36C25018Q9337 0005 36C25018Q9337 0005.docx

View the file

Other files

File Type Posted
-14954.docx DOCX document
36C25018Q9337-0006006.pdf PDF
36C25018Q9337-0006005.docx DOCX document
36C25018Q9337-0006004.docx DOCX document
36C25018Q9337-0004000.docx DOCX document
36C25018Q9337-0003000.docx DOCX document
36C25018Q9337-0002000.docx DOCX document
36C25018Q9337-0001000.docx DOCX document
36C25018Q9337-000.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE

7. ADMINISTERED BY

2.

AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER

3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE

OF PAGES

10A. MODIFICATION OF

CONTRACT/ORDER NUMBER

10B. DATED

BPA NO.

1. CONTRACT ID CODE

FACILITY CODE

CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV.

11/2016) is required to sign this document and return ___________ copies to the issuing office.

is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO:

Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITE M 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES

SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR

43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes r eference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS

ENTERED INTO

PURSUANT TO AUTHORITY OF:

D. OTHER

BY

Contractor

16C. DATE SIGNED

14.

DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME

AND TITLE OF SIGNER

16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30

PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS

OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer) 07-11-2018 552-18-3-6115-0031

NONE

36C250 Network Contracting Office (NCO) 10 Department of Veterans Affairs Dayton VA Medical Center 3140 Governor’s Place Blvd. Suite 210 Kettering OH 45409-1337 36C250 Network Contracting Office (NCO) 10 Department of Veterans Affairs Dayton VA Medical Center 3140 Governor’s Place Blvd. Suite 210 Kettering OH 45409-1337 To all Offerors/Bidders

36C25018Q9337 07-11-2018

X X X X The purpose of this Combined Solicitation/Synopsis Amendment is to:

A. Provide answers to questions received;

B. Provide new cost proposal form; and C. Proposal due date and time is not changed from Amendment 0004 - July 13, 2018, 1600 (4:00pm) D. All other terms and conditions remain the same.

NOTE: Ensure you annotate in proposal that you have read and understand all Amendments (0001, 0002, 0003, 0004, 0005) to date. Also, ensure a SF 30 is signed, dated and returned with prop osal.

Contract Specialist: Donna Sizemore, Contractor TAG, (937) 268-6511 ext 2324, donna.sizemore@va.gov

ADAM WEBER

Contracting Officer

VA-VHA-SAOC-2016-38C45735

Q1Would you please have another Mandatory site visit later this week or early next week?
A1Another site visit was scheduled for 7/2/2018 at 10:00am.
Q2As per conversation with the Bidders on the Mandatory Site Visit, June 26, 2018, for clarification, Government Furnished Equipment/Supplies to the Contractor?
A2As per Performance Work Statement (PWS), yes.
Q3Is there a building 322?
A3Yes, it is the CT scan area. It is patient care.
Q4Can we have the breakdown of carpet and VCT flooring in building 330?
A4Ratio is 60%/40%. 60% hard and 40% carpeted.
Q5What is the budget for this project?
A5A budget is not set, the competition from the Solicitation will help determine the budget as

this is the first time for this requirement.

Q6How many EMS staff members are covering these locations?
A6There is 2nd shift staff that cover these areas. 18 housekeepers in the shift.
Q7Can we have a list of room numbers that we are responsible for in building 330?
A7This was addressed during the walk through. All vendors were shown the areas that would fall under the contract during this timeframe. There is no set number of rooms.
Q8Is this project intended for only local vendors?
A8There is no restriction.
Q9We would like to confirm that a ‘capabilities statement’ is to be submitted with our proposal and not a narrative of our ‘technical capabilities’
A9Provide both a Capabilities Statement and Technical Capabilities.
Q10Can you provide a breakdown of SF by carpet and hard flooring requiring strip and waxing?
A10Please refer to Q4.
Q11Are we responsible for the badging cost? If so, how much is it per associate?
A11A Non-PIV (Physical Access Only) Card is required. There is no cost of badge itself, the Government covers the badge cost. However, there is a cost for fingerprinting, this cost is $25-$35 per person. This cost is to the Contractor. Additionally, Keys will be provided if there are spaces that need to be accessed. According to policy, a lost key will set a charge of a minimum $15 up to a maximum of $2000 per incident. Additionally, Keys may be issued by Service Chiefs to non-VA employees working for them in a consultant/liaison capacity, e.g., an individual working at the Dayton VA Medical Center but salaried by another medical institution. Such issuances may be accomplished only when the Service Chief makes arrangements to collect and retain from the consultant/liaison $50.00 per key issued until such time that the key(s) are returned, at which time the collected monies will be returned to the consultant/liaison.

Q12 Ref: SOW Pg 5 Item 7 (c) “total supplies and equipment costs” Comment: the SOW states on page 9 item C that the government is to furnish equipment and “any other supplies needed to accomplish daily tasks”.

