELD VERIFICATION. CONTRACTOR IS RESPONSIBLE FOR SCOPE OF ABOVE
CEILING WORK REQUIRED ABOVE AND BELOW THE FLOOR PLATE OF THE
PROJECT BOUNDARY.
COORDINATE LOCATION OF TEMPORARY INFECTION CONTROL (IC) BARRIER
WALL CONSTRUCTION AND INFECTION CONTROL (IC) MEASURES WITH COR
AND PATIENT SAFETY/ INFECTION CONTROL REPRESENTATIVE. TEMPORARY
IC BARRIER WALL CONSTRUCTION LOCATIONS IN DRAWINGS ARE
APPROXIMATE. CONTRACTOR SHALL PROVIDE DRAWING TO COR AND
PATIENT SAFETY/ INFECTION CONTROL REPRESENTATIVE ONCE ICRA
PROTOCOLS AND PLAN IS APPROVED.
CONTRACTOR TO VERIFY 1-HOUR WALL CONTINUOUSLY WRAPS SUITE AS
ANNOTATED IN DRAWINGS. CONTRACTOR TO CORRECT EXISTING WALLS
THAT ARE NOT 1-HR RATED TO SURROUND SUITE IN REQUIRED SEPARATION.
SCHEDULE AND TIME OF CONSTRUCTION WORK TO BE APPROVED BY COR
AND NURSING STAFF BEFORE CONSTRUCTION MAY BEGIN. PROVIDE PHASING
INFORMATION FOR ABOVE CEILING WORK IN THE CONTRACTOR PROVIDED
CMP SCHEDULE FOR WORK ALSO REQUIRED ABOVE AND BELOW THE FLOOR
PLATE OF THE PROJECT BOUNDARY.
ABOVE CEILING WORK SHALL TAKE PLACE BETWEEN THE HOURS OF 5:00 PM
AND 5:00 AM. IN AREAS THAT REQUIRE ABOVE CEILING WORK WHERE
CEILINGS ARE TO REMAIN, CEILING TILES SHALL BE REMOVED AND STORED IN
A SAFE MANOR UNTIL CEILING TILES CAN BE REINSTALLED. DAMAGED AND
BROKEN CEILING TILES SHALL BE REPLACED BY CONTRACTOR.
EXIT/ACCESS FOR ADJACENT OPERATIONAL AREAS SHALL BE MAINTAINED
DURING NORMAL BUSINESS HOURS. SEE SPECIFICATION FOR HOURS OF
OPERATION.
WORK REQUIRING VIBRATION OR LOAD NOISE SHALL TAKE PLACE BETWEEN
THE HOURS OF 5:00 PM AND 5:00 AM. EVERY EFFORT SHALL BE MADE TO
KEEP NOISE AND VIBRATION TO A MINIMUM.
PROVIDE THE FOLLOWING INFECTION CONTROL MEASURES, A 24"X36" STICKY
WALK OFF MAT AND HAND SANITIZER AT EACH TEMPORARY DOOR LOCATION.
MAT SHALL BE REPLACED OR CLEANED AS NECESSARY
PROVIDE THE VA AND OSHA REQUIRED TEMPORARY SIGNAGE AT EACH
TEMPORARY DOOR LOCATION.
CONTRACTOR SHALL SUPPLY SPILL KIT. SPILL KIT TO INCLUDE SHOP VAC,
MULTI-PURPOSE SPILL CONTROL SORBENTS TO ABSORB NON AGGRESSIVE
LIQUIDS UP TO 30 GALLONS.
ALL NEW MATERIAL MOVED THROUGH THE FACILITY SHALL BE COVERED WITH
4 MIL. POLY SHEET.
ALL DEMOLITION MATERIAL SHALL BE REMOVED FROM THE PROJECT
BOUNDARY THROUGH THE FACILITY TO DUMPSTER ALONG VA APPROVED
ROUTE IN ENCLOSED DUMPSTER CART DESIGNED FOR SUCH PURPOSED
WITH A LID.
ALL MATERIAL, DEBRIS AND HAZARDOUS MATERIALS SHALL BE PROPERLY
STORED IN DESIGNATED AREAS AND APPROVED CONTAINERS. FLAMMABLE
MATERIALS SHALL NOT BE STORED IN THE FACILITY.
PROVIDE CONTAINMENT CART FOR ABOVE CEILING ACCESS OUTSIDE
PROJECT BOUNDARY.
TEMPORARY PLASTIC CONSTRUCTION BARRIERS WILL BE REQUIRED TO
PROTECT THE LAB SPACE FROM THE CONSTRUCTION DEBRIS CREATED
WHEN CONSTRUCTING TEMPORARY PARTITIONS.
A
B
C
D
E
F
G
H
I
J
K
L
M
N
O
P
Q
R
INFECTION CONTROL GENERAL NOTES
PHASING GENERAL NOTES #
A
B
C
PROJECT AREAS TO BE OCCUPIED BY STAFF AND VETERANS THROUGHOUT
CONSTRUCTION.
CONSTRUCTION WORK BEHIND TEMPORARY CONSTRUCTION PARTITIONS
SHALL BE COMPLETED DURING NIGHT SHIFTS, 5:00 PM TO 5:00 AM.
REFER TO SPECIFICATION 01 00 00 FOR INFORMATION ON WORK DURATION
FOR EACH PHASE AND AREA OF WORK.
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
Consultant:
GUIDON DESIGN INC.
1221 N. PENNSYLVANIA ST. | INDIANAPOLIS, IN. 46202
317.800.6388 | WWW.GUIDONDESIGN.COM
SUSTAINABLE ARCHITECTURE + ENGINEERING
PROJECT LEAD
Architect, Structural Engineer, Civil Engineer
C U s e rs
\d v a lla n d in g h a m \D o c u m e n ts
\1 .1
.0
V A
I n d ia n a p o lis
L a b
R e n o v a ti o n d v a lla n d in g h a m g u id o n d e s ig n .c o m
.r v t
/1
/2
:3
:5
P
M
GI102
PHASING PLAN - PHASE 1
HEAPY ENGINEERING
3850 PRIORITY WAY SOUTH SUITE 204
INDIANAPOLIS, IN 46240
317.571.8795
WWW.HEAPY.COM
RENOVATE LAB - HISTOLOGY,
CYTOLOGY, AND MOLECULAR
1481 W 10TH ST, INDIANAPOLIS, IN
583-18-102
06/24/2020
BID DOCUMENTS
FULLY SPRINKLERED
SCALE: 3/16" = 1'-0"GI102
1 SECOND FLOOR PHASING PLAN - PHASE 1A
SCALE: 1 1/2" = 1'-0"GI102
2 TEMP 1 HR FIRE RATED SMOKE BARRIER WALL CONSTRUCTION NFPA 241
SCALE: 1/4" = 1'-0"GI102
4 TEMPORARY WALL CONSTRUCTION ELEVATION
N
SCALE: 1" = 100'-0"
KEY PLAN
C
D
E
F
16 15 14 13 12
DEVELOP.
