Breakdown
| JOB NAME: LOCATION: TBD PROPOSAL DATE: 01/01/1900 | Solicitation Number | Project Number | Project Title | Proposal Date |
| 36C24922R0038 | 621-17-110 | Renovate Women's Health Clinic Bldg 162 | |
SPEC/COST CODE DESCRIPTION LABOR MATERIAL EQUIPMENT DIVISION TOTALS
| DIVISION 1 | GENERAL REQUIREMENTS | $0.00 |
| 01 00 00 | General Requirements | |
| 01 32 16.15 | Project Schedules (small projects - Design/Bid/Build) | |
| 01 33 23 | Shop Drawings, Product Data, and Samples | |
| 01 35 26 | Safety Requirements | |
| 01 42 19 | Reference Standards | |
| 01 45 29 | Testing Laboratory Services | |
| 01 45 35 | Special Inspections | |
| 01 58 16 | Temporary Interior Signage | |
| 01 74 19 | Construction Waste Management | |
| 01 81 13 | Sustainable Construction Requirements | |
| DIVISION 2 | Existing Conditions | $0.00 |
| 02 41 00 | Demolition | |
| 02 83 33.13 | Lead Based Paint Removal and Disposal | |
| DIVISION 3 | CONCRETE | $0.00 |
| 03 30 53 | Cast in Place Concrete | |
| DIVISION 4 | MASONRY | |
| 04 05 13 | Masonry Mortaring | |
| DIVISION 5 | Metals | $0.00 |
| 05 50 00 | Metal Fabrications | |
| DIVISION 6 | Wood, plastics and Composites | $0.00 |
| 06 10 00 | Rough Carpentry | |
| DIVISION 7 | THERMAL AND MOISTURE PROTECTION | $0.00 |
| 07 21 13 | Thermal Insulation | |
| 07 84 00 | Firestopping | |
| 07 92 00 | Joint Sealants | |
| DIVISION 8 | Openings | $0.00 |
| 08 11 13 | Hollow Metal Doors & Frames | |
| 08 14 00 | Interior Wood Doors | |
| 08 71 00 | Door Hardware | |
| DIVISION 9 | FINISHES | $0.00 |
| 09 05 16 | Subsurface Prep for Floor Finishing | |
| 09 06 00 | Schedule for Finishes | |
| 09 22 16 | Non Struct Metal Framing | |
| 09 29 00 | Gypsum Board | |
| 09 30 13 | Ceramic/Porcelain Tiling | |
| 09 51 00 | Acoustical Ceilings | |
| 09 65 13 | Resilient Base and Accessories | |
| 09 65 16 | Resilient Sheet Flooring | |
| 09 65 19 | Resilient Tiling Flooring | |
| 09 91 00 | Painting | |
| DIVISION 10 | Specialties | $0.00 |
| 10 26 00 | Wall & Door Protection | |
| 10 28 00 | Toilet, Bath, & Laundry Accessories | |
| DIVISION 11 | EQUIPMENT | |
| DIVISION 12 | Furnishings | $0.00 |
DIVISION 13 Special Construction $0.00
| DIVISION 21 | Fire Suppression | $0.00 |
| 21 13 13 | Wet-Pipe Sprinkler Systems | |
| DIVISION 22 | Plumbing | $0.00 |
| 22 05 11 | Common Work Results for Plumbing | |
| 22 05 12 | General Motor Requirements for Plumbing Equipment | |
| 22 05 19 | Meters and Gages for Plumbing Piping | |
| 22 05 23 | General Duty Valves for Plumbing Piping | |
| 22 07 11 | Plumbing Insulation | |
| 22 11 00 | Facility Water Distribution | |
| 22 13 00 | Facility Sanitary & Vent Piping | |
| 22 40 00 | Plumbing Fixtures | |
| DIVISION 23 | Heating, Ventilating and Air Conditioning HVAC | $0.00 |
| 23 05 11 | Common Work Results for HVAC | |
| 23 05 51 | Noise and Vibration Control for Boiler Plant | |
| 23 05 93 | Testing, Adjusting, and Balancing for HVAC | |
| 23 07 11 | HVAC and Boiler Plant Insulation | |
| 23 31 00 | HVAC Ducts and Casing | |
| 23 37 00 | Air Outlets and Inlets | |
| DIVISION 26 | ELECTRICAL | $0.00 |
| 26 05 11 | Requirements for Electrical Installations | |
| 26 05 19 | Low-Voltage Electrical Power Conductors and Cables | |