Question: Will the government please confirm whether the contractor will or will not be responsible for any supplies i.e. paper products, cleaning agents, wax, burnishing pads, trash bags etc or equipment i.e. floor machines, carpet shampooer, custodial carts, tool caddies etc.?

A12 As per SOW, “(paper towels, toilet paper, hand soap, hand sanitizer, detergent, disinfectant solution, power equipment and any other supplies needed to accomplish daily tasks)” will be provided by the government.

Q13 Ref: Pg 8, number 5 Frequency of Services Required:

Question: All services are to be performed on either a daily, weekly, monthly or semi-annual basis or “as needed”. Who determines if a service is “as needed” and what standard will be used to make this determination?

A13Chief of EMS or his designee or the COR shall make this determination based on industry
recommendations or findings from QA/QC or EOC rounds.

Q14 Ref: Pg 6. Item 4 (b) and;

Ref 2: Pg 6, item 5, “contractor will perform cleaning services in administrative and non-direct patient care areas, and;

Ref 3: Pg 8, item 5 Frequency of Services Required, (Daily Tasks – Exam Rooms/Lab) Comment: The site visit stated that no cleaning of patient treatment areas would take place. Only common areas and admin areas.

Question: Will the contractor be responsible for cleaning any patient treatment areas?

A14 Contractor is not required to clean direct patient care areas.

Q15 Ref: Page 10, item 10 Question: will the government provide laundry facilities? What responsibility will the contractor have in washing mop heads and dusting cloths?

A15 Contractor will turn in mop heads and cloths into EMS for laundry cleaning.

Q16Question: Will the government pre-position all equipment needed in each building to be cleaned or will the contractor be required to move equipment from building to building and then return it to storage?
A16Equipment will be in designated areas. Contractor will have access to the equipment.
Q17Question: Will the government please provide a detailed breakdown of flooring types by SF, per building. i.e. Bldg 999 - 20,000 SF of carpet, 30,500 SF VTC, 10,000 SF Laminate.
A17Ratio is 60%/40%. 60% hard and 40% carpeted.
Q18Question: Will the government please provide a count of restrooms to be serviced?
A18Approximate number of restrooms to be serviced is 150.
Q19Question: How many windows are to be cleaned?
A19Interior of windows were to be cleaned only. No exterior window cleaning is required. Windows will be cleaned with supplied cleaning gear by EMS, i.e. glass cleaner, squeegee. There are approximately 2,100 windows included in the 17 buildings. However, contractor must remember this number includes patient rooms that are NOT to be cleaned by the contractor.
Q20Question: On the site visit it was mentioned that the contractor was not to dust desks, desk chairs, computers, bookshelves and other like personal work space items. Will the government please confirm this is SOW’s intent?
A20Personal work area space is NOT part of this solicitation.
Q21Question: To what height above the floor level will the contractor be responsible for dusting?
A21This was addressed during the walkthrough.
Q22Question: Will the government furnish office space for the contractor to use? If so what utilities will be provided to the contractor?
A22Space can be provided for supervision. No access to network unless approved by appropriate VA and OI&T offices.
Q23Question: Will there be a phase in period to contract performance?
A23No.
Q24Question: who will be responsible for repair of broken or damaged equipment? The government or the contractor?
A24The government.
Q25It was stated at the site visit that the contractor is only responsible for labor only and none of the following; cleaning equipment, supplies, chemicals, etc. Can you confirm this please?
A25This was addressed during the walk through and within the PWS.
Q26It was stated we could request and receive a schematic drawling of the buildings requiring housekeeping services with the correct square footage and with rooms marked do not clean or possibly shaded out. Can you provide this?
A26A schematic of the buildings could be provided; however, the plans would not be marked with each room that needs to be cleaned or square footage. A request has been put in with Engineering to provide drawings, EMS is still waiting on receipt of drawings.
Q27The square footage provided seems to be incorrect. Can the correct cleanable square footages be provided for all 17 buildings? Several areas were either larger or smaller.
A27Please use the square footage provided in the Performance Work Statement (PWS) and Amendment 0001 to the Combined Solicitation/Synopsis.
Q28It was stated that some areas require high dusting which requires lifts or very tall ladders that are provided by the VA.
A28Yes, this is correct.
Q29It was stated that an office would be provided for the contractor to work out of and for employees to clock in & out at. Is this correct?
A29Office will be provided. It is the contractor’s responsibility to clock in and out their employees.
Q30Can you provide the number of stairwell in building 330 the VA Hospital?
A31Seven stairwells
Q31Does the contractor work on holidays?
A31This is addressed in the PWS.
Q32The VA Medical Center building 330 is asking for very high dusting which requires the use of very tall ladders. This is not in the scope of work. Please advise.
A32This was addressed during the walk through. Also, refer to Q38/A38.
Q33Can you provide a map of the entire campus?
A33Yes.
Q34Can you provide a floor plan map of each building?
A34These have been requested from engineering, still waiting to receive.
Q35Can you provide an estimated square footage of carpeted areas vs. hard floor areas for each building?
A35Refer to Q4/A4.
Q36During the walk through, there were areas of multiple buildings that we were told we would not be responsible for cleaning them. Can we get an estimated square footage or percentage for each building for the areas we ARE responsible for?
A36Refer to Q4/A4.
Q37Can you provide us with an estimated square footage for any storage space or workspace that will be provided to us (the contractor) for our equipment storage or potential office workspace?
A37There is not a set work space at this time for office workspace. EMS has a warehouse that can be used to store any contractor equipment needed.
Q38During the walk through it was mentioned we would be able to use ladders or possibly lifts provided by the VA when doing the high cleaning requirements in the lobby of building 330. Can we get confirmation that this is true? If yes, what types of equipment would be available to us? i.e. Height of ladder, scissor lift or boom lift, etc.
A38Yes, this is true. Scissors lift, ladders will be provided.
Q39Can we receive a list of any chemicals and materials that will be provided by the VA for contractor use? Would any of the chemicals include spray bottles for use or come in aerosol form?
A39Yes. No aerosol.
Q40Does the current crew use the chemical method for stripping wax from the floors? If yes, are we expected to also use this method? We prefer the chem-free machine method for stripping floors as it is faster, easier to keep clean, and more environmentally friendly, would we be allowed to use this method?
A40Contractor can use any method that complies with VA and EMS policy.
Q41During the walk through we were told as a contractor we will be expected to provide labor and specialty equipment and we would be able to use regular machinery and equipment provided by the VA. Can we receive confirmation that this is correct, if so can we receive a list of any machinery and equipment we would be able to use? i.e. vacuums, janitorial carts, large trash carts, floor buffers, mopping systems, auto-scrubbers, cleaning rags, etc.
A41DVAMC shall supply all supplies and equipment needed to perform cleaning services.
Q42Is there a limit to the number of keys we can be assigned? This would help with potential staffing numbers for managers/leads.
A42DVAMC protocol will be followed.
Q43How many exterior windows are there to be cleaned semi-annually?
A43Not part of this solicitation.
Q44Can the exterior windows be cleaned by ladder?
A44Not part of this solicitation.
Q45Is there terminal cleaning involved?
A45No, no patient care areas to be cleaned by contractor.
Q46In the solicitation it states the following:

