36C24918R0366-0001004.pdf
PDF 3 MB Posted
- Solicitation number
- 36C24918R0366
About this file
36C24918R0366 0001 603-17-801 Specifications OR Anesthesia Supply Heads Spec Combined-REVISED 06052018.pdf
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C24918C0182-000.docx | DOCX document | |
| 36C24918R0366-0005000.docx | DOCX document | |
| 36C24918R0366-0004000.docx | DOCX document | |
| 36C24918R0366-0004002.pdf | ||
| 36C24918R0366-0004001.pdf | ||
| 36C24918R0366-0003000.docx | DOCX document | |
| 36C24918R0366-0003001.pdf | ||
| 36C24918R0366-0002002.docx | DOCX document | |
| 36C24918R0366-0001001.pdf | ||
| 36C24918R0366-0001000.docx | DOCX document | |
| 36C24918R0366-0001003.pdf | ||
| 36C24918R0366-0001002.xlsx | XLSX spreadsheet | |
| 36C24918R0366-005.pdf | ||
| 36C24918R0366-000.docx | DOCX document |
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Robley Rex VA Medical Center
Louisville, Kentucky
O.R. Anesthesia Supply Heads
603-17-801
08-01-17
00 01 10-1
DEPARTMENT OF VETERANS AFFAIRS
VHA MASTER SPECIFICATIONS
TABLE OF CONTENTS
Section 00 01 10
DIVISION 00 - SPECIAL SECTIONS DATE
00 01 15 List of Drawing Sheets 07-15
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 General Requirements (included in body of solicitation) 11-15
01 32 16.15 Project Schedules (Small Projects – Design/Bid/Build 04-13
01 33 23 Shop Drawings, Product Data, and Samples 05-17
01 35 26 Safety Requirements 02-17
01 42 19 Reference Standards 05-16
01 57 19 Temporary Environmental Controls 01-11
01 58 16 Temporary Interior Signage 07-15
01 74 19 Construction Waste Management 09-13
01 81 13 Sustainable Construction Requirements 09-15
DIVISION 02 – EXISTING CONDITIONS
02 41 00 Demolition 08-17
02 82 13.13 Glovebag Asbestos Abatement 09-15
DIVISION 05 – METALS
05 12 00 Structural Steel Framing 02-16
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 71 00 Roof Specialties 10-15
07 84 00 Firestopping 02-16
07 92 00 Joint Sealants 10-15
DIVISION 08 - OPENINGS
08 31 13 Access Doors and Frames 02-16
DIVISION 09 – FINISHES
09 22 16 Non-Structural Metal Framing 05-16
09 29 00 Gypsum Board 11-14
09 91 00 Painting 01-16
DIVISION 21- FIRE SUPPRESSION
21 13 13 Wet-Pipe Sprinkler Systems 06-15
DIVISION 22 – PLUMBING
22 05 11 Common Work Results for Plumbing 07-16
22 05 19 Meters and Gages for Plumbing Piping 09-15
22 05 23 General-Duty Valves for Plumbing Piping 09-15
22 07 11 Plumbing Insulation 09-15
22 62 00 Vacuum Systems for Laboratory and Healthcare Facilities 09-15
22 63 00 Gas Systems for Laboratory and Healthcare Facilities 09-15
O.R. Anesthesia Supply Heads
603-17-801
08-01-17
00 01 10-2
DIVISION 23 – HEATING, VENTILATING, AND AIR
CONDITIONING (HVAC)
23 05 11 Common Work Results for HVAC 08-17
23 05 93 Testing, Adjusting, and Balancing for HVAC 02-15
23 31 00 HVAC Ducts and Casings 03-13
23 37 00 Air Outlets and Inlets 02-15
DIVISION 26 – ELECTRICAL
26 05 11 Requirements for Electrical Installations 01-16
26 05 19 Low-Voltage Electrical Power Conductors and Cables 01-17
26 05 26 Grounding and Bonding for Electrical Systems 01-17
26 05 33 Raceway and Boxes for Electrical Systems 05-14
26 09 23 Lighting Controls 05-14
26 20 11 Isolated Power Systems 07-15
26 24 16 Panelboards 05-14
26 27 26 Wiring Devices 01-16
26 29 21 Enclosed Switches and Circuit Breakers 01-17
26 35 26 Harmonic Filters 08-14
26 43 13 Surge Protective Devices 01-17
26 51 00 Interior Lighting 08-14
DIVISION 27 – COMMUNICATIONS
27 05 11 Requirements for Communications Installations 06-15
27 05 26 Grounding and Bonding for Communications Systems 06-15
27 05 33 Raceways and Boxes for Communications Systems 06-15
27 10 00 Control, Communication and Signal Wiring 06-15
27 15 00 Communications Structured Cabling 01-16
O.R. Anesthesia Supply Heads
603-17-801
07-01-15
00 01 15 - 1
SECTION 00 01 15
LIST OF DRAWING SHEETS
The drawings listed below accompanying this specification form a part of the contract.
