This document is a Questions and Answers (Q&A) file addressing clarifications to a federal contract solicitation. The file resolves two key discrepancies identified by prospective offerors.

The first clarification addresses conflicting invoice submission requirements between two sections of the solicitation. Section B.1, Contract Administration Data, specified bi-weekly invoice submission in arrears, while Section B.2, Performance Work Statement, required monthly invoice submission in arrears through Tungsten. The government clarified that monthly invoice submission through Tungsten will control the awarded contract. The second clarification addresses the contract term and option period structure. The solicitation established a base year beginning April 1, 2027, with four one-year option periods extending through March 31, 2032 (totaling five years); however, FAR 52.217-9, Option to Extend the Term of the Contract, paragraph (c), initially limited total contract duration to one year. The government confirmed this provision will be revised to reflect the anticipated five-year period by amending paragraph (c) to state: "The total duration of this contract, including the exercise of any options under this clause, shall not exceed five (5) years."

View the file

Other files

File Type Posted
36C24827Q0064 0002.docx DOCX document
36C24827Q0064 0001.docx DOCX document
Attch 2 Revised PWS Sections.pdf PDF
Attch 1 Solicitation Questions and Answers Final.pdf PDF
36C24827Q0064.docx DOCX document
Attch 1 Past Performance Survey.pdf PDF
Attch 2 Inspection Checklist.xlsx XLSX spreadsheet

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Q1. Section B.1, Contract Administration Data, indicates invoices will be submitted in arrears bi-weekly.

Section B.2, Performance Work Statement, states invoices shall be submitted monthly in arrears through Tungsten. Which invoice frequency will control the awarded contract?

A1. Monthly. Invoices shall be submitted monthly in arrears through Tungsten.

Q2. Section B.2 and the price schedule establish a base year beginning April 1, 2027, and four one-year option periods (through March 31, 2032). However, FAR 52.217-9, Option to Extend the Term of the Contract, paragraph (c), states the total duration of the contract, including options, shall not exceed one year. Will this provision be corrected to reflect the anticipated base period plus four option years?

A2. Yes. FAR 52.217-9, paragraph (c), is revised as follows:

"(c) The total duration of this contract, including the exercise of any options under this clause, shall not exceed five (5) years."

File details come from the government source that posted it. Updated .