| 26 05 26 | Grounding and Bonding for Electrical Systems | |
| 26 05 33 | Raceway & Boxes for Electrical Systems | |
| 26 09 23 | Lighting Controls | |
| 26 27 26 | Wiring Devices | |
| 26 51 00 | Interior Lighting | |
| DIVISION 27 | COMMUNICATIONS | $0.00 |
| 27 05 11 | Requirements for Communications Installations | |
| 27 05 26 | Grounding and Bonding for Communications Systems | |
| 27 05 33 | Raceways and Boxes for Communications Systems | |
| 27 10 00 | Control, Communication and Signal Wiring | |
| 27 11 00 | Communications Equipment Room Fittings | |
| 27 15 00 | Communications Structured Cabling | |
| 27 41 31 | Master Antenna Television Equipment and Systems | |
| DIVISION 28 | ELECTRONIC SAFETY AND SECURITY | $0.00 |
| 28 05 00 | Common Work Results for Electronic Safety and Security | |
| 28 05 13 | Conductors and Cables for Electronic Safety and Security | |
| 28 05 26 | Grounding and Bonding for Electronic Safety and Security | |
| 28 05 28.33 | Conduits and Backboxes for Electronic Safety and Security | |
| 28 13 00 | Physical Access Control System | |
| 28 31 00 | Fire Detection and Alarm | |
| DIVISION 32 | EXTERIOR IMPROVEMENTS | $0.00 |
| TOTALS | | | | |
| $0.00 | | | |
| TOTAL LABOR | | | | |
| | $0.00 | | |
| TOTAL MATERIALS | | | | |
| 6% | $0.00 | | |
| TAX FOR MATERIALS | | | | |
| | | $0.00 | |
| TOTAL EQUIPMENT | | | | |
| DIVISION GRAND TOTALS | | | | $0.00 |
| $0 | INSTRUCTIONS |
| DIVISION GRAND TOTALS | $0 | |
| TAX FOR MATERIALS | | 1. Contract breakdowns must include the applicable VA Medical Center, the date the proposal was provided to the VA, the job title, project number, and the solicitation number; |
| SUBTOTAL | $0 | |
| OVERHEAD | 10% | $0 | |
| PROFIT | 10% | $0 | 2. Lump sum price breakdowns will not be accepted. Lump sum price breakdowns are defined as a single price provided by the contractor for one division or subdivision when each division or subdivision can be broken down by price to a greater degree; |
| BOND/FEE | 3% | $0 | 3. Divisions must still be listed even if not applicable to the construction requirement; |
| PERMITS/LICENSES | | | |
GRAND TOTAL $0 4. The template above does not include all possible divisions or subdivisions needed for the fictitious requirement referenced above. It is only provided as an example of what would be acceptable to the VA Network Contracting Office 9 -Construction Team as of 6-30-2016. Contractors shall provide all prices for each categorical column above and break down each specific division to the greatest degree possible, similar to what is referenced above. Utilizing this template in the contractor's proposal does not in any way require the Government to accept any subsequent price breakdown that is provided by the contractor or prevent the Government from requesting a further price breakdown. Therefore, it is in the Governments and contractor’s best interest to provide a thorough price breakdown initially; and
5. This template, or another template that would be provide the same kind of information referenced above, is required for all proposals provided to the VA Network Contracting Office 9 - Construction as of 6-30-2016.
Sheet3