GENERAL
GI001 COVER SHEET
GI002 ABBREVIATIONS AND SYMBOLS
GI003 INFECTION CONTROL CONSTRUCTION PERMIT
GI004 CONSTRUCTION DETAILS
GI100 BASEMENT THRU THIRD FLOOR PHASING PLAN
GI101 FOURTH FLOOR PHASING PLAN
GI102 ROOF PHASING PLAN
GI200 BASEMENT THRU THIRD FLOOR INFECTION AND DUST CONTROL PLAN
GI201 ROOF INFECTION AND DUST CONTROL PLAN
GI202 FOURTH FLOOR INFECTION AND DUST CONTROL PLAN
GI203 ENLARGED OR-6 INFECTION AND DUST CONTROL PLAN
GI204 ENLARGED OR-5 INFECTION AND DUST CONTROL PLAN
GI205 ENLARGED OR-4 AND OR-3 INFECTION AND DUST CONTROL PLAN
GI206 ENLARGED OR-2 AND OR-1 INFECTION AND DUST CONTROL PLAN
GI207 ENLARGED SPECIAL GU (B-425) INFECTION AND DUST CONTROL PLAN
ARCHITECTURAL
AD100 BASEMENT THRU THIRD FLOOR DEMOLITION PLAN
AD200 REFLECTED CEILING/FLOOR PLAN DEMOLITION - FOURTH FLOOR
AD201 ENLARGED OR-6 REFLECTED CEILING/FLOOR PLAN DEMOLITION
AD202 ENLARGED OR-5 REFLECTED CEILING/FLOOR PLAN DEMOLITION
AD203 ENLARGED OR-4 AND OR-3 REFLECTED CEILING/FLOOR PLAN DEMOLITION
AD204 ENLARGED OR-2 AND OR-1 REFLECTED CEILING/FLOOR PLAN DEMOLITION
AD205 ENLARGED SPECIAL GU (B-425) AND ELECTRICAL (B-403) REFLECTED
CEILING/FLOOR PLAN DEMOLITION
AE100 BASEMENT THRU THIRD FLOOR PLAN REVISED
AE200 REFLECTED CEILING/FLOOR PLAN REVISED - FOURTH FLOOR
AE201 ENLARGED OR-6 REFLECTED CEILING/FLOOR PLAN REVISED
AE202 ENLARGED OR-5 REFLECTED CEILING/FLOOR PLAN REVISED
O.R. Anesthesia Supply Heads
603-17-801
00 01 15 - 2
AE203 ENLARGED OR-4 AND OR-3 REFLECTED CEILING/FLOOR PLAN REVISED
AE204 ENLARGED OR-2 AND OR-1 REFLECTED CEILING/FLOOR PLAN REVISED
AE205 ENLARGED SPECIAL GU (B-425) AND ELECTRICAL (B-403) REFLECTED
CEILING/FLOOR PLAN REVISED
AE301 EQUIPMENT CEILING PLAN - FOURTH FLOOR
AE401 ROOF PLAN
AE601 STERIS - REFERENCE DOCUMENTS
AE602 STERIS - REFERENCE DOCUMENTS
AE603 STERIS - REFERENCE DOCUMENTS
STRUCTURAL
S-101 PARTIAL 5TH FLOOR FRAMING PLAN AND DETAILS
S-301 JOIST REINFORCING SCHEDULE AND DETAILS
FIRE PROTECTION
FX104 FOURTH FLOOR FIRE PROTECTION PLAN
MECHANICAL
MO001 MECHANICAL NOTES AND ABBREVIATIONS
MD200 FOURTH FLOOR DEMOLITION HVAC PLAN - OVERALL
MD201 ENLARGED OR-6 HVAC PLAN - DEMOLITION
MD202 ENLARGED OR-5 HVAC PLAN - DEMOLITION
MD203 ENLARGED OR-4 AND OR-3 HVAC PLAN - DEMOLITION
MD204 ENLARGED OR-2 AND OR-1 HVAC PLAN - DEMOLITION
MD205 ENLARGED SPECIAL GU AND ELECTRICAL HVAC PLAN - DEMOLITION
MH200 FOURTH FLOOR HVAC PLAN - OVERALL
MH201 ENLARGED OR-6 HVAC PLAN - REVISED
MH202 ENLARGED OR-5 HVAC PLAN - REVISED
MH203 ENLARGED OR-4 AND OR-3 HVAC PLAN - REVISED
MH204 ENLARGED OR-2 AND OR-1 HVAC PLAN - REVISED
MH205 ENLARGED SPECIAL GU AND ELECTRICAL MECHANICAL PLAN - REVISED
O.R. Anesthesia Supply Heads
603-17-801
00 01 15 - 3
MH400 FOURTH FLOOR HVAC DUCT PLAN - OVERALL
MH401 MECHANICAL ROOF PLAN - REVISED
PLUMBING
PO001 PLUMBING SCHEDULE AND ABBREVIATIONS
PD200 FOURTH FLOOR DEMOLITION PLUMBING PLAN - OVERALL
PD201 ENLARGED OR-6 PLUMBING PLAN - DEMOLITION
PD202 ENLARGED OR-5 PLUMBING PLAN - DEMOLITION
PD203 ENLARGED OR-4 AND OR-3 PLUMBING PLAN - DEMOLITION
PD204 ENLARGED OR-2 AND OR-1 PLUMBING PLAN - DEMOLITION
PD205 ENLARGED SPECIAL GU AND ELECTRICAL PLUMBING PLAN - DEMOLITION
PP200 FOURTH FLOOR PLUMBING PLAN - OVERALL
PP201 ENLARGED OR-6 PLUMBING PLAN - REVISED
PP202 ENLARGED OR-5 PLUMBING PLAN - REVISED
PP203 ENLARGED OR-4 AND OR-3 PLUMBING PLAN - REVISED
PP204 ENLARGED OR-2 AND OR-1 PLUMBING PLAN - REVISED
PP205 ENLARGED SPECIAL GU AND ELECTRICAL PLAN - REVISED
ELECTRICAL
EQ001 ELECTRICAL SYMBOLS AND ABBREVIATIONS
EQ002 ELECTRICAL SCHEDULES AND DETAILS
EQ003 ELECTRICAL DETAILS
ED200 FOURTH FLOOR DEMOLITION ELECTRICAL PLAN - OVERALL
ED201 ENLARGED OR-6 ELECTRICAL PLAN - DEMOLITION
ED202 ENLARGED OR-5 ELECTRICAL PLAN - DEMOLITION
ED203 ENLARGED OR-4 AND OR-3 ELECTRICAL PLAN - DEMOLITION
ED204 ENLARGED OR-2 AND OR-1 ELECTRICAL PLAN - DEMOLITION
ED205 ENLARGED SPECIAL GU (B-425) AND ELECTRICAL (B-403) ELECTRICAL PLAN -
DEMOLITION
EL200 FOURTH FLOOR LIGHTING PLAN - OVERALL
EL201 ENLARGED OR-6 LIGHTING PLAN - REVISED
O.R. Anesthesia Supply Heads
603-17-801
00 01 15 - 4
EL202 ENLARGED OR-5 LIGHTING PLAN - REVISED
EL203 ENLARGED OR-4 AND OR-3 LIGHTING PLAN - REVISED
EL203-A ENLARGED OR-4 AND OR-3 LIGHTING PLAN - REVISED (ALTERNATE #2)
EL204 ENLARGED OR-2 AND OR-1 LIGHTING PLAN - REVISED
EL205 ENLARGED SPECIAL GU (B-425) AND ELECTRICAL (B-403) LIGHTING PLAN -
REVISED
EP100 SUB-BASEMENT OVERALL PLAN
EP101 FOURTH PARTIAL BASEMENT THROUGH THIRD FLOOR POWER PLAN - OVERALL
EP200 FOURTH FLOOR POWER PLAN - OVERALL
EP201 ENLARGED OR-6 POWER PLAN - REVISED
EP202 ENLARGED OR-5 POWER PLAN - REVISED
EP203 ENLARGED OR-4 AND OR-3 POWER PLAN - REVISED
EP204 ENLARGED OR-2 AND OR-1 POWER PLAN - REVISED
EP205 ENLARGED SPECIAL GU (B-425) AND ELECTRICAL ROOM POWER PLAN - REVISED
EP301 OVERALL 5TH FLOOR POWER PLAN
EP401 ELECTRICAL SCHEDULES
EP501 ELECTRICAL ONE-LINE DIAGRAM
EX200 FOURTH FLOOR LOW-VOLTAGE PLAN - OVERALL
- - - END - - -
O.R. Anesthesia Supply Heads
603-17-801
02-01-15
01 32 16.15 - 1
PART 1- GENERAL
1.1 DESCRIPTION:
SECTION 01 32 16.15
PROJECT SCHEDULES
(SMALL PROJECTS – DESIGN/BID/BUILD)
A. The Contractor shall develop a Critical Path Method (CPM) plan and schedule demonstrating fulfillment of the contract requirements
(Project Schedule), and shall keep the Project Schedule up-to-date in accordance with the requirements of this section and shall utilize the plan for scheduling, coordinating and monitoring work under this contract (including all activities of subcontractors, equipment vendors and suppliers). Conventional Critical Path Method (CPM) technique shall be utilized to satisfy both time and cost applications.