(F.I.S.H.)
A-2063
EM SCOPE
A-2065
RESIDENTS
A-2099
LAB
INFORMATION
MANAGER
A-2078
PROCEDURE
ROOM
A-2077
MOLECULAR
PATHOLOGY
LABORATORY
A-2043
FINISH
A-2060
FILES
A-2061
H.A.C.
A-2103
LIFT
C-2 REFRIGERATOR
A-2101
TEACHING
MICROSCOPY
A-2100
STAFF
PATHOLOGIST
A2038
STAFF
PATHOLOGIST
A-2039
STAFF
PATHOLOGIST
A-2040
A-2045
SUPERVISOR
A-2046
MYCOBACT.
A-2047
BIOSAFETY
A-2049
PROSTATE
CANCER
RESEARCH
A-2133
A-2132A
SUPERVISOR
A-2058
CONTAIN.
A-2048
CYTOLOGY
A-2067
HISTOLOGY
A-2042
CYTOLOGY
A-2041
CORRIDOR
C2-6
CORRIDOR
C2-5
A-2059
MICROBIOLOGY
A-2044
CORRIDOR
C2-2
CORRIDOR
C2-3
CORRIDOR
A2-8
SPEC. CHEM
A-2132
ATRIUMATRIUM
INAC. SLD. BLK.
A-2066
CORRIDOR
C2-4
CORRIDOR
C2-9
A48
A38
A39 A34
A35
A36A37
M35B
M35A
A40
A20C
A20B
A20D
A19B
A19D
A19C
A19A20
A27AA27BA27C
A28
A40
A7A A24A
A7CA7B
A9A
A9B
A8A12A
A10A
A11AA12BA10B
A11BA11C
A12C A10C
A10D
A12D
A11D
A17BA17AA16
A26A
A60
A61
A3
M15 M6M16
M7 M5
M13
M17
M8
M9
M10
M17
M12
TANK
A-2055
TELE. ROOM
A-2056
ELEC. ROOM
A-2057
STERILE
SOLUTION
A-2051
STERILIZER
A-2050GIP STORAGE
A-2054A
FLUOR. MS.
A-2054
M21
M45
M42
M26 M19
M44
M39
M51B
M51A
M51C
M29
M37
M53
M52
WALK-IN
REFRIGERATOR
M20 shelves for supplies centrifuges, heat blocks, nanodrops clerical desk free work space
CONTRACTOR
ACCESS
PHASING NARRATIVE: PHASE 2
PHASE 2:
DURING THIS PHASE THE EXISTING WALK-IN
REFRIGERATOR AND STORAGE ROOMS ARE DEMOLISHED.
THE NEW WALK-IN REFRIGERATOR IS INSTALLED. THE
REMAINING SPACE IS REMODELED AND USED AS A SWING
SPACE FOR TEMPORARILY LOCATED EQUIPMENT. THE
EQUIPMENT LOCATED HERE IS TO BE INSTALLED AS IF IT
WERE TO BE PERMANENTLY LOCATED AS SOME ITEMS
WILL REMAIN HERE FOR THE ENTIRETY OF THE
CONSTRUCTION SCHEDULE.
IC/PHASING LEGEND
TEMPORARY WALLS. SEE PLAN AND
PLAN NOTES
TEMPORARY CONSTRUCTION ACCESS
DOORS
REFERENCE AREA FOR ABOVE
CEILING WORK ON FLOOR BELOW.
REFER TO ENGINEERING DRAWINGS
FOR FULL SCOPE OF WORK
BEYOND PROJECT BOUNDARY
PROJECT BOUNDARY
INFECTION CONTROL PLAN NOTES #
INFECTION CONTROL PROJECT INFORMATION
CONSTRUCTION ACTIVITY - FIRE RISK: TYPE C
PATIENT RISK GROUP: HIGH
CLASS OF PRECAUTION MATRIX: III
PROVIDE TEMPORARY 1 HR FIRE RATED SMOKE BARRIER WALL
CONSTRUCTION PER NFPA 241. REFER TO DETAIL 2/GI102.
PROVIDE TEMPORARY INFECTION CONTROL CONSTRUCTION DOOR WITH BLUE
CORE. REFER TO ELEVATION 4/GI102.
NOT USED
PROVIDE TEMPORARY INFECTION CONTROL PLASTIC BARRIER WALL
CONSTRUCTION. REFER TO SPECIFICATION FOR ADDITIONAL INFORMATION.
REFER TO LIST OF REQUIRED INFECTION CONTROL PRECAUTIONS OUTLINED
BY CLASS IN SPECIFICATION 010110 AND ADDITIONAL INFORMATION.
REFER TO DRAWINGS, SPECIFICATIONS AND DOOR HARDWARE SCHEDULE
FOR ADDITIONAL INFORMATION.
PROJECT SHALL BE COMPLETED IN 12 PHASES.
COORDINATE FULL SCOPE OF WORK WITH ENGINEERING DRAWINGS AND
FIELD VERIFICATION. CONTRACTOR IS RESPONSIBLE FOR SCOPE OF ABOVE
CEILING WORK REQUIRED ABOVE AND BELOW THE FLOOR PLATE OF THE
PROJECT BOUNDARY.
COORDINATE LOCATION OF TEMPORARY INFECTION CONTROL (IC) BARRIER
WALL CONSTRUCTION AND INFECTION CONTROL (IC) MEASURES WITH COR
AND PATIENT SAFETY/ INFECTION CONTROL REPRESENTATIVE. TEMPORARY
IC BARRIER WALL CONSTRUCTION LOCATIONS IN DRAWINGS ARE
APPROXIMATE. CONTRACTOR SHALL PROVIDE DRAWING TO COR AND
PATIENT SAFETY/ INFECTION CONTROL REPRESENTATIVE ONCE ICRA
PROTOCOLS AND PLAN IS APPROVED.
