Refurb Sample schedule.docx
DOCX document 16 KB Posted
- Solicitation number
- 36C24924B0008
About this file
This document outlines a sample schedule for refurbishing transformers at a Veterans Affairs hospital over three days. The schedule details the specific tasks to be completed each day, including pulling and analyzing oil samples from various transformers, installing sample ports, repairing leaks, replacing caps and terminals, adding oil as needed, and performing maintenance. Tasks will be completed with the hospital's maintenance staff support and require briefly de-energizing circuits by opening and closing specified breakers. The related federal contract opportunity is for refurbishing transformers, issued by the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 9. The solicitation number and brief description are provided.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sample Schedule(weekday) Day 1
| 1700-1900 VA Maintenance staff makes preps in hospital for Day 1 work (temp power, etc.) |
| 1900-1915 Work Brief with VA maintenance rep on hand |
| 1915-1930 Contractor Opens Breaker #3 with VA maintenance rep concurrence. |
| 1930-2300 Contractor completes: |
Task 1 – Substation Breaker 3 Work
| Location |
| Requirement |
| 102-21 |
| Pull oil sample from existing sample port on Transform 21A and conduct analysis. |
Repair oil leak from Transform 21A.
2300-2330 Contractor coordinates with VA maintenance to close breaker #3 and re-energize.
2330-0000 VA maintenance recovers and preps for Task 2 and 3 work if applicable.
0000-0015 Work Brief with VA maintenance rep on hand 0015-0030 Contractor Opens Breaker #4 with VA maintenance rep concurrence.
0030-0400 Contractor completes:
Task 2 – Substation Breaker 9 Work (Energized work unless vendor wants it de-energized)
| Location |
| Requirement |
| 102-21 |
| Pull oil sample from existing sample port on Transform 21B and conduct analysis. |
Task 3 – Substation Breaker 4 Work
| Location |
| Requirement |
| EXT T20 |
| Pull oil sample from Transform T2 and conduct analysis. |
Install oil sample port on T2.
Add matching oil to Transformer T2 (up to 10 gallons) to correct level as necessary.
| EXT BLDG 7 |
| Pull oil sample from Transform T7 and conduct analysis. |
Install oil sample port on T7.
| 0330-0400 Contractor coordinates with VA maintenance to close breaker #4 and re-energize. |
| 0400-0500 VA maintenance staff recover. All restored by 0500. |
Day 2
| 1700-1900 VA Maintenance staff makes preps in hospital for Day 1 work (temp power, etc.) |
| 1900-1915 Work Brief with VA maintenance rep on hand |
| 1915-1930 Contractor Opens Breaker #5 with VA maintenance rep concurrence. |
| 1930-0330 Contractor completes: |
Task 4 – Substation Breaker 5 Work
| Location |
| Requirement |
| EXT BLDG 5 |
| Pull oil sample from Transform T12 and conduct analysis. |
Install oil sample port on Transform T12.
| EXT BLDG 4 |
| Pull oil sample from Transform T4 and conduct analysis. |
Install oil sample port on Transform T4
Install or replace primary bushing well end caps on Transformer T4
Add matching oil to Transformer T4 (up to 10 gallons) to correct level as necessary.
| EXT BLDG 1 |
| Pull oil sample from Transform T1 and conduct analysis. |
Install oil sample port on Transform T1.
Repair Transformer T1 primary cable termination by adding compression pin to seal out moisture.
| BLDG 3/4 |
| Test panel 3XA and panel 4XA |
0330-0400 Contractor coordinates with VA maintenance to close breaker #4 and re-energize.
0400-0500 VA maintenance staff recover. All restored by 0500.
Day 3
| 1700-1900 VA Maintenance staff makes preps in hospital for Day 1 work (temp power, etc.) |
| 1900-1915 Work Brief with VA maintenance rep on hand |
| 1915-1930 Contractor Opens Breaker #6 with VA maintenance rep concurrence. |
| 1930-0100 Contractor completes: |
Task 5 – Substation Breaker 6
| Location |
| Requirement |
| SB-2 |
| Pull oil sample from Transform 1A and conduct analysis. |
Pull oil sample from Transform 1B and conduct analysis.
| B-013-1 |
| Pull oil sample from Transform 1D and conduct analysis. |
| 002-19 |
| Pull oil sample from Transform T19 and conduct analysis. |
Install oil sample port on Transform T19 (Breaker 6)
Add matching oil to Transformer T19 (up to 10 gallons) to correct level as necessary. (Breaker 6)
| 101-6 |
| Perform dry type transformer deenergized annual maintenance on Transformer T6A |
Perform dry type transformer deenergized annual maintenance on Transformer T6B
Replace Feeder Breaker 3 servicing Panel “C” on building 6 switch gear (BLDG 6 FDR 3)
Replace Feeder Breaker 4 servicing Panel “AA” on building 6 switch gear (BLDG 6 FDR 4)
0100-0115 Contractor Opens Breaker #10 with VA maintenance rep concurrence.
| 0115-0330 Contractor completes: |
| 002-19 |
| Perform testing on 6/10 selector switch servicing T19 |
| B-013 |
| Perform testing on 6/10 selector switch servicing T1D |
0330-0400 Contractor coordinates with VA maintenance to close breaker #6 & 10 and re-energize.
0400-0500 VA maintenance staff recover. All restored by 0500.