1.2 CONTRACTOR'S REPRESENTATIVE:
A. The Contractor shall designate an authorized representative responsible for the Project Schedule including preparation, review and progress reporting with and to the Contracting Officer's Representative (COR).
B. The Contractor's representative shall have direct project control and complete authority to act on behalf of the Contractor in fulfilling the requirements of this specification section.
C. The Contractor’s representative shall have the option of developing the project schedule within their organization or to engage the services of an outside consultant. If an outside scheduling consultant is utilized, Section 1.3 of this specification will apply.
1.3 CONTRACTOR'S CONSULTANT:
A. The Contractor shall submit a qualification proposal to the COR, within
10 days of bid acceptance. The qualification proposal shall include:
1. The name and address of the proposed consultant.
2. Information to show that the proposed consultant has the qualifications to meet the requirements specified in the preceding paragraph.
3. A representative sample of prior construction projects, which the proposed consultant has performed complete project scheduling services. These representative samples shall be of similar size and scope.
B. The Contracting Officer has the right to approve or disapprove the proposed consultant, and will notify the Contractor of the VA decision within seven calendar days from receipt of the qualification proposal.
In case of disapproval, the Contractor shall resubmit another
O.R. Anesthesia Supply Heads
603-17-801
01 32 16.15 - 2 consultant within 10 calendar days for renewed consideration. The
Contractor shall have their scheduling consultant approved prior to submitting any schedule for approval.
1.4 COMPUTER PRODUCED SCHEDULES
A. The contractor shall provide monthly, to the Department of Veterans
Affairs (VA), all computer-produced time/cost schedules and reports generated from monthly project updates. This monthly computer service will include: three copies of up to five different reports (inclusive of all pages) available within the user defined reports of the scheduling software approved by the Contracting Officer; a hard copy listing of all project schedule changes, and associated data, made at the update and an electronic file of this data; and the resulting monthly updated schedule in PDM format. These must be submitted with and substantively support the contractor’s monthly payment request and the signed look ahead report. The COR shall identify the five different report formats that the contractor shall provide.
B. The contractor shall be responsible for the correctness and timeliness of the computer-produced reports. The Contractor shall also responsible for the accurate and timely submittal of the updated project schedule and all CPM data necessary to produce the computer reports and payment request that is specified.
C. The VA will report errors in computer-produced reports to the
Contractor’s representative within ten calendar days from receipt of reports. The Contractor shall reprocess the computer-produced reports and associated diskette(s), when requested by the Contracting Officer’s representative, to correct errors which affect the payment and schedule for the project.
1.5 THE COMPLETE PROJECT SCHEDULE SUBMITTAL
A. Within 45 calendar days after receipt of Notice to Proceed, the
Contractor shall submit for the Contracting Officer's review; three blue line copies of the interim schedule on sheets of paper 765 x 1070 mm (30 x 42 inches) and an electronic file in the previously approved
CPM schedule program. The submittal shall also include three copies of a computer-produced activity/event ID schedule showing project duration; phase completion dates; and other data, including event cost.
Each activity/event on the computer-produced schedule shall contain as a minimum, but not limited to, activity/event ID, activity/event description, duration, budget amount, early start date, early finish
01 32 16.15 - 3
Louisville, Kentucky
O.R. Anesthesia Supply Heads
603-17-801 date, late start date, late finish date and total float. Work activity/event relationships shall be restricted to finish-to-start or start-to-start without lead or lag constraints. Activity/event date constraints, not required by the contract, will not be accepted unless submitted to and approved by the Contracting Officer. The contractor shall make a separate written detailed request to the Contracting
Officer identifying these date constraints and secure the Contracting
Officer’s written approval before incorporating them into the network diagram. The Contracting Officer’s separate approval of the Project
Schedule shall not excuse the contractor of this requirement. Logic events (non-work) will be permitted where necessary to reflect proper logic among work events, but must have zero duration. The complete working schedule shall reflect the Contractor's approach to scheduling the complete project. The final Project Schedule in its original form shall contain no contract changes or delays which may have been incurred during the final network diagram development period and shall reflect the entire contract duration as defined in the bid documents.
These changes/delays shall be entered at the first update after the final Project Schedule has been approved. The Contractor should provide their requests for time and supporting time extension analysis for contract time as a result of contract changes/delays, after this update, and in accordance with Article, ADJUSTMENT OF CONTRACT
COMPLETION.