CONTRACTOR TO VERIFY 1-HOUR WALL CONTINUOUSLY WRAPS SUITE AS
ANNOTATED IN DRAWINGS. CONTRACTOR TO CORRECT EXISTING WALLS
THAT ARE NOT 1-HR RATED TO SURROUND SUITE IN REQUIRED SEPARATION.
SCHEDULE AND TIME OF CONSTRUCTION WORK TO BE APPROVED BY COR
AND NURSING STAFF BEFORE CONSTRUCTION MAY BEGIN. PROVIDE PHASING
INFORMATION FOR ABOVE CEILING WORK IN THE CONTRACTOR PROVIDED
CMP SCHEDULE FOR WORK ALSO REQUIRED ABOVE AND BELOW THE FLOOR
PLATE OF THE PROJECT BOUNDARY.
ABOVE CEILING WORK SHALL TAKE PLACE BETWEEN THE HOURS OF 5:00 PM
AND 5:00 AM. IN AREAS THAT REQUIRE ABOVE CEILING WORK WHERE
CEILINGS ARE TO REMAIN, CEILING TILES SHALL BE REMOVED AND STORED IN
A SAFE MANOR UNTIL CEILING TILES CAN BE REINSTALLED. DAMAGED AND
BROKEN CEILING TILES SHALL BE REPLACED BY CONTRACTOR.
EXIT/ACCESS FOR ADJACENT OPERATIONAL AREAS SHALL BE MAINTAINED
DURING NORMAL BUSINESS HOURS. SEE SPECIFICATION FOR HOURS OF
OPERATION.
WORK REQUIRING VIBRATION OR LOAD NOISE SHALL TAKE PLACE BETWEEN
THE HOURS OF 5:00 PM AND 5:00 AM. EVERY EFFORT SHALL BE MADE TO
KEEP NOISE AND VIBRATION TO A MINIMUM.
PROVIDE THE FOLLOWING INFECTION CONTROL MEASURES, A 24"X36" STICKY
WALK OFF MAT AND HAND SANITIZER AT EACH TEMPORARY DOOR LOCATION.
MAT SHALL BE REPLACED OR CLEANED AS NECESSARY
PROVIDE THE VA AND OSHA REQUIRED TEMPORARY SIGNAGE AT EACH
TEMPORARY DOOR LOCATION.
CONTRACTOR SHALL SUPPLY SPILL KIT. SPILL KIT TO INCLUDE SHOP VAC,
MULTI-PURPOSE SPILL CONTROL SORBENTS TO ABSORB NON AGGRESSIVE
LIQUIDS UP TO 30 GALLONS.
ALL NEW MATERIAL MOVED THROUGH THE FACILITY SHALL BE COVERED WITH
4 MIL. POLY SHEET.
ALL DEMOLITION MATERIAL SHALL BE REMOVED FROM THE PROJECT
BOUNDARY THROUGH THE FACILITY TO DUMPSTER ALONG VA APPROVED
ROUTE IN ENCLOSED DUMPSTER CART DESIGNED FOR SUCH PURPOSED
WITH A LID.
ALL MATERIAL, DEBRIS AND HAZARDOUS MATERIALS SHALL BE PROPERLY
STORED IN DESIGNATED AREAS AND APPROVED CONTAINERS. FLAMMABLE
MATERIALS SHALL NOT BE STORED IN THE FACILITY.
PROVIDE CONTAINMENT CART FOR ABOVE CEILING ACCESS OUTSIDE
PROJECT BOUNDARY.
TEMPORARY PLASTIC CONSTRUCTION BARRIERS WILL BE REQUIRED TO
PROTECT THE LAB SPACE FROM THE CONSTRUCTION DEBRIS CREATED
WHEN CONSTRUCTING TEMPORARY PARTITIONS.
A
B
C
D
E
F
G
H
I
J
K
L
M
N
O
P
Q
R
INFECTION CONTROL GENERAL NOTES
PHASING GENERAL NOTES #
A
B
C
PROJECT AREAS TO BE OCCUPIED BY STAFF AND VETERANS THROUGHOUT
CONSTRUCTION.
CONSTRUCTION WORK BEHIND TEMPORARY CONSTRUCTION PARTITIONS
SHALL BE COMPLETED DURING NIGHT SHIFTS, 5:00 PM TO 5:00 AM.
REFER TO SPECIFICATION 01 00 00 FOR INFORMATION ON WORK DURATION
FOR EACH PHASE AND AREA OF WORK.
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
Consultant:
GUIDON DESIGN INC.
1221 N. PENNSYLVANIA ST. | INDIANAPOLIS, IN. 46202
317.800.6388 | WWW.GUIDONDESIGN.COM
SUSTAINABLE ARCHITECTURE + ENGINEERING
PROJECT LEAD
Architect, Structural Engineer, Civil Engineer
C U s e rs
\d v a lla n d in g h a m \D o c u m e n ts
\1 .1
.0
V A
I n d ia n a p o lis
L a b
R e n o v a ti o n d v a lla n d in g h a m g u id o n d e s ig n .c o m
.r v t
/1
/2
:3
:5
P
M
GI103
PHASING PLAN - PHASE 2
HEAPY ENGINEERING
3850 PRIORITY WAY SOUTH SUITE 204
INDIANAPOLIS, IN 46240
317.571.8795
WWW.HEAPY.COM
RENOVATE LAB - HISTOLOGY,
CYTOLOGY, AND MOLECULAR
1481 W 10TH ST, INDIANAPOLIS, IN
583-18-102
06/24/2020
BID DOCUMENTS
FULLY SPRINKLERED
SCALE: 3/16" = 1'-0"GI103
1 SECOND FLOOR PHASING PLAN - PHASE 2
N
SCALE: 1" = 100'-0"
KEY PLAN
C
D
E
F
16 15 14 13 12
DEVELOP.
(F.I.S.H.)
A-2063
EM SCOPE
A-2065
RESIDENTS
A-2099
LAB
INFORMATION
MANAGER
A-2078
PROCEDURE
ROOM
A-2077
MOLECULAR
PATHOLOGY
LABORATORY
A-2043
H.A.C.