GOVERNMENT FURNISHED EQUIPMENT/SUPPLIES

(paper towels, toilet paper, hand soap, hand sanitizer, detergent, disinfectant) solution, power equipment and any other supplies needed to accomplish daily tasks.

But right under that it states the following:

1. CONTRACTOR FURNISHED EQUIPMENT/SUPPLIES

1. The contractor shall be furnished the supplies necessary to perform all services required. Supplies and equipment shall meet the specifications below and comply with VA, federal or state Occupational Safety and Health Standards and fire regulations. Contractor furnished items shall be subject to use by VA employees. A listing of these items follows, paper towels, toilet paper, hand soap, hand sanitizer, power equipment etc.).

Can you clarify if the Government or the Contractor will supply the cleaning items?

A46 Government provided. Yes, both items state the contractor SHALL be furnished the supplies necessary to perform all services required. If contractor brings in their own items/equipment it must conform to these specifications.

Q47Do you anticipate an extension by amendment to the subject solicitation?
A47Yes, it will be extended to COB (1600 hours) Friday, July 13, 2018
Q48Does the statement "remove work to be completed annually" in the last amendment mean that just annual cleaning or does this also refer to semi-annual as well?
A48There was an Annual column in the table that was deleted. The one item within this column was moved over to the semi-annual column. Essentially, when contract is in the 5th month, they will complete these requirements.
Q49The statement of work looked the same. Will there be a revised statement of work and price schedule?
A49The Performance Work Statement was updated to remove one-year base, the four option years, annual column of work to be completed, etc. Yes, a new price sheet is included with this amendment.
Q50Is this requirement know longer needed beyond six months? Why have the option years been removed?
A50No one is allowed to replace Government workers without a Competitive Sourcing effort, which is currently not approved or appropriated by Congress. We can augment for a temporary time frame. Option years were removed due to augmenting for a temporary time frame.
Q51This project is going to require a large staff that will be unemployed in 6 months. Is there a possibility of an extension beyond 6 months?
A51Amendment 0004 to Combined Solicitation/Synopsis added FAR Clause 52.217-8, Option to Extend Services. However, there is no guarantee this will occur.

Cost Proposal Worksheet to be Submitted with Proposal

Total hours labor hours per week: _____ Total labor cost per week _____ X _____=$______ Total health and welfare costs per week _____ X _____=$______ Total management costs per month = _____ Total supplies and equipment costs per month = _____ Total sick time accrual cost per month = _____

Total 6-month cost is $______________