D. Within 30 calendar days after receipt of the complete project interim
Project Schedule and the complete final Project Schedule, the
Contracting Officer or his representative, will do one or both of the following:
1. Notify the Contractor concerning his actions, opinions, and objections.
2. A meeting with the Contractor at or near the job site for joint review, correction or adjustment of the proposed plan will be scheduled if required. Within 14 calendar days after the joint review, the Contractor shall revise and shall submit three blue line copies of the revised Project Schedule, three copies of the revised computer-produced activity/event ID schedule and a revised electronic file as specified by the Contracting Officer. The revised
01 32 16.15 - 4
Louisville, Kentucky
O.R. Anesthesia Supply Heads submission will be reviewed by the Contracting Officer and, if found to be as previously agreed upon, will be approved.
E. The approved baseline schedule and the computer-produced schedule(s) generated there from shall constitute the approved baseline schedule until subsequently revised in accordance with the requirements of this section.
1.6 WORK ACTIVITY/EVENT COST DATA
A. The Contractor shall cost load all work activities/events except procurement activities. The cumulative amount of all cost loaded work activities/events (including alternates) shall equal the total contract price. Prorate overhead, profit and general conditions on all work activities/events for the entire project length. The contractor shall generate from this information cash flow curves indicating graphically the total percentage of work activity/event dollar value scheduled to be in place on early finish, late finish. These cash flow curves will be used by the Contracting Officer to assist him in determining approval or disapproval of the cost loading. Negative work activity/event cost data will not be acceptable, except on VA issued contract changes.
B. The Contractor shall cost load work activities/events for guarantee period services, test, balance and adjust various systems in accordance with the provisions in Article, FAR 52.232 – 5 (PAYMENT UNDER
FIXED-PRICE CONSTRUCTION CONTRACTS) and VAAR 852.236 – 83 (PAYMENT
UNDER FIXED-PRICE CONSTRUCTION CONTRACTS).
C. In accordance with FAR 52.236 – 1 (PERFORMANCE OF WORK BY THE
CONTRACTOR) and VAAR 852.236 – 72 (PERFORMANCE OF WORK BY THE
CONTRACTOR), the Contractor shall submit, simultaneously with the cost per work activity/event of the construction schedule required by this
Section, a responsibility code for all activities/events of the project for which the Contractor's forces will perform the work.
D. The Contractor shall cost load work activities/events for all BID ITEMS including ASBESTOS ABATEMENT. The sum of each BID ITEM work shall equal the value of the bid item in the Contractors' bid.
1.7 PROJECT SCHEDULE REQUIREMENTS
A. Show on the project schedule the sequence of work activities/events required for complete performance of all items of work. The Contractor
Shall:
1. Show activities/events as:
01 32 16.15 - 5
Louisville, Kentucky
O.R. Anesthesia Supply Heads
a. Contractor's time required for submittal of shop drawings, templates, fabrication, delivery and similar pre-construction work.
b. Contracting Officer's and Architect-Engineer's review and approval of shop drawings, equipment schedules, samples, template, or similar items.
c. Interruption of VA Facilities utilities, delivery of Government furnished equipment, and rough-in drawings, project phasing and any other specification requirements.
d. Test, balance and adjust various systems and pieces of equipment, maintenance and operation manuals, instructions and preventive maintenance tasks.
e. VA inspection and acceptance activity/event with a minimum duration of five work days at the end of each phase and immediately preceding any VA move activity/event required by the contract phasing for that phase.
2. Show not only the activities/events for actual construction work for each trade category of the project, but also trade relationships to indicate the movement of trades from one area, floor, or building, to another area, floor, or building, for at least five trades who are performing major work under this contract.
3. Break up the work into activities/events of a duration no longer than 20 work days each or one reporting period, except as to non-construction activities/events (i.e., procurement of materials, delivery of equipment, concrete and asphalt curing) and any other activities/events for which the COR may approve the showing of a longer duration. The duration for VA approval of any required submittal, shop drawing, or other submittals will not be less than
20 work days.
4. Describe work activities/events clearly, so the work is readily identifiable for assessment of completion. Activities/events labeled
"start," "continue," or "completion," are not specific and will not be allowed. Lead and lag time activities will not be acceptable.
5. The schedule shall be generally numbered in such a way to reflect either discipline, phase or location of the work.
B. The Contractor shall submit the following supporting data in addition to the project schedule:
01 32 16.15 - 6
Louisville, Kentucky
O.R. Anesthesia Supply Heads
1. The appropriate project calendar including working days and holidays.
2. The planned number of shifts per day.
3. The number of hours per shift.
Failure of the Contractor to include this data shall delay the review of the submittal until the Contracting Officer is in receipt of the missing data.
C. To the extent that the Project Schedule or any revised Project Schedule shows anything not jointly agreed upon, it shall not be deemed to have been approved by the COR. Failure to include any element of work required for the performance of this contract shall not excuse the
Contractor from completing all work required within any applicable completion date of each phase regardless of the COR’s approval of the
Project Schedule.
D. Compact Disk Requirements and CPM Activity/Event Record Specifications:
Submit to the VA an electronic file(s) containing one file of the data required to produce a schedule, reflecting all the activities/events of the complete project schedule being submitted.
1.8 PAYMENT TO THE CONTRACTOR:
A. Monthly, the contractor shall submit an application and certificate for payment using VA Form 10-6001a reflecting updated schedule activities and cost data in accordance with the provisions of the following
Article, PAYMENT AND PROGRESS REPORTING, as the basis upon which progress payments will be made pursuant to Article, FAR 52.232 – 5
(PAYMENT UNDER FIXED-PRICE CONSTRUCTION CONTRACTS) and VAAR 852.236 –
83 (PAYMENT UNDER FIXED-PRICE CONSTRUCTION CONTRACTS). The Contractor shall be entitled to a monthly progress payment upon approval of estimates as determined from the currently approved updated project schedule. Monthly payment requests shall include: a listing of all agreed upon project schedule changes and associated data; and an electronic file (s) of the resulting monthly updated schedule.