A-2103
LIFT
C-2 REFRIGERATOR
A-2101
TEACHING
MICROSCOPY
A-2100
STAFF
PATHOLOGIST
A2038
STAFF
PATHOLOGIST
A-2039
STAFF
PATHOLOGIST
A-2040
A-2045
SUPERVISOR
A-2046
MYCOBACT.
A-2047
BIOSAFETY
A-2049
PROSTATE
CANCER
RESEARCH
A-2133
A-2132A
SUPERVISOR
A-2058
CONTAIN.
A-2048
CYTOLOGY
A-2067
HISTOLOGY
A-2042
CYTOLOGY
A-2041
CORRIDOR
C2-5
MICROBIOLOGY
A-2044
CORRIDOR
C2-2
CORRIDOR
C2-3
CORRIDOR
A2-8
SPEC. CHEM
A-2132
ATRIUMATRIUM
INAC. SLD. BLK.
A-2066
CORRIDOR
C2-4
CORRIDOR
C2-9
A48
A38
A39 A34
A35
A36A37
A40
A20C
A20B
A20D
A19B
A19D
A19C
A19A20
A27AA27BA27C
A28
A40
A24A
A26A
A60
A61
M15 M6M16
M7 M5
M13
M17
M8
M9
M10
M17
M12
MIN.
4' - 0".
M
IN
5'
TANK
A-2055
TELE. ROOM
A-2056
ELEC. ROOM
A-2057
STERILE
SOLUTION
A-2051
STERILIZER
A-2050GIP STORAGE
A-2054A
TISSUE
A-7
CUTTING AREA
A-2
EMBEDDING
A-3
GROSSING
A-4
A10A
A1F
A12A
A11A
A11B
A10CA12C
A11C
A13
A9B
A9A
A7A
A7B
A7C
A1B A1A
A1C
A1D
A24B
A16
A56
A3
A59B
A59A
A62 A50
A63
A8
A15
FLUOR. MS.
A-2054
A17A
A17B
MIN.
5' - 0"
A12B
A10B
S2
A65
M21
M45
M42
M26
M19
M44
M39
M51B
M51A
M51C
M29
M37
M53M52
WALK-IN
REFRIGERATOR
M20
CONTRACTOR
ACCESS
IC/PHASING LEGEND
TEMPORARY WALLS. SEE PLAN AND
PLAN NOTES
TEMPORARY CONSTRUCTION ACCESS
DOORS
REFERENCE AREA FOR ABOVE
CEILING WORK ON FLOOR BELOW.
REFER TO ENGINEERING DRAWINGS
FOR FULL SCOPE OF WORK
BEYOND PROJECT BOUNDARY
PROJECT BOUNDARY
INFECTION CONTROL PLAN NOTES #
INFECTION CONTROL PROJECT INFORMATION
CONSTRUCTION ACTIVITY - FIRE RISK: TYPE C
PATIENT RISK GROUP: HIGH
CLASS OF PRECAUTION MATRIX: III
PROVIDE TEMPORARY 1 HR FIRE RATED SMOKE BARRIER WALL
CONSTRUCTION PER NFPA 241. REFER TO DETAIL 2/GI102.
PROVIDE TEMPORARY INFECTION CONTROL CONSTRUCTION DOOR WITH BLUE
CORE. REFER TO ELEVATION 4/GI102.
NOT USED
PROVIDE TEMPORARY INFECTION CONTROL PLASTIC BARRIER WALL
CONSTRUCTION. REFER TO SPECIFICATION FOR ADDITIONAL INFORMATION.
REFER TO LIST OF REQUIRED INFECTION CONTROL PRECAUTIONS OUTLINED
BY CLASS IN SPECIFICATION 010110 AND ADDITIONAL INFORMATION.
REFER TO DRAWINGS, SPECIFICATIONS AND DOOR HARDWARE SCHEDULE
FOR ADDITIONAL INFORMATION.
PROJECT SHALL BE COMPLETED IN 12 PHASES.
COORDINATE FULL SCOPE OF WORK WITH ENGINEERING DRAWINGS AND
FIELD VERIFICATION. CONTRACTOR IS RESPONSIBLE FOR SCOPE OF ABOVE
CEILING WORK REQUIRED ABOVE AND BELOW THE FLOOR PLATE OF THE
PROJECT BOUNDARY.
COORDINATE LOCATION OF TEMPORARY INFECTION CONTROL (IC) BARRIER
WALL CONSTRUCTION AND INFECTION CONTROL (IC) MEASURES WITH COR
AND PATIENT SAFETY/ INFECTION CONTROL REPRESENTATIVE. TEMPORARY
IC BARRIER WALL CONSTRUCTION LOCATIONS IN DRAWINGS ARE
APPROXIMATE. CONTRACTOR SHALL PROVIDE DRAWING TO COR AND
PATIENT SAFETY/ INFECTION CONTROL REPRESENTATIVE ONCE ICRA
PROTOCOLS AND PLAN IS APPROVED.
CONTRACTOR TO VERIFY 1-HOUR WALL CONTINUOUSLY WRAPS SUITE AS
ANNOTATED IN DRAWINGS. CONTRACTOR TO CORRECT EXISTING WALLS
THAT ARE NOT 1-HR RATED TO SURROUND SUITE IN REQUIRED SEPARATION.
SCHEDULE AND TIME OF CONSTRUCTION WORK TO BE APPROVED BY COR
AND NURSING STAFF BEFORE CONSTRUCTION MAY BEGIN. PROVIDE PHASING
INFORMATION FOR ABOVE CEILING WORK IN THE CONTRACTOR PROVIDED
CMP SCHEDULE FOR WORK ALSO REQUIRED ABOVE AND BELOW THE FLOOR
PLATE OF THE PROJECT BOUNDARY.
ABOVE CEILING WORK SHALL TAKE PLACE BETWEEN THE HOURS OF 5:00 PM
AND 5:00 AM. IN AREAS THAT REQUIRE ABOVE CEILING WORK WHERE
CEILINGS ARE TO REMAIN, CEILING TILES SHALL BE REMOVED AND STORED IN
A SAFE MANOR UNTIL CEILING TILES CAN BE REINSTALLED. DAMAGED AND
BROKEN CEILING TILES SHALL BE REPLACED BY CONTRACTOR.
EXIT/ACCESS FOR ADJACENT OPERATIONAL AREAS SHALL BE MAINTAINED
DURING NORMAL BUSINESS HOURS. SEE SPECIFICATION FOR HOURS OF
OPERATION.
WORK REQUIRING VIBRATION OR LOAD NOISE SHALL TAKE PLACE BETWEEN
THE HOURS OF 5:00 PM AND 5:00 AM. EVERY EFFORT SHALL BE MADE TO
KEEP NOISE AND VIBRATION TO A MINIMUM.
PROVIDE THE FOLLOWING INFECTION CONTROL MEASURES, A 24"X36" STICKY
WALK OFF MAT AND HAND SANITIZER AT EACH TEMPORARY DOOR LOCATION.
MAT SHALL BE REPLACED OR CLEANED AS NECESSARY
PROVIDE THE VA AND OSHA REQUIRED TEMPORARY SIGNAGE AT EACH
TEMPORARY DOOR LOCATION.
CONTRACTOR SHALL SUPPLY SPILL KIT. SPILL KIT TO INCLUDE SHOP VAC,
MULTI-PURPOSE SPILL CONTROL SORBENTS TO ABSORB NON AGGRESSIVE
LIQUIDS UP TO 30 GALLONS.
ALL NEW MATERIAL MOVED THROUGH THE FACILITY SHALL BE COVERED WITH
4 MIL. POLY SHEET.
ALL DEMOLITION MATERIAL SHALL BE REMOVED FROM THE PROJECT
BOUNDARY THROUGH THE FACILITY TO DUMPSTER ALONG VA APPROVED
ROUTE IN ENCLOSED DUMPSTER CART DESIGNED FOR SUCH PURPOSED
WITH A LID.
ALL MATERIAL, DEBRIS AND HAZARDOUS MATERIALS SHALL BE PROPERLY
STORED IN DESIGNATED AREAS AND APPROVED CONTAINERS. FLAMMABLE
MATERIALS SHALL NOT BE STORED IN THE FACILITY.
PROVIDE CONTAINMENT CART FOR ABOVE CEILING ACCESS OUTSIDE
PROJECT BOUNDARY.
TEMPORARY PLASTIC CONSTRUCTION BARRIERS WILL BE REQUIRED TO
PROTECT THE LAB SPACE FROM THE CONSTRUCTION DEBRIS CREATED
WHEN CONSTRUCTING TEMPORARY PARTITIONS.
A
B
C
D
E
F
G
H
I
J
K
L
M
N
O
P
Q
R
INFECTION CONTROL GENERAL NOTES
PHASING GENERAL NOTES #
A
B
C
PROJECT AREAS TO BE OCCUPIED BY STAFF AND VETERANS THROUGHOUT
CONSTRUCTION.
CONSTRUCTION WORK BEHIND TEMPORARY CONSTRUCTION PARTITIONS
SHALL BE COMPLETED DURING NIGHT SHIFTS, 5:00 PM TO 5:00 AM.
REFER TO SPECIFICATION 01 00 00 FOR INFORMATION ON WORK DURATION
FOR EACH PHASE AND AREA OF WORK.
PHASING NARRATIVE: PHASE 3
PHASE 3:
DURING THIS PHASE THE NEW CUTTING, EMBEDDING, AND
GROSSING AREAS ARE CONSTRUCTED. THE STAINER
EQUIPMENT WILL TEMPORARILY BE INSTALLED AT
EASTERN MOST CUTTING STATION TO BE IN THE
PROXIMITY OF THE CUTTING AND EMBEDDING STATIONS.
STAFF ACCESS MUST REMAIN FOR F.I.S.H., EM SCOPE,
AND THE INAC. SLD. BLK. STORAGE SPACE.
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
Consultant:
GUIDON DESIGN INC.
1221 N. PENNSYLVANIA ST. | INDIANAPOLIS, IN. 46202
317.800.6388 | WWW.GUIDONDESIGN.COM
SUSTAINABLE ARCHITECTURE + ENGINEERING
PROJECT LEAD
Architect, Structural Engineer, Civil Engineer
C U s e rs
\d v a lla n d in g h a m \D o c u m e n ts
\1 .1
.0
V A
I n d ia n a p o lis
L a b
R e n o v a ti o n d v a lla n d in g h a m g u id o n d e s ig n .c o m
.r v t
/1
/2
:3
:0
P
M
GI104
PHASING PLAN - PHASE 3
HEAPY ENGINEERING
3850 PRIORITY WAY SOUTH SUITE 204
INDIANAPOLIS, IN 46240
317.571.8795
WWW.HEAPY.COM
RENOVATE LAB - HISTOLOGY,
CYTOLOGY, AND MOLECULAR
1481 W 10TH ST, INDIANAPOLIS, IN
583-18-102
06/24/2020
BID DOCUMENTS
FULLY SPRINKLERED
SCALE: 3/16" = 1'-0"GI104
1 SECOND FLOOR PHASING PLAN - PHASE 3
N
SCALE: 1" = 100'-0"
KEY PLAN
TANK
A-2055
TELE. ROOM
A-2056
ELEC. ROOM
A-2057
STERILE
SOLUTION
A-2051
STERILIZER
A-2050GIP STORAGE
A-2054A
TISSUE
A-7
CUTTING AREA
A-2
EMBEDDING
A-3
GROSSING
A-4
A10A
A1F
A12A
A11A
A11B
A10CA12C
A11C
A13
A9B
A9A
A7A
A7B
A7C
A1B A1A
A1C
A1D
A24B
A16
A56
A3
A59B
A59A
A62 A50
A63
A8
A15
FLUOR. MS.
A-2054
A17A
A17B
M21 M45
M42
M26 M19
M44
M39
M51B
M51A
M51C
M29
WALK-IN
REFRIGERATOR
M20M37
INFECTION CONTROL PLAN NOTES #
INFECTION CONTROL PROJECT INFORMATION
CONSTRUCTION ACTIVITY - FIRE RISK: TYPE C
PATIENT RISK GROUP: HIGH
CLASS OF PRECAUTION MATRIX: III
PROVIDE TEMPORARY 1 HR FIRE RATED SMOKE BARRIER WALL
CONSTRUCTION PER NFPA 241. REFER TO DETAIL 2/GI102.
PROVIDE TEMPORARY INFECTION CONTROL CONSTRUCTION DOOR WITH BLUE
CORE. REFER TO ELEVATION 4/GI102.