B. Approval of the Contractor’s monthly Application for Payment shall be contingent, among other factors, on the submittal of a satisfactory monthly update of the project schedule.
1.9 PAYMENT AND PROGRESS REPORTING
A. Monthly schedule update meetings will be held on dates mutually agreed to by the COR and the Contractor. Contractor and their CPM consultant
(if applicable) shall attend all monthly schedule update meetings. The
01 32 16.15 - 7
Louisville, Kentucky
O.R. Anesthesia Supply Heads
Contractor shall accurately update the Project Schedule and all other data required and provide this information to the COR three work days in advance of the schedule update meeting. Job progress will be reviewed to verify:
1. Actual start and/or finish dates for updated/completed activities/events.
2. Remaining duration for each activity/event started, or scheduled to start, but not completed.
3. Logic, time and cost data for change orders, and supplemental agreements that are to be incorporated into the Project Schedule.
4. Changes in activity/event sequence and/or duration which have been made, pursuant to the provisions of following Article, ADJUSTMENT OF
CONTRACT COMPLETION.
5. Completion percentage for all completed and partially completed activities/events.
6. Logic and duration revisions required by this section of the specifications.
7. Activity/event duration and percent complete shall be updated independently.
B. After completion of the joint review, the contractor shall generate an updated computer-produced calendar-dated schedule and supply the
Contracting Officer’s representative with reports in accordance with the Article, COMPUTER PRODUCED SCHEDULES, specified.
C. After completing the monthly schedule update, the contractor’s representative or scheduling consultant shall rerun all current period contract change(s) against the prior approved monthly project schedule.
The analysis shall only include original workday durations and schedule logic agreed upon by the contractor and COR for the contract change(s).
When there is a disagreement on logic and/or durations, the Contractor shall use the schedule logic and/or durations provided and approved by the COR. After each rerun update, the resulting electronic project schedule data file shall be appropriately identified and submitted to the VA in accordance to the requirements listed in articles 1.4 and
1.7. This electronic submission is separate from the regular monthly project schedule update requirements and shall be submitted to the COR within fourteen (14) calendar days of completing the regular schedule update. Before inserting the contract changes durations, care must be
01 32 16.15 - 8
Louisville, Kentucky
O.R. Anesthesia Supply Heads taken to ensure that only the original durations will be used for the analysis, not the reported durations after progress. In addition, once the final network diagram is approved, the contractor must recreate all manual progress payment updates on this approved network diagram and associated reruns for contract changes in each of these update periods as outlined above for regular update periods. This will require detailed record keeping for each of the manual progress payment updates.
D. Following approval of the CPM schedule, the VA, the General Contractor, its approved CPM Consultant, COR office representatives, and all subcontractors needed, as determined by the SRE, shall meet to discuss the monthly updated schedule. The main emphasis shall be to address work activities to avoid slippage of project schedule and to identify any necessary actions required to maintain project schedule during the reporting period. The Government representatives and the Contractor should conclude the meeting with a clear understanding of those work and administrative actions necessary to maintain project schedule status during the reporting period. This schedule coordination meeting will occur after each monthly project schedule update meeting utilizing the resulting schedule reports from that schedule update. If the project is behind schedule, discussions should include ways to prevent further slippage as well as ways to improve the project schedule status, when appropriate.
1.10 RESPONSIBILITY FOR COMPLETION
A. If it becomes apparent from the current revised monthly progress schedule that phasing or contract completion dates will not be met, the
Contractor shall execute some or all of the following remedial actions:
1. Increase construction manpower in such quantities and crafts as necessary to eliminate the backlog of work.
2. Increase the number of working hours per shift, shifts per working day, working days per week, the amount of construction equipment, or any combination of the foregoing to eliminate the backlog of work.
3. Reschedule the work in conformance with the specification requirements.
B. Prior to proceeding with any of the above actions, the Contractor shall notify and obtain approval from the COR for the proposed schedule changes. If such actions are approved, the representative schedule revisions shall be incorporated by the Contractor into the Project
01 32 16.15 - 9
Louisville, Kentucky
O.R. Anesthesia Supply Heads
Schedule before the next update, at no additional cost to the
Government.
1.11 CHANGES TO THE SCHEDULE
A. Within 30 calendar days after VA acceptance and approval of any updated project schedule, the Contractor shall submit a revised electronic file
(s) and a list of any activity/event changes including predecessors and successors for any of the following reasons:
1. Delay in completion of any activity/event or group of activities/events, which may be involved with contract changes, strikes, unusual weather, and other delays will not relieve the
Contractor from the requirements specified unless the conditions are shown on the CPM as the direct cause for delaying the project beyond the acceptable limits.
2. Delays in submittals, or deliveries, or work stoppage are encountered which make rescheduling of the work necessary.
3. The schedule does not represent the actual prosecution and progress of the project.
4. When there is, or has been, a substantial revision to the activity/event costs regardless of the cause for these revisions.
B. CPM revisions made under this paragraph which affect the previously approved computer-produced schedules for Government furnished equipment, vacating of areas by the VA Facility, contract phase(s) and sub phase(s), utilities furnished by the Government to the Contractor, or any other previously contracted item, shall be furnished in writing to the Contracting Officer for approval.
C. Contracting Officer's approval for the revised project schedule and all relevant data is contingent upon compliance with all other paragraphs of this section and any other previous agreements by the Contracting
Officer or the VA representative.
D. The cost of revisions to the project schedule resulting from contract changes will be included in the proposal for changes in work as specified in FAR 52.243 – 4 (Changes) and VAAR 852.236 – 88 (Changes –
Supplemental), and will be based on the complexity of the revision or contract change, man hours expended in analyzing the change, and the total cost of the change.
E. The cost of revisions to the Project Schedule not resulting from contract changes is the responsibility of the Contractor.
01 32 16.15 - 10
Louisville, Kentucky
O.R. Anesthesia Supply Heads
1.12 ADJUSTMENT OF CONTRACT COMPLETION
A. The contract completion time will be adjusted only for causes specified in this contract. Request for an extension of the contract completion date by the Contractor shall be supported with a justification, CPM data and supporting evidence as the COR may deem necessary for determination as to whether or not the Contractor is entitled to an extension of time under the provisions of the contract. Submission of proof based on revised activity/event logic, durations (in work days) and costs is obligatory to any approvals. The schedule must clearly display that the Contractor has used, in full, all the float time available for the work involved in this request. The Contracting
Officer's determination as to the total number of days of contract extension will be based upon the current computer-produced calendar-dated schedule for the time period in question and all other relevant information.