NOT USED
PROVIDE TEMPORARY INFECTION CONTROL PLASTIC BARRIER WALL
CONSTRUCTION. REFER TO SPECIFICATION FOR ADDITIONAL INFORMATION.
REFER TO LIST OF REQUIRED INFECTION CONTROL PRECAUTIONS OUTLINED
BY CLASS IN SPECIFICATION 010110 AND ADDITIONAL INFORMATION.
REFER TO DRAWINGS, SPECIFICATIONS AND DOOR HARDWARE SCHEDULE
FOR ADDITIONAL INFORMATION.
PROJECT SHALL BE COMPLETED IN 12 PHASES.
COORDINATE FULL SCOPE OF WORK WITH ENGINEERING DRAWINGS AND
FIELD VERIFICATION. CONTRACTOR IS RESPONSIBLE FOR SCOPE OF ABOVE
CEILING WORK REQUIRED ABOVE AND BELOW THE FLOOR PLATE OF THE
PROJECT BOUNDARY.
COORDINATE LOCATION OF TEMPORARY INFECTION CONTROL (IC) BARRIER
WALL CONSTRUCTION AND INFECTION CONTROL (IC) MEASURES WITH COR
AND PATIENT SAFETY/ INFECTION CONTROL REPRESENTATIVE. TEMPORARY
IC BARRIER WALL CONSTRUCTION LOCATIONS IN DRAWINGS ARE
APPROXIMATE. CONTRACTOR SHALL PROVIDE DRAWING TO COR AND
PATIENT SAFETY/ INFECTION CONTROL REPRESENTATIVE ONCE ICRA
PROTOCOLS AND PLAN IS APPROVED.
CONTRACTOR TO VERIFY 1-HOUR WALL CONTINUOUSLY WRAPS SUITE AS
ANNOTATED IN DRAWINGS. CONTRACTOR TO CORRECT EXISTING WALLS
THAT ARE NOT 1-HR RATED TO SURROUND SUITE IN REQUIRED SEPARATION.
SCHEDULE AND TIME OF CONSTRUCTION WORK TO BE APPROVED BY COR
AND NURSING STAFF BEFORE CONSTRUCTION MAY BEGIN. PROVIDE PHASING
INFORMATION FOR ABOVE CEILING WORK IN THE CONTRACTOR PROVIDED
CMP SCHEDULE FOR WORK ALSO REQUIRED ABOVE AND BELOW THE FLOOR
PLATE OF THE PROJECT BOUNDARY.
ABOVE CEILING WORK SHALL TAKE PLACE BETWEEN THE HOURS OF 5:00 PM
AND 5:00 AM. IN AREAS THAT REQUIRE ABOVE CEILING WORK WHERE
CEILINGS ARE TO REMAIN, CEILING TILES SHALL BE REMOVED AND STORED IN
A SAFE MANOR UNTIL CEILING TILES CAN BE REINSTALLED. DAMAGED AND
BROKEN CEILING TILES SHALL BE REPLACED BY CONTRACTOR.
EXIT/ACCESS FOR ADJACENT OPERATIONAL AREAS SHALL BE MAINTAINED
DURING NORMAL BUSINESS HOURS. SEE SPECIFICATION FOR HOURS OF
OPERATION.
WORK REQUIRING VIBRATION OR LOAD NOISE SHALL TAKE PLACE BETWEEN
THE HOURS OF 5:00 PM AND 5:00 AM. EVERY EFFORT SHALL BE MADE TO
KEEP NOISE AND VIBRATION TO A MINIMUM.
PROVIDE THE FOLLOWING INFECTION CONTROL MEASURES, A 24"X36" STICKY
WALK OFF MAT AND HAND SANITIZER AT EACH TEMPORARY DOOR LOCATION.
MAT SHALL BE REPLACED OR CLEANED AS NECESSARY
PROVIDE THE VA AND OSHA REQUIRED TEMPORARY SIGNAGE AT EACH
TEMPORARY DOOR LOCATION.
CONTRACTOR SHALL SUPPLY SPILL KIT. SPILL KIT TO INCLUDE SHOP VAC,
MULTI-PURPOSE SPILL CONTROL SORBENTS TO ABSORB NON AGGRESSIVE
LIQUIDS UP TO 30 GALLONS.
ALL NEW MATERIAL MOVED THROUGH THE FACILITY SHALL BE COVERED WITH
4 MIL. POLY SHEET.
ALL DEMOLITION MATERIAL SHALL BE REMOVED FROM THE PROJECT
BOUNDARY THROUGH THE FACILITY TO DUMPSTER ALONG VA APPROVED
ROUTE IN ENCLOSED DUMPSTER CART DESIGNED FOR SUCH PURPOSED
WITH A LID.
ALL MATERIAL, DEBRIS AND HAZARDOUS MATERIALS SHALL BE PROPERLY
STORED IN DESIGNATED AREAS AND APPROVED CONTAINERS. FLAMMABLE
MATERIALS SHALL NOT BE STORED IN THE FACILITY.
PROVIDE CONTAINMENT CART FOR ABOVE CEILING ACCESS OUTSIDE
PROJECT BOUNDARY.
TEMPORARY PLASTIC CONSTRUCTION BARRIERS WILL BE REQUIRED TO
PROTECT THE LAB SPACE FROM THE CONSTRUCTION DEBRIS CREATED
WHEN CONSTRUCTING TEMPORARY PARTITIONS.
A
B
C
D
E
F
G
H
I
J
K
L
M
N
O
P
Q
R
INFECTION CONTROL GENERAL NOTES
PHASING GENERAL NOTES #
A
B
C
PROJECT AREAS TO BE OCCUPIED BY STAFF AND VETERANS THROUGHOUT
CONSTRUCTION.
CONSTRUCTION WORK BEHIND TEMPORARY CONSTRUCTION PARTITIONS
SHALL BE COMPLETED DURING NIGHT SHIFTS, 5:00 PM TO 5:00 AM.
REFER TO SPECIFICATION 01 00 00 FOR INFORMATION ON WORK DURATION
FOR EACH PHASE AND AREA OF WORK.
IC/PHASING LEGEND
TEMPORARY WALLS. SEE PLAN AND
PLAN NOTES
TEMPORARY CONSTRUCTION ACCESS
DOORS
REFERENCE AREA FOR ABOVE
CEILING WORK ON FLOOR BELOW.
REFER TO ENGINEERING DRAWINGS
FOR FULL SCOPE OF WORK
BEYOND PROJECT BOUNDARY
PROJECT BOUNDARY
PHASING NARRATIVE: PHASE 4
PHASE 4:
DURING THIS PHASE ALL REMAINING EXISTING
EQUIPMENT LOCATED IS HISTOLOGY IS RELOCATED TO
TEMPORARY LOCATIONS. THE FINAL WALLS OF OF THIS
AREA ARE CONSTRUCTED AND THE SPACE WILL SOON
HOUSE TEMPORARILY LOCATED EQUIPMENT.
A
B
C
D
E
F
16 15 14 13 12
DEVELOP.
(F.I.S.H.)
A-2063
EM SCOPE
A-2065
RESIDENTS
A-2099
LAB
INFORMATION
MANAGER
A-2078
PROCEDURE
ROOM
A-2077
MOLECULAR
PATHOLOGY
LABORATORY
A-2043
H.A.C.
A-2103
LIFT
C-2 REFRIGERATOR
A-2101
TEACHING
MICROSCOPY
A-2100
STAFF
PATHOLOGIST
A2038
STAFF
PATHOLOGIST
A-2039
STAFF
PATHOLOGIST
A-2040
A-2045
SUPERVISOR
A-2046
MYCOBACT.
A-2047
BIOSAFETY
A-2049
PROSTATE
CANCER
RESEARCH
A-2133
A-2132A
CONTAIN.
A-2048
CYTOLOGY
A-2067
HISTOLOGY
A-2042
CYTOLOGY
A-2041
CORRIDOR
C2-5
MICROBIOLOGY
A-2044
CORRIDOR
C2-2
CORRIDOR
C2-3
CORRIDOR
A2-8
SPEC. CHEM
A-2132
ATRIUMATRIUM
INAC. SLD. BLK.
A-2066
CORRIDOR
C2-4
CORRIDOR
C2-9 A48
A38
A39 A34
A35
A36A37
M35B
M35A
A40
A20C
A20B
A20D
A19B
A19D
A19C
A19A20
M15 M6M16
M7 M5
M13
M17
M8
M9
M10
M17
M12
CONTRACTOR
ACCESS
AMPLI-PREP
A-2060
2 1
M22 M12
M46
A27A A27B A27C
M25
A26AA60
A61
A24A
FUME
HOOD
GROSS
STATION
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
Consultant:
GUIDON DESIGN INC.
1221 N. PENNSYLVANIA ST. | INDIANAPOLIS, IN. 46202
317.800.6388 | WWW.GUIDONDESIGN.COM
SUSTAINABLE ARCHITECTURE + ENGINEERING
PROJECT LEAD
Architect, Structural Engineer, Civil Engineer
C U s e rs
\d v a lla n d in g h a m \D o c u m e n ts
\1 .1
.0
V A
I n d ia n a p o lis
L a b
R e n o v a ti o n d v a lla n d in g h a m g u id o n d e s ig n .c o m
.r v t
/1
/2
:3
:0
P
M
GI105
PHASING PLAN - PHASE 4
HEAPY ENGINEERING
3850 PRIORITY WAY SOUTH SUITE 204
INDIANAPOLIS, IN 46240
317.571.8795
WWW.HEAPY.COM
RENOVATE LAB - HISTOLOGY,
CYTOLOGY, AND MOLECULAR
1481 W 10TH ST, INDIANAPOLIS, IN
583-18-102
06/24/2020
BID DOCUMENTS
FULLY SPRINKLERED
N
SCALE: 1" = 100'-0"
KEY PLAN
SCALE: 3/16" = 1'-0"GI105
1 SECOND FLOOR PHASING PLAN - PHASE 5
C
D
E
F
16 15 14 13 12
DEVELOP.
(F.I.S.H.)
A-2063
EM SCOPE
A-2065
RESIDENTS
A-2099
LAB
INFORMATION
MANAGER
A-2078
PROCEDURE
ROOM
A-2077
MOLECULAR
PATHOLOGY
LABORATORY
A-2043
H.A.C.
A-2103
LIFT
C-2 REFRIGERATOR
A-2101
TEACHING
MICROSCOPY
A-2100
STAFF
PATHOLOGIST
A2038
STAFF
PATHOLOGIST
A-2039
STAFF
PATHOLOGIST
A-2040
A-2045
SUPERVISOR
A-2046
MYCOBACT.
A-2047
BIOSAFETY
A-2049
PROSTATE
CANCER
RESEARCH
A-2133
A-2132A
CONTAIN.
A-2048
CYTOLOGY
A-2067
HISTOLOGY
A-2042
CYTOLOGY
A-2041
CORRIDOR
C2-5
MICROBIOLOGY
A-2044
CORRIDOR
C2-2
CORRIDOR
C2-3
CORRIDOR
A2-8
SPEC. CHEM
A-2132
ATRIUMATRIUM
INAC. SLD. BLK.
A-2066
CORRIDOR
C2-4
CORRIDOR
C2-9 A48
A38
A39 A34
A35
A36A37
M35B
M35A
A40
A20C
A20B
A20D
A19B
A19D
A19C
A19A20
M15 M6M16
M7 M5
M13
M17
M8
M9
M10
M17
M12
M
IN
3'
MIN.
5' - 0".
CONTRACTOR
ACCESS
BLOCKS AND
SLIDES
A-2066
TANK
A-2055
TELE. ROOM
A-2056
ELEC. ROOM
A-2057
STERILE
SOLUTION
A-2051
STERILIZER
A-2050GIP STORAGE
A-2054A
TISSUE
A-7
CUTTING AREA
A-2
EMBEDDING
A-3
GROSSING
A-4
A10A
A1F
A12A
A11A
A11B
A10CA12C
A11C
A9B
A9A
A7A
A7B
A7C
A1B A1A
A1C
A1D
A24B
A16
M54M54
M56
A57
A56
A3
A59B
A59A
A62 A50
GIP STORAGE
A-8
A63
A8
A15
FLUOR. MS.
A-2054
F.I.S.H.