B. Actual delays in activities/events which, according to the computer- produced calendar-dated schedule, do not affect the extended and predicted contract completion dates shown by the critical path in the network, will not be the basis for a change to the contract completion date. The Contracting Officer will within a reasonable time after receipt of such justification and supporting evidence, review the facts and advise the Contractor in writing of the Contracting Officer's decision.
C. The Contractor shall submit each request for a change in the contract completion date to the Contracting Officer in accordance with the provisions specified under FAR 52.243 – 4 (Changes) and VAAR 852.236 –
88 (Changes – Supplemental). The Contractor shall include, as a part of each change order proposal, a sketch showing all CPM logic revisions, duration (in work days) changes, and cost changes, for work in question and its relationship to other activities on the approved network diagram.
D. All delays due to non-work activities/events such as RFI’s, WEATHER, STRIKES, and similar non-work activities/events shall be analyzed on a month by month basis.
- - - E N D - - -
O.R. Anesthesia Supply Heads
01 33 23 - 1
SECTION 01 33 23
SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES
1-1. Refer to Articles titled SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION
(FAR 52.236-21) and, SPECIAL NOTES (VAAR 852.236-91), in GENERAL
CONDITIONS.
1-2. For the purposes of this contract, samples (including laboratory samples to be tested), test reports, certificates, and manufacturers' literature and data shall also be subject to the previously referenced requirements. The following text refers to all items collectively as
SUBMITTALS.
1-3. Submit for approval, all of the items specifically mentioned under the separate sections of the specification, with information sufficient to evidence full compliance with contract requirements. Materials, fabricated articles and the like to be installed in permanent work shall equal those of approved submittals. After an item has been approved, no change in brand or make will be permitted unless:
A. Satisfactory written evidence is presented to, and approved by
Contracting Officer, that manufacturer cannot make scheduled delivery of approved item or;
B. Item delivered has been rejected and substitution of a suitable item is an urgent necessity or;
C. Other conditions become apparent which indicates approval of such substitute item to be in best interest of the Government.
1-4. Forward submittals in sufficient time to permit proper consideration and approval action by Government. Time submission to assure adequate lead time for procurement of contract - required items. Delays attributable to untimely and rejected submittals (including any laboratory samples to be tested) will not serve as a basis for extending contract time for completion.
1-5. Submittals will be reviewed for compliance with contract requirements by Architect-Engineer, and action thereon will be taken by COR on behalf of the Contracting Officer.
1-6. Upon receipt of submittals, Architect-Engineer will assign a file number thereto. Contractor, in any subsequent correspondence, shall refer to this file and identification number to expedite replies relative to previously approved or disapproved submittals.
1-7. The Government reserves the right to require additional submittals, whether or not particularly mentioned in this contract. If additional submittals beyond those required by the contract are furnished pursuant
O.R. Anesthesia Supply Heads
01 33 23 - 2 to request therefor by Contracting Officer, adjustment in contract price and time will be made in accordance with Articles titled CHANGES
(FAR 52.243-4) and CHANGES - SUPPLEMENT (VAAR 852.236-88) of the
GENERAL CONDITIONS.
1-8. Schedules called for in specifications and shown on shop drawings shall be submitted for use and information of Department of Veterans Affairs and Architect-Engineer. However, the Contractor shall assume responsibility for coordinating and verifying schedules. The
Contracting Officer and Architect- Engineer assumes no responsibility for checking schedules or layout drawings for exact sizes, exact numbers and detailed positioning of items.
1-9. Submittals must be submitted by Contractor only and shipped prepaid.
Contracting Officer assumes no responsibility for checking quantities or exact numbers included in such submittals.
A. Submit samples in single units unless otherwise specified. Submit shop drawings, schedules, manufacturers' literature and data, and certificates in quadruplicate, except where a greater number is specified.
B. Submittals will receive consideration only when covered by a transmittal letter signed by Contractor. Letter shall be sent via first class mail and shall contain the list of items, name of Medical Center, name of Contractor, contract number, applicable specification paragraph numbers, applicable drawing numbers (and other information required for exact identification of location for each item), manufacturer and brand, ASTM or Federal Specification Number (if any) and such additional information as may be required by specifications for particular item being furnished. In addition, catalogs shall be marked to indicate specific items submitted for approval.
1. A copy of letter must be enclosed with items, and any items received without identification letter will be considered "unclaimed goods" and held for a limited time only.
2. Each sample, certificate, manufacturers' literature and data shall be labeled to indicate the name and location of the Medical Center, name of Contractor, manufacturer, brand, contract number and ASTM or
Federal Specification Number as applicable and location(s) on project.
01 33 23 - 3
Louisville, Kentucky
O.R. Anesthesia Supply Heads
3. Required certificates shall be signed by an authorized representative of manufacturer or supplier of material, and by
Contractor.
C. In addition to complying with the applicable requirements specified in preceding Article 1.9, samples which are required to have Laboratory
Tests (those preceded by symbol "LT" under the separate sections of the specification shall be tested, at the expense of Contractor, in a commercial laboratory approved by Contracting Officer.
1. Laboratory shall furnish Contracting Officer with a certificate stating that it is fully equipped and qualified to perform intended work, is fully acquainted with specification requirements and intended use of materials and is an independent establishment in no way connected with organization of Contractor or with manufacturer or supplier of materials to be tested.
2. Certificates shall also set forth a list of comparable projects upon which laboratory has performed similar functions during past five years.
3. Samples and laboratory tests shall be sent directly to approved commercial testing laboratory.
4. Contractor shall send a copy of transmittal letter to both COR and to Architect-Engineer simultaneously with submission of material to a commercial testing laboratory.
5. Contractor shall forward a copy of transmittal letter to COR simultaneously with submission to a commercial testing laboratory.
6. Laboratory test reports shall be sent directly to COR for appropriate action.
7. Laboratory reports shall list contract specification test requirements and a comparative list of the laboratory test results.
When tests show that the material meets specification requirements, the laboratory shall so certify on test report.
8. Laboratory test reports shall also include a recommendation for approval or disapproval of tested item.
D. If submittal samples have been disapproved, resubmit new samples as soon as possible after notification of disapproval. Such new samples shall be marked "Resubmitted Sample" in addition to containing other previously specified information required on label and in transmittal letter.
01 33 23 - 4
Louisville, Kentucky
O.R. Anesthesia Supply Heads
E. Approved samples will be kept on file by the COR at the site until completion of contract, at which time such samples will be delivered to
Contractor as Contractor's property. Where noted in technical sections of specifications, approved samples in good condition may be used in their proper locations in contract work. At completion of contract, samples that are not approved will be returned to Contractor only upon request and at Contractor's expense. Such request should be made prior to completion of the contract. Disapproved samples that are not requested for return by Contractor will be discarded after completion of contract.
F. Submittal drawings (shop, erection or setting drawings) and schedules, required for work of various trades, shall be checked before submission by technically qualified employees of Contractor for accuracy, completeness and compliance with contract requirements. These drawings and schedules shall be stamped and signed by Contractor certifying to such check.
1. For each drawing required, submit one legible photographic paper or vellum reproducible.
2. Reproducible shall be full size.
3. Each drawing shall have marked thereon, proper descriptive title, including Medical Center location, project number, manufacturer's number, reference to contract drawing number, detail Section Number, and Specification Section Number.
4. A space 120 mm by 125 mm (4-3/4 by 5 inches) shall be reserved on each drawing to accommodate approval or disapproval stamp.
5. Submit drawings, ROLLED WITHIN A MAILING TUBE, fully protected for shipment.
6. One reproducible print of approved or disapproved shop drawings will be forwarded to Contractor.
7. When work is directly related and involves more than one trade, shop drawings shall be submitted to Architect-Engineer under one cover.
1-10. Samples (except laboratory samples), shop drawings, test reports, certificates and manufacturers' literature and data, shall be submitted for review to
Paradigm Engineers and Constructors
200 Envoy Circle, Suite 201
Louisville, KY 40299
O.R. Anesthesia Supply Heads
01 33 23 - 5
1-11. At the time of transmittal to the Architect-Engineer, the Contractor shall also send a copy of the complete submittal directly to the COR.
1-12. Samples (except laboratory samples) for approval shall be sent to
Architect-Engineer, in care of COR, VA Medical Center, COR Mr. Doug Foster
Email: Douglas.Foster@VA.gov
Robley Rex VAMC
800 Zorn Ave
Louisville, KY 40206
- - - E N D - - -mailto:Douglas.Foster@VA.gov
O.R. Anesthesia Supply Heads
603-17-801
02-01-17
01 35 26 -1
TABLE OF CONTENTS
SECTION 01 35 26
SAFETY REQUIREMENTS
1.1 APPLICABLE PUBLICATIONS
1.2 DEFINITIONS
1.3 REGULATORY REQUIREMENTS
1.4 ACCIDENT PREVENTION PLAN (APP)
1.5 ACTIVITY HAZARD ANALYSES (AHAs)
1.6 PRECONSTRUCTION CONFERENCE
1.7 “SITE SAFETY AND HEALTH OFFICER” (SSHO) and “COMPETENT PERSON” (CP)
1.8 TRAINING
1.9 INSPECTIONS
1.10 ACCIDENTS, OSHA 300 LOGS, AND MAN-HOURS
1.11 PERSONAL PROTECTIVE EQUIPMENT (PPE)
1.12 INFECTION CONTROL
1.13 TUBERCULOSIS SCREENING
1.14 FIRE SAFETY
1.15 ELECTRICAL
1.16 FALL PROTECTION
1.17 SCAFFOLDS AND OTHER WORK PLATFORMS
1.18 EXCAVATION AND TRENCHES .................... Error! Bookmark not defined.
1.19 CRANES
1.20 CONTROL OF HAZARDOUS ENERGY (LOCKOUT/TAGOUT)
1.21 CONFINED SPACE ENTRY
1.22 WELDING AND CUTTING
1.23 LADDERS
1.24 FLOOR & WALL OPENINGS
O.R. Anesthesia Supply Heads
603-17-801
01 35 26 -2
1.1 APPLICABLE PUBLICATIONS:
SECTION 01 35 26
SAFETY REQUIREMENTS
A. Latest publications listed below form part of this Article to extent referenced. Publications are referenced in text by basic designations only.
B. American Society of Safety Engineers (ASSE):
A10.1-2011...........Pre-Project & Pre-Task Safety and Health
Planning
A10.34-2012..........Protection of the Public on or Adjacent to
Construction Sites
A10.38-2013..........Basic Elements of an Employer’s Program to
Provide a Safe and Healthful Work Environment
American National Standard Construction and
Demolition Operations
C. American Society for Testing and Materials (ASTM):
E84-2013.............Surface Burning Characteristics of Building
Materials
D. The Facilities Guidelines Institute (FGI):
FGI Guidelines-2010Guidelines for Design and Construction of
Healthcare Facilities
E. National Fire Protection Association (NFPA):
10-2013..............Standard for Portable Fire Extinguishers
30-2012..............Flammable and Combustible Liquids Code
51B-2014.............Standard for Fire Prevention During Welding, Cutting and Other Hot Work
70-2014..............National Electrical Code
70B-2013.............Recommended Practice for Electrical Equipment
Maintenance
70E-2015 ............Standard for Electrical Safety in the Workplace
99-2012..............Health Care Facilities Code
241-2013.............Standard for Safeguarding Construction, Alteration, and Demolition Operations
F. The Joint Commission (TJC)
TJC Manual ..........Comprehensive Accreditation and Certification
Manual
G. U.S. Nuclear Regulatory Commission
10 CFR 20 ...........Standards for Protection Against Radiation
O.R. Anesthesia Supply Heads
603-17-801
01 35 26 -3
H. U.S. Occupational Safety and Health Administration (OSHA):
29 CFR 1904 .........Reporting and Recording Injuries & Illnesses
29 CFR 1910 .........Safety and Health Regulations for General
Industry
29 CFR 1926 .........Safety and Health Regulations for Construction
Industry
CPL 2-0.124..........Multi-Employer Citation Policy
I. VHA Directive 2005-007
1.2 DEFINITIONS:
A. Critical Lift. A lift with the hoisted load exceeding 75% of the crane’s maximum capacity; lifts made out of the view of the operator
(blind picks); lifts involving two or more cranes; personnel being hoisted; and special hazards such as lifts over occupied facilities, loads lifted close to power-lines, and lifts in high winds or where other adverse environmental conditions exist; and any lift which the crane operator believes is critical.
B. OSHA “Competent Person” (CP). One who is capable of identifying existing and predictable hazards in the surroundings and working conditions which are unsanitary, hazardous or dangerous to employees, and who has the authorization to take prompt corrective measures to eliminate them (see 29
CFR 1926.32(f)).
C. "Qualified Person" means one who, by possession of a recognized degree, certificate, or professional standing, or who by extensive knowledge, training and experience, has successfully demonstrated his ability to solve or resolve problems relating to the subject matter, the work, or the project.
D. High Visibility Accident. Any mishap which may generate publicity or high visibility.
E. Accident/Incident Criticality Categories:
No impact – near miss incidents that should be investigated but are not required to be reported to the VA;
Minor incident/impact – incidents that require first aid or result in minor equipment damage (less than $5000). These incidents must be investigated but are not required to be reported to the VA;
Moderate incident/impact – Any work-related injury or illness that results in:
1. Days away from work (any time lost after day of injury/illness onset);
O.R. Anesthesia Supply Heads
603-17-801
01 35 26 -4
2. Restricted work;
3. Transfer to another job;
4. Medical treatment beyond first aid;
5. Loss of consciousness;
6. A significant injury or illness diagnosed by a physician or other licensed health care professional, even if it did not result in (1) through (5) above or,
7. any incident that leads to major equipment damage (greater than $5000).
These incidents must be investigated and are required to be reported to the VA;
Major incident/impact – Any mishap that leads to fatalities, hospitalizations, amputations, and losses of an eye as a result of contractors’ activities. Or any incident which leads to major property damage (greater than $20,000) and/or may generate publicity or high visibility. These incidents must be investigated and are required to be reported to the VA as soon as practical, but not later than 2 hours after the incident.
E. Medical Treatment. Treatment administered by a physician or by registered professional personnel under the standing orders of a physician. Medical treatment does not include first aid treatment even through provided by a physician or registered personnel.
1.3 REGULATORY REQUIREMENTS:
A. In addition to the detailed requirements included in the provisions of this contract, comply with 29 CFR 1926, comply with 29 CFR 1910 as incorporated by reference within 29 CFR 1926, comply with ASSE A10.34, and all applicable [federal, state, and local] laws, ordinances, criteria, rules and regulations. Submit matters of interpretation of standards for resolution before starting work. Where the requirements of this specification, applicable laws, criteria, ordinances, regulations, and referenced documents vary, the most stringent requirements govern except with specific approval and acceptance by the
Contracting Officer Representative or Government Designated Authority.
1.4 ACCIDENT PREVENTION PLAN (APP):
A. The APP (aka Construction Safety & Health Plan) shall interface with the Contractor's overall safety and health program. Include any portions of the Contractor's overall safety and health program referenced in the APP in the applicable APP element and ensure it is
O.R. Anesthesia Supply Heads
603-17-801
01 35 26 -5 site-specific. The Government considers the Prime Contractor to be the
"controlling authority" for all worksite safety and health of each subcontractor(s). Contractors are responsible for informing their subcontractors of the safety provisions under the terms of the contract and the penalties for noncompliance, coordinating the work to prevent one craft from interfering with or creating hazardous working conditions for other crafts, and inspecting subcontractor operations to ensure that accident prevention responsibilities are being carried out.
B. The APP shall be prepared as follows:
1. Written in English by a qualified person who is employed by the
Prime Contractor articulating the specific work and hazards pertaining to the contract (model language can be found in ASSE
A10.33). Specifically articulating the safety requirements found within these VA contract safety specifications.
2. Address both the Prime Contractors and the subcontractors work operations.
3. State measures to be taken to control hazards associated with materials, services, or equipment provided by suppliers.
4. Address all the elements/sub-elements and in order as follows:
a. SIGNATURE SHEET. Title, signature, and phone number of the following:
1) Plan preparer (Qualified Person such as corporate safety staff person or contracted Certified Safety Professional with construction safety experience);
2) Plan approver (company/corporate officers authorized to obligate the company);
3) Plan concurrence (e.g., Chief of Operations, Corporate Chief of Safety, Corporate Industrial Hygienist, project manager or superintendent, project safety professional). Provide concurrence of other applicable corporate and project personnel (Contractor).
b. BACKGROUND INFORMATION. List the following:
1) Contractor;
2) Contract number;
3) Project name;
4) Brief project description, description of work to be performed, and location; phases of work anticipated (these will require an AHA).
O.R. Anesthesia Supply Heads
603-17-801
01 35 26 -6
c. STATEMENT OF SAFETY AND HEALTH POLICY. Provide a copy of current corporate/company Safety and Health Policy Statement, detailing commitment to providing a safe and healthful workplace for all employees. The Contractor’s written safety program goals, objectives, and accident experience goals for this contract should be provided.
d. RESPONSIBILITIES AND LINES OF AUTHORITIES. Provide the following:
1) A statement of the employer’s ultimate responsibility for the implementation of his SOH program;
2) Identification and accountability of personnel responsible for safety at both corporate and project level. Contracts specifically requiring safety or industrial hygiene personnel shall include a copy of their resumes.
3) The names of Competent and/or Qualified Person(s) and proof of competency/qualification to meet specific OSHA
Competent/Qualified Person(s) requirements must be attached.;
4) Requirements that no work shall be performed unless a designated competent person is present on the job site;
5) Requirements for pre-task Activity Hazard Analysis (AHAs);
6) Lines of authority;
7) Policies and procedures regarding noncompliance with safety requirements (to include disciplinary actions for violation of safety requirements) should be identified;
e. SUBCONTRACTORS AND SUPPLIERS. If applicable, provide procedures for coordinating SOH activities with other employers…