A-2067
M53 M52
M21 M45
M42
M26 M19
M44
M39
M51B
M51A
M51C
M29
WALK-IN
REFRIGERATOR
M20M37
M22 M12
M46
A27A A27B A27C
M25
A26AA60
A61
A24A
IC/PHASING LEGEND
TEMPORARY WALLS. SEE PLAN AND
PLAN NOTES
TEMPORARY CONSTRUCTION ACCESS
DOORS
REFERENCE AREA FOR ABOVE
CEILING WORK ON FLOOR BELOW.
REFER TO ENGINEERING DRAWINGS
FOR FULL SCOPE OF WORK
BEYOND PROJECT BOUNDARY
PROJECT BOUNDARY
INFECTION CONTROL PLAN NOTES #
INFECTION CONTROL PROJECT INFORMATION
CONSTRUCTION ACTIVITY - FIRE RISK: TYPE C
PATIENT RISK GROUP: HIGH
CLASS OF PRECAUTION MATRIX: III
PROVIDE TEMPORARY 1 HR FIRE RATED SMOKE BARRIER WALL
CONSTRUCTION PER NFPA 241. REFER TO DETAIL 2/GI102.
PROVIDE TEMPORARY INFECTION CONTROL CONSTRUCTION DOOR WITH BLUE
CORE. REFER TO ELEVATION 4/GI102.
NOT USED
PROVIDE TEMPORARY INFECTION CONTROL PLASTIC BARRIER WALL
CONSTRUCTION. REFER TO SPECIFICATION FOR ADDITIONAL INFORMATION.
REFER TO LIST OF REQUIRED INFECTION CONTROL PRECAUTIONS OUTLINED
BY CLASS IN SPECIFICATION 010110 AND ADDITIONAL INFORMATION.
REFER TO DRAWINGS, SPECIFICATIONS AND DOOR HARDWARE SCHEDULE
FOR ADDITIONAL INFORMATION.
PROJECT SHALL BE COMPLETED IN 12 PHASES.
COORDINATE FULL SCOPE OF WORK WITH ENGINEERING DRAWINGS AND
FIELD VERIFICATION. CONTRACTOR IS RESPONSIBLE FOR SCOPE OF ABOVE
CEILING WORK REQUIRED ABOVE AND BELOW THE FLOOR PLATE OF THE
PROJECT BOUNDARY.
COORDINATE LOCATION OF TEMPORARY INFECTION CONTROL (IC) BARRIER
WALL CONSTRUCTION AND INFECTION CONTROL (IC) MEASURES WITH COR
AND PATIENT SAFETY/ INFECTION CONTROL REPRESENTATIVE. TEMPORARY
IC BARRIER WALL CONSTRUCTION LOCATIONS IN DRAWINGS ARE
APPROXIMATE. CONTRACTOR SHALL PROVIDE DRAWING TO COR AND
PATIENT SAFETY/ INFECTION CONTROL REPRESENTATIVE ONCE ICRA
PROTOCOLS AND PLAN IS APPROVED.
CONTRACTOR TO VERIFY 1-HOUR WALL CONTINUOUSLY WRAPS SUITE AS
ANNOTATED IN DRAWINGS. CONTRACTOR TO CORRECT EXISTING WALLS
THAT ARE NOT 1-HR RATED TO SURROUND SUITE IN REQUIRED SEPARATION.
SCHEDULE AND TIME OF CONSTRUCTION WORK TO BE APPROVED BY COR
AND NURSING STAFF BEFORE CONSTRUCTION MAY BEGIN. PROVIDE PHASING
INFORMATION FOR ABOVE CEILING WORK IN THE CONTRACTOR PROVIDED
CMP SCHEDULE FOR WORK ALSO REQUIRED ABOVE AND BELOW THE FLOOR
PLATE OF THE PROJECT BOUNDARY.
ABOVE CEILING WORK SHALL TAKE PLACE BETWEEN THE HOURS OF 5:00 PM
AND 5:00 AM. IN AREAS THAT REQUIRE ABOVE CEILING WORK WHERE
CEILINGS ARE TO REMAIN, CEILING TILES SHALL BE REMOVED AND STORED IN
A SAFE MANOR UNTIL CEILING TILES CAN BE REINSTALLED. DAMAGED AND
BROKEN CEILING TILES SHALL BE REPLACED BY CONTRACTOR.
EXIT/ACCESS FOR ADJACENT OPERATIONAL AREAS SHALL BE MAINTAINED
DURING NORMAL BUSINESS HOURS. SEE SPECIFICATION FOR HOURS OF
OPERATION.
WORK REQUIRING VIBRATION OR LOAD NOISE SHALL TAKE PLACE BETWEEN
THE HOURS OF 5:00 PM AND 5:00 AM. EVERY EFFORT SHALL BE MADE TO
KEEP NOISE AND VIBRATION TO A MINIMUM.
PROVIDE THE FOLLOWING INFECTION CONTROL MEASURES, A 24"X36" STICKY
WALK OFF MAT AND HAND SANITIZER AT EACH TEMPORARY DOOR LOCATION.
MAT SHALL BE REPLACED OR CLEANED AS NECESSARY
PROVIDE THE VA AND OSHA REQUIRED TEMPORARY SIGNAGE AT EACH
TEMPORARY DOOR LOCATION.
CONTRACTOR SHALL SUPPLY SPILL KIT. SPILL KIT TO INCLUDE SHOP VAC,
MULTI-PURPOSE SPILL CONTROL SORBENTS TO ABSORB NON AGGRESSIVE
LIQUIDS UP TO 30 GALLONS.
ALL NEW MATERIAL MOVED THROUGH THE FACILITY SHALL BE COVERED WITH
4 MIL. POLY SHEET.
ALL DEMOLITION MATERIAL SHALL BE REMOVED FROM THE PROJECT
BOUNDARY THROUGH THE FACILITY TO DUMPSTER ALONG VA APPROVED
ROUTE IN ENCLOSED DUMPSTER CART DESIGNED FOR SUCH PURPOSED
WITH A LID.
ALL MATERIAL, DEBRIS AND HAZARDOUS MATERIALS SHALL BE PROPERLY
STORED IN DESIGNATED AREAS AND APPROVED CONTAINERS. FLAMMABLE
MATERIALS SHALL NOT BE STORED IN THE FACILITY.
PROVIDE CONTAINMENT CART FOR ABOVE CEILING ACCESS OUTSIDE
PROJECT BOUNDARY.
TEMPORARY PLASTIC CONSTRUCTION BARRIERS WILL BE…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .